Somali Urban Investment Planning

Abstract*

The development objective of the Urban Investment Planning Project for Somali is to provide: (i) an assessment of the feasibility of, and preliminary plans for, selected urban investment, and institutional strengthening activities in southern Somalia, Puntland, and Somaliland, and (ii) enhanced project preparation and implementation capacity of participating agencies. The project comprises of four components. The first component is Mogadishu. For...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To provide: (i) an assessment of the feasibility of, and preliminary plans for, selected urban investment and institutional strengthening activities in targeted cities, and (ii) enhanced project preparation and implementation capacity of participating agencies.

Key Details

Project Details

  • P150374

  • Closed

  • Makiko Watanabe

  • Ministry of Finance

  • Somalia

  • November 27, 2015

  • (as of board presentation)

    February 4, 2016

  • July 29, 2016

  • US$ 6.00 million

  • Baidoa Municipality,Kismayo Municipality,Mogadishu Municipality

  • Eastern and Southern Africa

  • 2016

  • US$ 6.00 million

  • B

  • Not Applicable

  • December 31, 2021

  • Yes

  • BANK APPROVED

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Somalia Multi-Partner Fund 6.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 6.00
Total Project Cost** 6.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2021-07-07
Monitoring and Evaluation Satisfactory 2021-07-07
Overall Implementation Progress (IP) Satisfactory 2021-07-07
Procurement Moderately Satisfactory 2021-07-07
Project Management Satisfactory 2021-07-07
Financial Management Moderately Satisfactory 2021-07-07

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-24-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Feasibility, preliminary design, and detailed design studies for specific urban investments: secondary roads in Kismayo and BaidoaValue0.005.000.00
    DateAugust 28, 2015December 31, 2021
    Comment
  • Institutional assessments of participating agenciesValue0.005.000.00
    DateAugust 28, 2015December 31, 2021
    Comment
  • Project implementation units established in targeted citiesValue0.005.000.00
    DateAugust 28, 2015December 31, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Contracting for Feasibility Studies and Institutional AssessmentsValue0.004.000.00
    DateMarch 1, 2016December 31, 2021
    Comment
  • Establishment of Project Implementation Units (PIUs) in target citiesValue0.005.000.00
    DateMarch 1, 2016December 31, 2021
    Comment