Tanzania: Resilient Natural Resource Management for Tourism and Growth

Abstract*

The development objective of Resilient Natural Resource Management for Tourism and Growth Project for Tanzania is to improve management of natural resources and tourism assets in priority areas of Southern Tanzania and to increase access to alternative livelihood activities for targeted communities. This project has four components. 1) The first component, Strengthen management and improve infrastructure in priority Protected Areas, has the following...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve management of natural resources and tourism assets in priority areas of Southern Tanzania and to increase access to alternative livelihood activities for targeted communities

Key Details

Project Details

  • P150523

  • Closed

  • Makiko Watanabe , Mirko Serkovic, Nicholas Soikan

  • Ministry of Finance, United Republic of Tanzania

  • Tanzania

  • July 11, 2017

  • (as of board presentation)

    September 28, 2017

  • June 6, 2018

  • US$ 150.00 million

  • Ministry of Natural Resources and Tourism

  • Eastern and Southern Africa

  • 2018

  • US$ 150.00 million

  • B

  • January 31, 2024

  • November 6, 2024

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 150.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 150.00
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 150.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2021 IDA-61430 Int Charges 43,070.48
Dec 15, 2021 IDA-61430 Int Charges 43,070.48
Jan 18, 2022 IDA-61430 Loan Disb 171,877.95
Jun 15, 2020 IDA-61430 Int Charges 30,114.05
Jun 15, 2020 IDA-61430 Int Charges 30,114.05
Feb 27, 2024 IDA-61430 Loan Disb 22,521,718.00
Feb 26, 2024 IDA-61430 Loan Disb 2,786,311.50
Jan 24, 2024 IDA-61430 Loan Disb 11,215.81
Jun 15, 2024 IDA-61430 Int Charges 59,420.33
Sep 28, 2017 IDA-61430 Loan Commitment 150,000,000.00
Sep 21, 2020 IDA-61430 Loan Disb 38,474.50
Sep 21, 2020 IDA-61430 Loan Disb 79,625.45
Sep 21, 2020 IDA-61430 Loan Disb 62,624.55
Oct 13, 2020 IDA-61430 Loan Disb 339,714.00
Dec 15, 2020 IDA-61430 Int Charges 296.21
Dec 15, 2020 IDA-61430 Int Charges 296.21
Dec 15, 2020 IDA-61430 Int Charges 33,856.42
Dec 15, 2020 IDA-61430 Int Charges 33,856.42
Jan 7, 2021 IDA-61430 Loan Disb 436,001.47
Jun 15, 2021 IDA-61430 Int Charges 640.75
Jun 15, 2021 IDA-61430 Int Charges 640.75
Jun 15, 2021 IDA-61430 Int Charges 36,894.27
Jun 15, 2021 IDA-61430 Int Charges 36,894.27
Aug 30, 2021 IDA-61430 Loan Disb 2,350,000.00
Mar 31, 2020 IDA-61430 Loan Disb 869,436.00
Dec 15, 2019 IDA-61430 Int Charges 149.37
Dec 15, 2019 IDA-61430 Int Charges 149.37
Dec 15, 2019 IDA-61430 Int Charges 28,373.15
Dec 15, 2019 IDA-61430 Int Charges 28,373.15
Feb 21, 2020 IDA-61430 Loan Disb 23,892.09
Jun 15, 2020 IDA-61430 Int Charges 365.29
Jun 15, 2020 IDA-61430 Int Charges 365.29
Dec 15, 2018 IDA-61430 Int Charges 6,263.95
Dec 15, 2018 IDA-61430 Int Charges 6,263.95
Dec 15, 2018 IDA-61430 Int Charges 16,600.28
Dec 15, 2018 IDA-61430 Int Charges 16,600.28
Jun 15, 2019 IDA-61430 Int Charges 28,465.17
Jun 15, 2019 IDA-61430 Int Charges 28,465.17
Jun 15, 2019 IDA-61430 Int Charges 312.72
Jun 15, 2019 IDA-61430 Int Charges 312.72
Oct 24, 2019 IDA-61430 Loan Disb 59,268.15
Aug 20, 2019 IDA-61430 Loan Disb 13,268.27
Jun 28, 2018 IDA-61430 Loan Disb 3,000,000.00
Jun 19, 2018 IDA-61430 Loan Disb 1,775,897.40
Sep 4, 2018 IDA-61430 Loan Disb 3,000,000.00
Jun 15, 2024 IDA-61430 Int Charges 59,420.33
Jun 15, 2024 IDA-61430 Loan Repay 2,194,660.80
Jun 15, 2024 IDA-61430 Int Charges 273.89
Jun 15, 2024 IDA-61430 Int Charges 273.89
Jun 15, 2024 IDA-61430 Int Charges 411,578.25
Jun 15, 2024 IDA-61430 Int Charges 411,578.25
Jun 15, 2023 IDA-61430 Int Charges 232,063.10
Jun 15, 2023 IDA-61430 Int Charges 232,063.10
Jun 15, 2023 IDA-61430 Int Charges 9,706.60
Jun 15, 2023 IDA-61430 Int Charges 9,706.60
May 11, 2021 IDA-61430 Loan Disb 3,392.00
May 11, 2021 IDA-61430 Loan Disb -3,392.00
Jun 15, 2023 IDA-61430 Loan Disb 6,832,110.00
Aug 2, 2023 IDA-61430 Loan Disb 210,236.10
Dec 21, 2023 IDA-61430 Loan Repay 2,226,428.00
Dec 21, 2023 IDA-61430 Int Charges 281,621.22
Dec 21, 2023 IDA-61430 Int Charges 281,621.22
Dec 15, 2023 IDA-61430 Loan Repay 3,615.78
Nov 10, 2023 IDA-61430 Loan Disb 882,234.90
Jun 16, 2023 IDA-61430 Loan Disb 20,352,948.00
Jan 4, 2024 IDA-61430 Loan Disb 11,343.70
Nov 20, 2023 IDA-61430 Loan Disb 7,661,211.00
Nov 1, 2023 IDA-61430 Loan Disb 229,478.33
Oct 6, 2023 IDA-61430 Loan Disb 15,889.50
Jan 29, 2024 IDA-61430 Loan Disb 247,640.50
Dec 15, 2022 IDA-61430 Int Charges 11,227.52
Dec 15, 2022 IDA-61430 Int Charges 11,227.52
Dec 15, 2022 IDA-61430 Int Charges 185,863.83
Dec 15, 2022 IDA-61430 Int Charges 185,863.83
Dec 13, 2022 IDA-61430 Loan Disb 3,058,833.80
Mar 24, 2023 IDA-61430 Loan Disb 125,414.01
Apr 5, 2023 IDA-61430 Loan Disb 661,514.30
Jan 23, 2023 IDA-61430 Loan Disb 588,550.30
Oct 15, 2021 IDA-61430 Loan Disb 3,617,244.80
Aug 20, 2021 IDA-61430 Loan Disb 545,664.70
Apr 21, 2022 IDA-61430 Loan Disb 3,754,820.20
May 24, 2022 IDA-61430 Loan Disb 342,107.50
Jun 23, 2022 IDA-61430 Loan Disb 8,527,490.00
Apr 22, 2022 IDA-61430 Loan Disb 7,280,007.50
May 26, 2022 IDA-61430 Loan Disb 111,249.90
May 26, 2022 IDA-61430 Loan Disb 189,141.67
May 26, 2022 IDA-61430 Loan Disb 122,750.19
May 26, 2022 IDA-61430 Loan Disb 479,620.80
Jun 15, 2022 IDA-61430 Int Charges 61,585.39
Jun 15, 2022 IDA-61430 Int Charges 61,585.39
Jun 15, 2022 IDA-61430 Int Charges 3,816.09
Jun 15, 2022 IDA-61430 Int Charges 3,816.09
Jun 15, 2022 IDA-61430 Loan Disb 250,046.39
Jun 14, 2022 IDA-61430 Loan Disb 6,191,256.00
May 5, 2022 IDA-61430 Loan Disb 131,069.87
Jun 17, 2022 IDA-61430 Loan Disb 8,527,489.00
Jun 17, 2022 IDA-61430 Loan Disb 317,701.66
May 24, 2022 IDA-61430 Loan Disb 250,046.39
May 10, 2022 IDA-61430 Loan Disb 79,088.57
Dec 5, 2022 IDA-61430 Loan Disb 5,591,593.00
Dec 30, 2021 IDA-61430 Loan Disb 452,155.60
Dec 21, 2021 IDA-61430 Loan Disb 115,275.00
Dec 15, 2021 IDA-61430 Int Charges 269.49
Dec 15, 2021 IDA-61430 Int Charges 269.49

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2024-06-06
Procurement Moderately Satisfactory 2024-06-06
Project Management Moderately Unsatisfactory 2024-06-06
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-06-06
Progress towards achievement of PDO Moderately Satisfactory 2024-06-06
Monitoring and Evaluation Moderately Satisfactory 2024-06-06

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area of the priority Protected Area (PA) with improved access for basic management supported by the projectValue0.004439.006850.00
    DateDecember 21, 2017December 5, 2023February 26, 2025
    Comment
  • Total tourist visits to the priority PAsValue64000.0098921.00135000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Households with access to alternative livelihood activities supported by the projectValue0.003701.0020000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Land area under sustainable landscape management practicesValue0.004202.0010000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Share of beneficiaries with rating â??Satisfiedâ?? or above on project interventionsValue0.000.0065.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Nyerere National ParkValue0.001515.001500.00
    DateDecember 21, 2017December 6, 2022September 28, 2023
    Comment
  • Mikumi National ParkValue42000.0052474.0071000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • NRM-basedValue0.00649.0015000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • of which femaleValue0.000.0065.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Udzungwa National ParkValue0.000.00350.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Ruaha National ParkValue18961.0011947.0026000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Tourism-basedValue0.002584.005000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • of which youthValue0.000.0065.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Mikumi National ParkValue0.0060.00500.00
    DateDecember 21, 2017December 6, 2023September 28, 2023
    Comment
  • Nyerere National ParkValue18197.0028586200.0026000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Ruaha National ParkValue0.002864.004500.00
    DateDecember 21, 2017December 6, 2023September 28, 2023
    Comment
  • Udzungwa National ParkValue4618.005887.0012000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Access roads rehabilitated inside priority Protected AreasValue0.001606.00982.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Dry season water supply sources constructed by the project in Ruaha National ParkValue0.0046.004.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Scholarships for vocational training in nature conservation and/or tourism hospitality awarded (disaggregated by sex, age (16-29))Value0.001051.00160.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • of which womenValue0.00417.0080.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Nyerere National ParkValue0.00420.00600.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Smallholder farmers trained on the irrigation water use efficient technologies for improving farming and exploitation of water resourcesValue0.006000.0020000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • of which youthValue0.00634.00120.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Ruaha National ParkValue0.001156.00189.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Smallholder agriculture area benefiting from improved irrigation infrastructureValue0.001365.002200.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Households trained by the project in alternative livelihood activities (disaggregated by sex, age (16-29))Value0.003107.0020000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Operational water user associations and irrigators organizations strengthened under the projectValue0.0013.0016.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Mikumi National ParkValue0.0030.00193.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • of which youthValue0.00844.0010000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Airstrips rehabilitated in selected project sitesValue0.007.0015.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Nyerere National ParkValue0.003.006.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • of which womenValue0.002263.0010000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Households trained by the project in reduction of human-wildlife conflictsValue0.00161.006000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Ruaha National ParkValue0.003.008.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Mikumi National ParkValue0.001.001.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Communities using project-promoted techniques to reduce human-wildlife conflict disaggregated by crop-protection and livestock-protection techniqueValue0.00240.005000.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Ranger posts constructed or/and upgraded in priority Protected AreasValue0.000.0015.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Crop-protection techniqueValue0.00201.002500.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Livestock-protection techniqueValue0.0039.002500.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • Udzungwa National ParkValue0.000.001.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Nyerere National ParkValue0.000.005.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Ruaha National ParkValue0.000.007.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Mikumi National ParkValue0.000.002.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Visitor information centers constructed and operational in priority Protected AreasValue0.000.005.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Nyerere National ParkValue0.000.003.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Ruaha National ParkValue0.000.002.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Wildlife census conducted in priority Protected AreasValue0.006.0012.00
    DateDecember 21, 2017December 6, 2023February 26, 2025
    Comment
  • UdzungwaValue0.000.003.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Nyerere National ParkValue0.000.003.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Ruaha National ParkValue0.000.003.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Mikumi National ParkValue0.000.003.00
    DateDecember 21, 2017June 20, 2022September 28, 2023
    Comment
  • Product and Market Development Strategy for Southern Tanzania is developedValueNoNoYes
    DateDecember 21, 2017June 20, 2022February 26, 2025
    Comment
  • Destination management partnership for Southern Tanzania operationalValueNoYesYes
    DateDecember 21, 2017September 20, 2023February 26, 2025
    Comment