Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
P150950
Closed
Abdoulaye Sy , Jean-Luc Bernasconi
Ministry of Finance
October 1, 2015
(as of board presentation)
October 1, 2015
December 23, 2015
US$ 500.00 million
MINISTRY OF INVESTMENT AND INTERNATIONAL COOPERATION
2016
US$ 500.00 million
N/A
Not Applicable
December 31, 2016
BANK APPROVED
August 16, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 500.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 500.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 500.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 500.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2024 | IBRD-85360 | Int Charges | 3,976,617.80 |
Dec 30, 2015 | IBRD-85360 | Loan Disb | 496,389,664.00 |
Oct 1, 2015 | IBRD-85360 | Loan Commitment | 500,000,000.00 |
Sep 15, 2023 | IBRD-85360 | Int Charges | 3,890,812.50 |
Mar 15, 2023 | IBRD-85360 | Int Charges | 3,880,041.20 |
Mar 15, 2022 | IBRD-85360 | Int Charges | 4,098,974.00 |
Mar 15, 2022 | IBRD-85360 | Loan Repay | 10,018,267.00 |
Sep 15, 2022 | IBRD-85360 | Int Charges | 3,643,985.50 |
Sep 15, 2021 | IBRD-85360 | Int Charges | 239,441.17 |
Sep 15, 2021 | IBRD-85360 | Int Charges | 3,633,968.80 |
Sep 15, 2021 | IBRD-85360 | Loan Repay | 10,774,852.00 |
Apr 16, 2021 | IBRD-85360 | Loan Disb | -546,098,940.00 |
Apr 16, 2021 | IBRD-85360 | Loan Disb | 546,098,940.00 |
Apr 16, 2021 | IBRD-85360 | Loan Disb | -546,098,940.00 |
Apr 16, 2021 | IBRD-85360 | Loan Disb | 546,098,940.00 |
Mar 15, 2021 | IBRD-85360 | Int Charges | 1,475,424.00 |
Sep 15, 2020 | IBRD-85360 | Int Charges | 1,468,278.00 |
Mar 15, 2020 | IBRD-85360 | Int Charges | 1,490,426.40 |
Sep 15, 2019 | IBRD-85360 | Int Charges | 1,988,312.90 |
Mar 15, 2019 | IBRD-85360 | Int Charges | 1,840,560.20 |
Sep 15, 2018 | IBRD-85360 | Int Charges | 1,879,725.00 |
Mar 15, 2018 | IBRD-85360 | Int Charges | 1,925,216.90 |
Sep 15, 2017 | IBRD-85360 | Int Charges | 1,947,627.90 |
Mar 15, 2017 | IBRD-85360 | Int Charges | 1,727,471.40 |
Sep 15, 2016 | IBRD-85360 | Int Charges | 1,936,257.40 |
Mar 15, 2016 | IBRD-85360 | Int Charges | 100,232.16 |
Mar 15, 2016 | IBRD-85360 | Int Charges | 938,248.44 |
Dec 23, 2015 | IBRD-85360 | Loan Disb | 1,244,767.60 |
Dec 23, 2015 | IBRD-85360 | Fee Charges | 1,244,767.60 |
Mar 15, 2024 | IBRD-85360 | Loan Repay | 14,882,552.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2016-12-06 |
Monitoring and Evaluation | Moderately Satisfactory | 2016-12-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2016-12-06 |
Program Management | Moderately Satisfactory | 2016-12-06 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-01-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Unsatisfactory |
Government Performance | Moderately Unsatisfactory |
Implementing Agency | Moderately Unsatisfactory |
INDICATOR | ICR REVIEW: 01-21-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Not Rated | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Quantitative Estimate of Compliance Cost Savings (in US$) | Value | 0.00 | 0.00 | 30000000.00 |
Date | May 30, 2014 | September 30, 2016 | June 30, 2015 | |
Comment |
Number of Staff at Tunisie Telecom that have Taken Up the Early Retirement Plan | Value | 0.00 | 1300.00 | 3000.00 |
Date | May 30, 2014 | September 30, 2016 | December 31, 2016 | |
Comment |
Number of broadband wholesale access | Value | 0.00 | 0.00 | 15000.00 |
Date | May 30, 2014 | December 31, 2015 | December 31, 2016 | |
Comment |
Restructuring plans for STB, BNA and BH approved by their respective Board of Directors | Value | 0.00 | 3.00 | 3.00 |
Date | December 31, 2014 | April 1, 2016 | December 31, 2016 | |
Comment |
Common equity tier-1 ratio the three state-owned banks STB, BH and BNA | Value | STB (-5.7 %), BH (4.6 %) and BNA (6.3 %) | STB (9%); BH (7.5%) and BNA (6.8%) | STB, BH and BNA (1.7^%) |
Date | December 31, 2014 | June 30, 2016 | December 31, 2016 | |
Comment |
Publication of the annual report on the finances of State-Owned Banks for the period 2010-2012 | Value | No publication | The reports on the finances on State-Owned Enterpr | The reports have been published in 2015 and 2016. |
Date | December 31, 2014 | April 1, 2016 | December 31, 2016 | |
Comment |
Number of access to information requests that have been responded to | Value | 80.00 | 2606.00 | 120.00 |
Date | December 31, 2015 | September 30, 2016 | December 31, 2016 | |
Comment |