Skip to Main Navigation

Inclusive Housing Finance Program

Abstract*

The project development objective of the Inclusive Housing Finance Program-for-Results is to improve the affordability of formal housing for low-income households in the Arab Republic of Egypt and to strengthen the Social Housing Fund's capacity to design policies and coordinate programs in the social housing sector. The SHF has the mandate to finance, manage and release social housing units using dedicated resources from multiple sources, and provide...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Program is to improve the affordability of formal housing for low-income households in the Arab Republic of Egypt and to strengthen the SHMFF's capacity to design policies and coordinate programs in the social housing sector.

Key Details

Project Details

  • P150993

  • Active

  • Laila Ahmed , Rinku Chandra, Alia Eldidi

  • Arab Republic of Egypt

  • Egypt, Arab Republic of

  • January 29, 2015

  • (as of board presentation)

    May 5, 2015

  • November 11, 2015

  • US$ 500.00 million

  • Social Housing and Mortgage Finance Fund

  • Middle East and North Africa

  • 2015

  • US$ 1000.00 million

  • N/A

  • March 20, 2024

  • December 31, 2025

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 1000.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 1000.00
IDA Commitment N/A
IBRD + IDA Commitment 1000.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 500.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 15, 2022 IBRD-84980 Loan Repay 6,889,079.00
Jul 15, 2022 IBRD-84980 Int Charges 112,037.49
Apr 1, 2023 IBRD-90330 Int Charges 642,455.00
Apr 4, 2023 IBRD-90330 Loan Disb 10,642,628.00
Apr 1, 2023 IBRD-90330 Int Charges 351,300.90
Apr 1, 2023 IBRD-90330 Int Charges 29,320.53
Apr 1, 2023 IBRD-90330 Int Charges 5,775,433.00
Oct 1, 2022 IBRD-90330 Int Charges 429,119.56
Oct 1, 2022 IBRD-90330 Int Charges 2,006,726.40
Jan 15, 2023 IBRD-84980 Int Charges 436,790.38
Jan 15, 2023 IBRD-84980 Int Charges 113,462.05
Jan 15, 2023 IBRD-84980 Int Charges 8,395,618.00
Jan 15, 2023 IBRD-84980 Loan Repay 6,896,351.50
Jul 15, 2023 IBRD-84980 Int Charges 497,455.72
Jul 15, 2023 IBRD-84980 Int Charges 111,542.11
Jul 15, 2023 IBRD-84980 Int Charges 10,759,849.00
Jul 15, 2023 IBRD-84980 Loan Repay 6,896,351.50
Oct 1, 2023 IBRD-90330 Int Charges 126,508.52
Oct 1, 2023 IBRD-90330 Int Charges 340,110.06
Oct 1, 2023 IBRD-90330 Int Charges 7,444,110.00
Jan 15, 2024 IBRD-84980 Int Charges 158,673.19
Dec 1, 2020 IBRD-90330 Loan Disb 116,000,000.00
Jan 15, 2021 IBRD-84980 Loan Repay 6,245,506.50
Jan 15, 2021 IBRD-84980 Int Charges 21,381.52
Jan 15, 2021 IBRD-84980 Int Charges 226,430.19
Jan 15, 2021 IBRD-84980 Int Charges 159,574.60
Jan 15, 2021 IBRD-84980 Int Charges 2,518,250.50
Jul 15, 2021 IBRD-84980 Int Charges 157,370.10
Jul 15, 2021 IBRD-84980 Int Charges 2,307,907.20
Jul 15, 2021 IBRD-84980 Loan Repay 6,245,506.50
Apr 1, 2021 IBRD-90330 Int Charges 606,920.70
Apr 1, 2021 IBRD-90330 Int Charges 663,010.80
Aug 26, 2021 IBRD-84980 Loan Disb 36,566,616.00
Oct 1, 2021 IBRD-90330 Int Charges 458,440.10
Oct 1, 2021 IBRD-90330 Int Charges 982,710.00
Jan 15, 2020 IBRD-84980 Int Charges 10,905.41
Jan 15, 2020 IBRD-84980 Int Charges 159,812.64
Jan 15, 2020 IBRD-84980 Int Charges 224,603.48
Jul 15, 2016 IBRD-84980 Int Charges 464,634.56
Jul 15, 2016 IBRD-84980 Int Charges 1,104,196.50
Nov 11, 2015 IBRD-84980 Loan Disb 1,250,000.00
Nov 11, 2015 IBRD-84980 Fee Charges 1,250,000.00
Jan 15, 2017 IBRD-84980 Int Charges 469,838.34
Jan 15, 2017 IBRD-84980 Int Charges 1,219,575.00
Dec 4, 2020 IBRD-90330 Loan Disb 17,000,000.00
Jul 15, 2020 IBRD-84980 Int Charges 200,219.69
Jul 15, 2020 IBRD-84980 Int Charges 4,635,808.50
Jul 15, 2020 IBRD-84980 Loan Repay 5,373,141.00
Jan 15, 2019 IBRD-84980 Int Charges 228,097.34
Jan 15, 2019 IBRD-84980 Int Charges 304,913.97
Jan 15, 2019 IBRD-84980 Int Charges 4,616,360.00
May 16, 2018 IBRD-84980 Loan Disb 52,771,304.00
Jan 15, 2019 IBRD-84980 Int Charges 21,686.83
Jun 20, 2019 IBRD-84980 Loan Disb 63,687,568.00
Jul 15, 2019 IBRD-84980 Int Charges 289,037.12
Jul 15, 2019 IBRD-84980 Int Charges 5,008,177.50
Jul 15, 2017 IBRD-84980 Int Charges 463,347.62
Jul 15, 2017 IBRD-84980 Int Charges 1,440,898.20
Aug 11, 2017 IBRD-84980 Loan Disb 79,036,096.00
Jan 15, 2018 IBRD-84980 Int Charges 2,385,810.80
Jan 15, 2018 IBRD-84980 Int Charges 386,036.53
Jul 15, 2018 IBRD-84980 Int Charges 343,677.66
Jul 15, 2018 IBRD-84980 Int Charges 2,931,257.20
Dec 21, 2015 IBRD-84980 Loan Disb 125,000,000.00
Jul 15, 2016 IBRD-84980 Int Charges 522,462.00
Jul 15, 2016 IBRD-84980 Int Charges 116,671.86
Mar 20, 2020 IBRD-90330 Loan Commitment 500,000,000.00
May 5, 2015 IBRD-84980 Loan Commitment 500,000,000.00
Jan 15, 2024 IBRD-84980 Int Charges 113,367.31
Jan 15, 2024 IBRD-84980 Int Charges 12,444,798.00
Jan 15, 2024 IBRD-84980 Loan Repay 6,896,351.50
Apr 1, 2024 IBRD-90330 Int Charges 119,609.09
Apr 1, 2024 IBRD-90330 Int Charges 339,429.62
Apr 1, 2024 IBRD-90330 Int Charges 8,139,452.00
Jul 15, 2024 IBRD-84980 Int Charges 78,041.10
Jul 15, 2024 IBRD-84980 Int Charges 111,851.92
Jul 15, 2024 IBRD-84980 Int Charges 12,274,987.00
Jul 15, 2024 IBRD-84980 Loan Repay 6,896,351.50
Apr 1, 2022 IBRD-90330 Int Charges 455,934.94
Apr 1, 2022 IBRD-90330 Int Charges 943,404.56
Jan 15, 2022 IBRD-84980 Int Charges 124,413.63
Jan 15, 2022 IBRD-84980 Int Charges 2,312,426.50
Jan 15, 2022 IBRD-84980 Loan Repay 6,889,079.00
Aug 10, 2022 IBRD-84980 Loan Disb 399,600.00
Aug 11, 2022 IBRD-90330 Loan Disb 83,937,184.00
Jul 15, 2022 IBRD-84980 Int Charges 2,784,255.50
Jan 15, 2020 IBRD-84980 Int Charges 5,262,317.50
Oct 27, 2020 IBRD-90330 Loan Disb 1,250,000.00
Oct 27, 2020 IBRD-90330 Fee Charges 1,250,000.00
May 15, 2020 IBRD-84980 Loan Disb 51,315,624.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-11-05
Monitoring and Evaluation Moderately Satisfactory 2024-11-05
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-05

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1.1 Number of targeted households accessing ownership and rental housing units with support from the ProgramValue0.00567777.001052400.00
    DateApril 1, 2015May 2, 2024December 31, 2024
    Comment
  • 1.2 female-headed households as a percentage of benefeciariesValue0.0023.6024.00
    DateApril 1, 2015April 29, 2018June 30, 2020
    Comment
  • 2. Percentage of Program beneficiaries in bottom 20% of the income distributionValue0.0084.0050.00
    DateApril 1, 2015May 2, 2024December 31, 2024
    Comment
  • 3. Percentage of income spent on housing costs by Program beneficiariesValue0.0041.5030.00
    DateApril 1, 2015May 2, 2024December 31, 2024
    Comment
  • 4. Establishment of a housing M&E system functioning and informing the Multi-Year Plan and Annual TargetsValueNoYesYes
    DateApril 1, 2015May 2, 2024December 31, 2024
    Comment
  • 5. Development, adoption and implementation of an alternative system that progressively phases out the interest rate subsidyValueNoNoYes
    DateMay 31, 2019May 2, 2024December 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1.1. Completed executive by-laws, organizational structure, financing model, fiduciary arrangements, operating systems for the SHMFFValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.1. Mechanism to monitor occupancy of housing post-subsidy established and functioning as per DLI definitionValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 5.1. Number of demand-side subsidies supporting the purchase or rental of housing units developed by the private sectorValue0.002697.00250000.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 4.1. Percent of demand-side subsidies supporting the purchase or rental of housing units within a 60 minute travel time to an employment centerValue0.00100.0050.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 3.1. Number of households receiving demand side home ownership subsidies for new units under the AMPValue0.00564072.00950000.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 1.2. SHMFF fully staffed as per organizational planValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 3.1.1. Female- headed households as percentage of beneficiariesValue0.0023.600.00
    Date
    Comment
  • 5.2. PPP guidelines publicly disseminatedValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.2. Percentage of rental housing units occupied by targeted beneficiaries at least 1 year after leaseValue0.0093.3375.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 4.2. Percent of demand-side subsidies supporting the purchase or rental of housing units within a 45 minute travel time to an employment centerValue0.00100.0050.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 1.3. Internal audit function providing assurance services for the ownership and rental programs affiliated with the SHMFF established and operatingValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 5.3. Percentage of demand side subsidy supporting the purchase or rental of housing units developed by private sectorValue0.000.4843.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.3. Percentage of ownership housing units occupied by low-income households after at least 1 year of receiving subsidies under theAMPValue0.0093.3385.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 3.2. Number of households participating in rental subsidy programsValue0.003705.00102400.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 4.3. Percent of demand-side subsidies supporting the purchase or rental of housing units within a 30 minute travel time to an employment centerValue0.00100.0015.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 3.2.1. Female-headed households as percentage of beneficiariesValue0.000.000.00
    Date
    Comment
  • 4.4. Percentage of land made available for SHMFF developments that complies with location and service criteria stated in LawValue0.00100.00100.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.4. Establish a unified social programs and beneficiary databasesValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 1.4. Adequate staffing of social officers per organizational planValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 3.3. Number of previously vacant units occupied 1 year after inclusion into the ProgramValue0.0083071.0030000.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.5. Establishment of a functioning accountability and transparency mechanism in SHMFF as per DLI definitionValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 1.5. Number of capacity building and training workshops conducted for the hired social workers at the Central and Governorate levelValue0.00135.0027.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.6. Average time required to resolve complaints in AMPValue60.0020.0020.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.7. Percentage of resolved complaints received by SHMFFF and Governorate housing officesValue0.0097.0090.00
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment
  • 2.8. Annual published reports on complaints and how issues were resolved, including resolution ratesValueNoYesYes
    DateAugust 10, 2015May 2, 2024December 31, 2024
    Comment