Urban Productive Safety Net Project (UPSNP)

Abstract*

The objective of the Urban Productive Safety Net Project is to support the Government of Ethiopia to improve income of targeted poor households and establish urban safety net mechanisms. There are three components to the project, the first component being safety net support. This component will support the delivery of a predictable, timely, and productive safety net through conditional and unconditional safety net transfers. The project will ensure...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO of the proposed project is to support the Government of Ethiopia to improve income of targeted poor households and establish urban safety net mechanisms

Key Details

Project Details

  • P151712

  • Closed

  • Ayuba Hussein

  • FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA

  • Ethiopia

  • February 6, 2015

  • (as of board presentation)

    December 16, 2015

  • June 29, 2016

  • US$ 450.00 million

  • Ministry of Urban Development and Infrastructure,Ministry of Labor and Skills,Ministry of Women and Social Affairs

  • Eastern and Southern Africa

  • 2016

  • US$ 300.00 million

  • B

  • N/A

  • October 10, 2022

  • Yes

  • BANK APPROVED

  • January 17, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 150.00
IDA Credit 300.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 300.00
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 450.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 15, 2020 IDA-57560 Int Charges 577,073.44
Feb 26, 2019 IDA-57560 Loan Disb 58,936,620.00
Jul 15, 2019 IDA-57560 Int Charges 530,467.40
Jul 15, 2019 IDA-57560 Int Charges 530,467.40
Jul 15, 2019 IDA-57560 Int Charges 3,172.61
Sep 12, 2018 IDA-57560 Loan Disb 14,862,243.00
Nov 5, 2018 IDA-57560 Loan Disb 14,512,169.00
Jan 15, 2019 IDA-57560 Int Charges 310,425.03
Jul 20, 2023 IDA-57560 Loan Repay 4,534,461.50
Jul 20, 2023 IDA-57560 Int Charges 463.03
Jul 20, 2023 IDA-57560 Int Charges 463.03
Jan 15, 2022 IDA-57560 Int Charges 1,029,448.60
Sep 22, 2022 IDA-57560 Loan Disb 10,465.70
Jan 20, 2023 IDA-57560 Loan Repay 4,435,822.50
Jan 20, 2023 IDA-57560 Int Charges 918,621.90
Jan 20, 2023 IDA-57560 Int Charges 918,621.90
Jul 15, 2022 IDA-57560 Loan Repay 4,394,371.50
Jul 15, 2022 IDA-57560 Int Charges 1,033,727.30
Jul 15, 2022 IDA-57560 Int Charges 1,033,727.30
Jul 15, 2022 IDA-57560 Int Charges 11,313.47
Jul 15, 2022 IDA-57560 Int Charges 11,313.47
Jan 15, 2022 IDA-57560 Int Charges 1,029,448.60
Jan 31, 2022 IDA-57560 Loan Disb 14,977,403.00
Jan 15, 2022 IDA-57560 Loan Repay 9,785.64
Jan 15, 2022 IDA-57560 Loan Repay 4,715,478.50
Jul 15, 2021 IDA-57560 Int Charges 12,771.62
Jul 15, 2021 IDA-57560 Int Charges 12,771.62
Jul 15, 2021 IDA-57560 Int Charges 974,510.75
Jul 15, 2021 IDA-57560 Int Charges 974,510.75
Oct 27, 2021 IDA-57560 Loan Disb 15,504,100.00
Jan 15, 2021 IDA-57560 Int Charges 872,430.60
Jan 15, 2021 IDA-57560 Int Charges 872,430.60
Jan 15, 2021 IDA-57560 Int Charges 18,471.33
Jan 15, 2021 IDA-57560 Int Charges 18,471.33
Mar 5, 2021 IDA-57560 Loan Disb 14,493,050.00
Jul 27, 2021 IDA-57560 Loan Disb 11,111,468.00
Jul 23, 2020 IDA-57560 Int Charges 2,953.53
Jul 23, 2020 IDA-57560 Int Charges 2,953.53
Jul 23, 2020 IDA-57560 Int Charges 660,188.30
Jul 23, 2020 IDA-57560 Int Charges 660,188.30
Apr 17, 2020 IDA-57560 Loan Disb 48,953,796.00
Sep 29, 2020 IDA-57560 Loan Disb 38,289,960.00
Jul 15, 2019 IDA-57560 Int Charges 3,172.61
Jan 15, 2020 IDA-57560 Int Charges 928.16
Jan 15, 2020 IDA-57560 Int Charges 928.16
Jan 15, 2020 IDA-57560 Int Charges 577,073.44
Jan 15, 2019 IDA-57560 Int Charges 310,425.03
Jan 15, 2019 IDA-57560 Int Charges 13,164.15
Jan 15, 2019 IDA-57560 Int Charges 13,164.15
Jan 16, 2018 IDA-57560 Loan Disb 21,710,742.00
Jan 15, 2018 IDA-57560 Int Charges 120,605.10
Jan 15, 2018 IDA-57560 Int Charges 120,605.10
Jan 15, 2018 IDA-57560 Int Charges 11,218.28
Jan 15, 2018 IDA-57560 Int Charges 11,218.28
May 23, 2018 IDA-57560 Loan Disb 15,189,250.00
Jul 17, 2018 IDA-57560 Int Charges 1,832.91
Jul 17, 2018 IDA-57560 Int Charges 1,832.91
Jul 17, 2018 IDA-57560 Int Charges 202,471.55
Jul 17, 2018 IDA-57560 Int Charges 202,471.55
Jul 24, 2017 IDA-57560 Int Charges 18,488.14
Jul 24, 2017 IDA-57560 Int Charges 18,488.14
Jul 24, 2017 IDA-57560 Int Charges 87,304.97
Jul 24, 2017 IDA-57560 Int Charges 87,304.97
Jun 29, 2016 IDA-57560 Loan Disb 3,377,802.50
Jan 15, 2017 IDA-57560 Int Charges 1,089.93
Jan 15, 2017 IDA-57560 Int Charges 1,089.93
Jan 15, 2017 IDA-57560 Int Charges 12,383.40
Nov 22, 2016 IDA-57560 Loan Disb 16,280,452.00
Jan 15, 2017 IDA-57560 Int Charges 12,383.40
May 15, 2017 IDA-57560 Loan Disb 6,593,044.00
Mar 1, 2017 IDA-57560 Loan Disb 4,783,896.50
Jan 15, 2024 IDA-57560 Int Charges 35,040.02
Jan 15, 2024 IDA-57560 Int Charges 35,040.02
Jan 15, 2024 IDA-57560 Loan Repay 4,484,118.00
Jan 15, 2024 IDA-57560 Int Charges 467.10
Jan 15, 2024 IDA-57560 Int Charges 467.10
Jan 15, 2024 IDA-57560 Int Charges 968,788.06
Jan 15, 2024 IDA-57560 Int Charges 968,788.06
Jul 15, 2024 IDA-57560 Int Charges 969,316.20
Jul 15, 2024 IDA-57560 Int Charges 969,316.20
Jul 15, 2024 IDA-57560 Int Charges 39,874.35
Jul 15, 2024 IDA-57560 Int Charges 39,874.35
Jul 15, 2024 IDA-57560 Loan Repay 4,454,616.50
Dec 16, 2015 IDA-57560 Loan Commitment 300,000,000.00
Jan 15, 2023 IDA-57560 Loan Repay 89,153.67
Jul 20, 2023 IDA-57560 Int Charges 1,001,824.60
Jul 20, 2023 IDA-57560 Int Charges 1,001,824.60
Jul 20, 2023 IDA-57560 Int Charges 133,696.90
Jul 20, 2023 IDA-57560 Int Charges 133,696.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2022-04-21
Project Management Satisfactory 2022-04-21
Monitoring and Evaluation Moderately Satisfactory 2022-04-21
Overall Implementation Progress (IP) Satisfactory 2022-04-21
Progress towards achievement of PDO Satisfactory 2022-04-21
Financial Management Moderately Satisfactory 2022-04-21
Counterpart Funding Satisfactory 2022-04-21
Overall Safeguards Rating Moderately Satisfactory 2022-04-21

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 04-27-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-16-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Livelihood Services beneficiaries that secured a new job or set up/expand a business and are still in the new job/operating the business 12 months later.Value0.0025.000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Participating urban local governments reporting improved capacity to deliver safety net and livelihood services as a result of program support.Value0.0011.006.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Direct project beneficiariesValue0.00465600.00304000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Female beneficiariesValue0.0061.0050.00
    DateJanuary 29, 2016May 30, 2018
    Comment
  • Beneficiaries that feel project investments reflected their needs (percentage)Value0.0070.0055.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries that feel project inv. reflected their needs - female (number)Value0.000.0083600.00
    DateJanuary 29, 2016May 31, 2018
    Comment
  • Total beneficiaries - female (number)Value0.00273819.00152000.00
    DateJanuary 29, 2016May 31, 2018
    Comment
  • Total beneficiaries - male (number)Value0.00175065.00152000.00
    DateJanuary 29, 2016May 31, 2018
    Comment
  • Total beneficiaries - male (number)Value0.00175065.00152000.00
    DateJanuary 29, 2016May 31, 2018
    Comment
  • Beneficiaries that feel project inv. reflected their needs - male (number)Value0.000.0083600.00
    DateJanuary 29, 2016May 31, 2018
    Comment
  • Project beneficiaries under the national poverty lineValue0.0075.0070.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Project beneficiaries reporting increased household consumption as a result of the projectValue0.0080.0050.00
    DateJanuary 29, 2016October 10, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries of Safety Nets programs (number)Value0.00465600.00304000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries receiving guidance/information on employment opportunitiesValue0.0080000.0025000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Federal institutions and cities where the project management and coordination arrangements are established and functionalValue0.0090.0050.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries of Safety Nets programs - Female (number)Value0.00237456.00152000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries reporting receiving satisfactory information on entrepreneurship opportunities, availability of wage jobs, and training available to meet identified skill needsValue0.0070.0040.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Establishment of functional M&E/MIS system at the Federal and city levels (yes/no)ValueNoYesYes
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Complaints to Woreda/Kebele Targeting Appeals Committee satisfactorily addressed within 3 months of initial complaint being recorded.Value0.0090.0070.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries receiving appropriate training that received a livelihood grantValue0.0080.0065.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries of Safety Nets programs - Unconditional cash transfers (number)Value0.0074496.0048640.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Ketenas in which community-based targeting is verified to acceptable levels in the PMT verification processValue0.0090.0070.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Training recipients reporting improved skills as a result of the training provided by the projectValue0.0070.0060.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number)Value0.00391104.00255360.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Number of project implementation staff trained on various aspects of the project at all levelsValue0.00850.00150.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Businesses with approved business plans that are set up within 6 months of receiving livelihood grant supportValue0.0080.000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Payments delivered to beneficiaries within 15 days of the due dateValue0.0090.0060.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Number of person days of employment createdValue0.0058666.0025536.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Businesses that are still operating 6 months after livelihood grant supportValue0.0050.000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • PW sub-projects identified through community participationValue0.0090.0080.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • New wage jobs held for more than 8 weeks by program beneficiariesValue0.0050.000.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Beneficiaries that are satisfied that the PW projects meets/serves their needsValue0.0080.0060.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • PW days allocated to trainingValue0.0010.004.00
    DateJanuary 29, 2016October 10, 2022
    Comment
  • Infrastructure sub-projects with clear maintenance plan and sustainability measuresValue0.0070.0050.00
    DateJanuary 29, 2016October 10, 2022
    Comment