Dominican Republic. FCPF REDD+ Readiness Preparation Project

Abstract*

The development objective of the Restructuring FCPF REDD+ Readiness Preparation Project in Dominican Republic is to assist the Dominican Republic to design and carry out the Readiness Preparation Activities by supporting the preparation of the Recipient’s REDD+ Strategy through a participatory and inclusive process. The purpose of this restructuring request is for an extension in the Closing Date of the operation. In doing so, the extension will build...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is 'to assist the Dominican Republic to design and carry out the Readiness Preparation Activities by supporting the preparation of the Recipient's REDD+ Strategy through a participatory and inclusive process.'

Key Details

Project Details

  • P151752

  • Closed

  • Philippe Dardel

  • Ministerio de Economía, Planificación y Desarrollo MEPyD

  • Dominican Republic

  • August 27, 2015

  • (as of board presentation)

    September 14, 2015

  • N/A

  • US$ 6.00 million

  • Ministro del Ministerio de Medio Ambiente y Recursos Naturales

  • Latin America and Caribbean

  • 2016

  • US$ 6.00 million

  • B

  • Not Applicable

  • August 15, 2022

  • BANK APPROVED

  • August 10, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
The Forest Carbon Partnership Facility – Readiness Fund 6.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 6.00
Total Project Cost** 6.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • By End of Project (EOP), government institutions have been provided with capacity building support to improve management of forest resources.Value0.003.002.00
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • By Q1, an ENREDD+ strategy including the design of specific legal, economic and technological instruments (i.e. a REDD+ incentives system, regulation of LULUCF related sectors, technological packagesValueNoNoYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q4, a citizen feedback mechanism and institutional protocol will be in place and operational.ValueNoNoYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q1, a national communications and dissemination strategy for REDD+ has been designed and initiates full implementation by Q2.ValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q2, a gender mainstreaming strategy has been designed and incorporated into the national participation and consultation planValueNoNoYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q1, a SESA has been carried out and an appropriate safeguard instrument such as an ESMF has been preparedValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q1, PIU disbursing funds as programmed, and meeting fiduciary commitments as established in the Grant Agreement.ValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By EOP, an exit strategy to ensure continuity of institutional capacity for REDD+ is developed and agreed with ME.ValueNoNoYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By EOP, the capacity and progress to develop a National Forest Monitoring System (NFMS) for the MRV of GHG emissions reductions have been significantly improvedValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q3, the logical framework and required institutional arrangements for MRV have been establishedValueNoNoYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q2, the capacity of the remote sensing, and the GHG Inventory units have been strengthenedValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q2, a research program on forest monitoring has been supported.ValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q4, monitoring protocols to assess the environmental and social impacts of the ENREDD+ have been developed.ValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment
  • By Q1, the National Forest Inventory has been completed; and allometric equations developed for three areas.ValueNoYesYes
    DateOctober 1, 2015November 17, 2020December 31, 2020
    Comment