Mark your calendar for October 13–18 as leaders, experts, and voices from around the world come together for critical conversations on the global economy and development. From live discussions to special events, there’s something for everyone to follow online. Sign up now to receive updates and be the first to know what’s happening throughout the week.

Skip to Main Navigation

Youth Employment and Skills Development - Additional Financing

Development Objective

The proposed Project Development Objective (PDO) is to improve access to temporary employment and skills development opportunities for young men and women in Cote d'Ivoire' s territory.

Key Details

Project Details

  • P151844

  • Closed

  • Waly Wane

  • N/A

  • Cote d'Ivoire

  • February 13, 2015

  • (as of board presentation)

    March 26, 2015

  • N/A

  • US$ 50.00 million

  • B

  • Not Applicable

  • December 31, 2020

  • TBD

  • BANK APPROVED

  • P122546

  • July 17, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 50.00
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of September 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of September 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue25422.0025422.0056922.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Number of additional person days provided in LIPW (disaggregated by gender, district and type of sub-project)Value1564649.001564649.002679649.00
    DateDecember 31, 2015December 31, 2014June 30, 2019
    Comment
  • Completion rate of youth participating in apprenticeship and internship programsValue76.0076.0080.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Female beneficiariesValue0.0032.0030.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Labor Intensive Public Work (LIPW)Value12675.0012675.0025175.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Skills DevelopmentValue12747.0012747.0031747.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Female beneficiariesValue32.0032.0040.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Percentage of youth who are employed or self-employed within six months of completion (internship/retooling)Value0.000.0070.00
    DateJune 30, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehabilitated/maintained (kilometers)Value253725373537 kilometers
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Percentage of total costs going to wage bills (all sub-projects)Value56.0056.0050.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Percentage of LIPW participants' wages paid in a timely manner per 6 months cycleValue100.00100.0095.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Total number of internship/retooling weeks providedValue53342.0053342.00193342.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Number of apprenticeship contracts signedValue0.003914.003000.00
    DateSeptember 15, 2011September 30, 2014June 30, 2015
    Comment
  • Service provider meeting performance indicators specified in contractsValue0.0073.0090.00
    DateSeptember 15, 2011September 30, 2014June 30, 2015
    Comment
  • Number of regular progress reports produced on time by the service providers of component 2 (cumulative)Value0.0054.0030.00
    DateSeptember 15, 2011September 30, 2014June 30, 2015
    Comment
  • Number of business plans submitted by participants of the entrepreneurship training program Component 2, activity (d)Value0.00199.000.00
    DateSeptember 30, 2014
    Comment
  • Contracts with service providers signed on time by the relevant authoritiesValuen/aYesYes
    DateSeptember 15, 2011September 30, 2014June 30, 2015
    Comment
  • Annual work plans, budgets and procurement plans are prepared and submitted to IDA in a timely and satisfactory mannerValuen/aYesYES
    DateSeptember 15, 2011September 30, 2014June 30, 2015
    Comment
  • Number of communications campaigns launchedValue0.005.005.00
    DateSeptember 15, 2011September 30, 2014June 30, 2015
    Comment
  • Youth who have completed Internship/Retooling programValue0.000.0080.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Number of impact evaluation completedValue0.000.002.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Percentage of youth who are employed or self employed within 6 months of completion (apprenticeship/dual training program)Value0.000.0070.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Female beneficiariesValue0.000.0030.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Number of youth enrolled in apprenticeship/dual training programValue4294.004294.0014295.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Percentage of Youth who have completed apprenticeship/Dual training programValue70.0080.0080.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Female beneficiariesValue30.0030.0030.00
    DateDecember 31, 2014December 31, 2014June 30, 2019
    Comment
  • Number of AGRs or micro projects supported by the projectValue0.000.003000.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Number of tracer surveyValue0.000.004.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Number of youth who receive entrepreneurship training programValue2077.000.007077.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Number of public private joint management agreements signed in the centers supported by the projectValue0.000.0010.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Female beneficiariesValue30.000.0030.00
    DateDecember 31, 2014June 30, 2019
    Comment
  • Number of staff trained in impact evaluation (IE) methods.Value0.000.008.00
    DateDecember 31, 2014June 30, 2019
    Comment