Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Borrower/Recipient | 48.15 |
P151851
Closed
Griselle Vega , Martin Albrecht, Zael Sanz Uriarte
REPUBLIC OF PERU
June 14, 2016
(as of board presentation)
April 28, 2017
March 12, 2018
US$ 88.15 million
National Water Authority of the Ministry of Agriculture - Autoridad Nacional del Agua (ANA)
2017
US$ 40.00 million
B
June 24, 2024
December 31, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Borrower/Recipient | 48.15 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 88.15 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 27, 2020 | IBRD-87400 | Loan Disb | 399,547.47 |
Nov 10, 2020 | IBRD-87400 | Loan Disb | 252,294.02 |
Jul 6, 2020 | IBRD-87400 | Loan Disb | 855,246.10 |
Feb 4, 2021 | IBRD-87400 | Loan Disb | -191,946.90 |
Feb 17, 2021 | IBRD-87400 | Loan Disb | 726,068.90 |
Mar 8, 2021 | IBRD-87400 | Loan Disb | 188,403.90 |
Jan 27, 2021 | IBRD-87400 | Loan Disb | 881,285.10 |
Jan 27, 2021 | IBRD-87400 | Loan Disb | 304,006.12 |
Oct 15, 2020 | IBRD-87400 | Int Charges | 3,042.41 |
Oct 5, 2020 | IBRD-87400 | Loan Disb | 308,598.62 |
Oct 15, 2020 | IBRD-87400 | Int Charges | 35,084.57 |
Oct 15, 2020 | IBRD-87400 | Int Charges | 116,900.90 |
Aug 10, 2020 | IBRD-87400 | Loan Disb | 731,059.25 |
Nov 5, 2020 | IBRD-87400 | Loan Disb | 408,291.03 |
Feb 26, 2020 | IBRD-87400 | Loan Disb | 352,292.66 |
Feb 5, 2020 | IBRD-87400 | Loan Disb | 5,000,000.00 |
Apr 15, 2020 | IBRD-87400 | Int Charges | 229.48 |
Apr 15, 2020 | IBRD-87400 | Int Charges | 2,869.70 |
Apr 15, 2020 | IBRD-87400 | Int Charges | 41,720.36 |
Apr 15, 2020 | IBRD-87400 | Int Charges | 87,462.38 |
Sep 25, 2019 | IBRD-87400 | Loan Disb | 996,482.30 |
Dec 18, 2019 | IBRD-87400 | Loan Disb | 681,892.90 |
Mar 12, 2020 | IBRD-87400 | Loan Disb | 815,719.40 |
Dec 4, 2019 | IBRD-87400 | Loan Disb | 973,006.40 |
Oct 15, 2019 | IBRD-87400 | Int Charges | 606.25 |
Oct 15, 2019 | IBRD-87400 | Int Charges | 47,565.60 |
Oct 15, 2019 | IBRD-87400 | Int Charges | 31,627.40 |
Oct 15, 2019 | IBRD-87400 | Int Charges | 48.33 |
Aug 15, 2019 | IBRD-87400 | Loan Disb | 222,539.78 |
Jun 7, 2019 | IBRD-87400 | Loan Disb | 635,482.60 |
Mar 21, 2019 | IBRD-87400 | Loan Disb | 282,210.12 |
Jun 25, 2019 | IBRD-87400 | Loan Disb | 220,184.75 |
Apr 15, 2019 | IBRD-87400 | Int Charges | 48,568.12 |
Apr 15, 2019 | IBRD-87400 | Int Charges | 16,885.55 |
Oct 15, 2018 | IBRD-87400 | Int Charges | 38,904.12 |
Oct 15, 2018 | IBRD-87400 | Int Charges | 49,575.35 |
Oct 15, 2018 | IBRD-87400 | Int Charges | 7,243.34 |
Jul 25, 2018 | IBRD-87400 | Loan Disb | 1,000,000.00 |
May 9, 2018 | IBRD-87400 | Fee Charges | 100,000.00 |
Feb 15, 2024 | IBRD-87400 | Loan Cancel | 3,952.34 |
Apr 28, 2017 | IBRD-87400 | Loan Commitment | 40,000,000.00 |
Apr 15, 2024 | IBRD-87400 | Int Charges | 272,260.16 |
Apr 15, 2024 | IBRD-87400 | Loan Repay | 8,401,786.00 |
Feb 13, 2024 | IBRD-87400 | Loan Disb | -3,952.34 |
Oct 15, 2023 | IBRD-87400 | Int Charges | 507.54 |
Oct 15, 2023 | IBRD-87400 | Int Charges | 2,518.29 |
Oct 15, 2023 | IBRD-87400 | Int Charges | 10,278.12 |
Oct 15, 2023 | IBRD-87400 | Loan Repay | 6,355,608.50 |
Oct 15, 2023 | IBRD-87400 | Int Charges | 384,331.60 |
Apr 15, 2024 | IBRD-87400 | Int Charges | 5,043.63 |
Apr 15, 2024 | IBRD-87400 | Int Charges | 178.13 |
Apr 15, 2024 | IBRD-87400 | Int Charges | 215.78 |
Nov 10, 2023 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Jan 11, 2023 | IBRD-87400 | Loan Disb | 1,500,000.00 |
Feb 17, 2023 | IBRD-87400 | Loan Disb | 1,300,000.00 |
Sep 15, 2023 | IBRD-87400 | Loan Disb | 1,050,130.10 |
Sep 15, 2022 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Apr 15, 2023 | IBRD-87400 | Int Charges | 521,561.70 |
Apr 15, 2023 | IBRD-87400 | Loan Repay | 10,411,218.00 |
Apr 15, 2023 | IBRD-87400 | Int Charges | 6,329.17 |
Apr 15, 2023 | IBRD-87400 | Int Charges | 1,892.12 |
Apr 15, 2023 | IBRD-87400 | Int Charges | 232.88 |
May 9, 2023 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Dec 2, 2022 | IBRD-87400 | Loan Disb | 1,200,000.00 |
Oct 11, 2022 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Oct 28, 2022 | IBRD-87400 | Loan Disb | 1,295,000.00 |
Oct 15, 2022 | IBRD-87400 | Int Charges | 1,399.98 |
Oct 15, 2022 | IBRD-87400 | Int Charges | 12,812.05 |
Oct 15, 2022 | IBRD-87400 | Int Charges | 338,465.06 |
Oct 15, 2022 | IBRD-87400 | Loan Repay | 14,827,435.00 |
Oct 15, 2022 | IBRD-87400 | Int Charges | 562.74 |
Jan 11, 2022 | IBRD-87400 | Loan Disb | 770,000.00 |
Jan 24, 2022 | IBRD-87400 | Loan Disb | 950,000.00 |
Apr 15, 2022 | IBRD-87400 | Int Charges | 110,047.42 |
Apr 15, 2022 | IBRD-87400 | Int Charges | 673.43 |
Apr 15, 2022 | IBRD-87400 | Int Charges | 17,747.98 |
Apr 7, 2022 | IBRD-87400 | Loan Disb | 520,000.00 |
Mar 18, 2022 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Feb 24, 2022 | IBRD-87400 | Loan Disb | 1,000,000.00 |
May 4, 2022 | IBRD-87400 | Loan Disb | 600,000.00 |
Apr 15, 2022 | IBRD-87400 | Int Charges | 246.57 |
Sep 9, 2021 | IBRD-87400 | Loan Disb | 1,000,000.00 |
May 6, 2021 | IBRD-87400 | Loan Disb | 588,712.50 |
Oct 15, 2021 | IBRD-87400 | Int Charges | 409.94 |
Oct 15, 2021 | IBRD-87400 | Int Charges | 1,169.50 |
Oct 15, 2021 | IBRD-87400 | Int Charges | 23,446.89 |
Oct 15, 2021 | IBRD-87400 | Int Charges | 98,663.81 |
Oct 28, 2021 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Aug 12, 2021 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Nov 30, 2021 | IBRD-87400 | Loan Disb | 1,000,000.00 |
Apr 15, 2021 | IBRD-87400 | Int Charges | 144.37 |
Apr 15, 2021 | IBRD-87400 | Int Charges | 29,071.45 |
Apr 15, 2021 | IBRD-87400 | Int Charges | 78,384.93 |
Apr 15, 2021 | IBRD-87400 | Int Charges | 21.07 |
Jan 27, 2021 | IBRD-87400 | Loan Disb | 318,450.78 |
Feb 4, 2021 | IBRD-87400 | Loan Disb | 191,946.90 |
Feb 4, 2021 | IBRD-87400 | Loan Disb | 185,006.00 |
Mar 23, 2021 | IBRD-87400 | Loan Disb | 709,001.60 |
Nov 23, 2020 | IBRD-87400 | Loan Disb | 713,037.90 |
Dec 2, 2020 | IBRD-87400 | Loan Disb | 408,698.70 |
Apr 6, 2021 | IBRD-87400 | Loan Disb | 937,391.06 |
Oct 15, 2020 | IBRD-87400 | Int Charges | 307.36 |
Nov 3, 2020 | IBRD-87400 | Loan Disb | 719,959.90 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2023-12-18 |
Financial Management | Moderately Unsatisfactory | 2023-12-18 |
Procurement | Satisfactory | 2023-12-18 |
Progress towards achievement of PDO | Moderately Satisfactory | 2023-12-18 |
Counterpart Funding | Moderately Unsatisfactory | 2023-12-18 |
Monitoring and Evaluation | Satisfactory | 2023-12-18 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-12-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-23-2024 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 09-09-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
National Water Resources Information System providing validated online data and information products to decision makers, water resources professionals and general public | Value | NWRIS databases established. | Achieved | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Dam safety unit established and operational | Value | No unit. | Partially | Dam safety unit established |
Date | March 14, 2017 | December 5, 2023 | February 28, 2018 | |
Comment |
Basin councils /committees with approved IWRM plans and under implementation | Value | 6 | 10. Achieved | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Groundwater committees established for targeted aquifers with participatory management plans approved under implementation. | Value | No committees in place. | Achieved | Diagnostic of groundwater resources and design of |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Monitoring systems implemented a with O&M implemented via a O&M Unit | Value | No monitoring system in place. | Partially. | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Number of basins in the Pacific Watershed with IWRM plans updated with financing and under implementation | Value | 6 (with average 30% of plans implemented) | Achieved. | 6 plans updated |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Cultura del Agua program tailored to Atlantic Watershed context to build capacity and improve knowledge and practices of the general public in IWRM at the river basin level | Value | Cultura de Agua program rolled out in 6 basins in | Achieved | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Number of dams with dam safety assessments completed and monitoring instruments installed | Value | 0 | Partially | 2 |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
ALAs and Water User Organizations carry out monitoring and evaluation of the use of water user rights | Value | No control and monitoring of formalized water righ | 912. Achieved | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Number of project proposals proposed by indigenous communities included into the management plans of the Atlantic river basins. . | Value | 0.00 | 17.00 | 0.00 |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Number of surface water quality points monitored on a permanent basis | Value | No water quality point monitored. | Partially | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Conservation Committees for Hydromet/Hydrologic Stations established | Value | 0.00 | 125.00 | 0.00 |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
An increase in collection fees (retribución economica) for use of surface, groundwater and discharge of wastewater | Value | No increase in collection fees. | 38.7 % Achieved | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |
Number of water resources related conflicts adequately addressed by ANA | Value | 40 (registered by Defensoría del Pueblo) | 127. Achieved | |
Date | March 14, 2017 | December 5, 2023 | ||
Comment |