Syr Darya Control and Northern Aral Sea Project, Phase 2

Development Objective

The project development objectives (PDOs) are to improve flood management capacity and improve water provision for developing aquaculture and other socioeconomic activities in the project areas along the lower Syr Darya.

Key Details

Project Details

  • P152001

  • Dropped

  • Ahmed Abdelghany

  • REPUBLIC OF KAZAKHSTAN

  • Kazakhstan

  • September 24, 2014

  • (as of board presentation)

    N/A

  • N/A

  • US$ 126.00 million

  • Ministry of Agriculture, Committee for Water Resources

  • Europe and Central Asia

  • 2017

  • US$ 107.00 million

  • B

  • Not Applicable

  • N/A

  • TBD

  • BEGIN APPRAISAL

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 107.00
Borrower/Recipient 19.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 107.00
IDA Commitment N/A
IBRD + IDA Commitment 107.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 126.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area with improved delta lakesValue0.000.00100000.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Area of fish hatcheries developmentValue0.000.00230.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Direct project beneficiariesValue0.000.00160000.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Female beneficiariesValue0.000.0040.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Bulk water savings (average of last 3 years)Value0.000.001500000000.00
    DateOctober 17, 2014March 13, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Replaced low-capacity bridge in Birlik areaValue0.000.001.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Area protected from flooding (agricultural, residential and services)Value0.000.0050000.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Increase in river conveyance capacity at critical sections (flow)Value500 flow (m3/sec)650 flow (m3/sec)
    DateOctober 17, 2014March 13, 2022
    Comment
  • Increase in Dissolved Oxygen in delta lakesValue2 ppm4 ppm
    DateOctober 17, 2014March 13, 2022
    Comment
  • Modeling and monitoring tools for improved decision making in RBMValue0.000.001.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Number of fish hatchery ponds provided for restocking of fisheriesValue0.000.00100.00
    DateOctober 17, 2014March 13, 2022
    Comment
  • Citizens reporting satisfaction with key aspects of consultation processValue0.000.0090.00
    DateOctober 17, 2014March 13, 2022
    Comment