Additional Financing - Stormwater Management and Climate Change Adaptation Project

Development Objective

To improve flood prevention management in peri-urban areas of Dakar and to promote city sustainability management practices, including climate resilience, in two selected urban areas

Key Details

Project Details

  • P152150

  • Closed

  • Isabelle Kane

  • N/A

  • Senegal

  • March 20, 2015

  • (as of board presentation)

    May 27, 2015

  • N/A

  • US$ 38.00 million

  • Agence de Developpement Municipal -ADM-

  • Western and Central Africa

  • 2015

  • US$ 35.00 million

  • A

  • August 5, 2024

  • May 31, 2020

  • TBD

  • BANK APPROVED

  • P122841

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 35.00
Borrower/Recipient 3.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 35.00
IBRD + IDA Commitment 35.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 38.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.0018500.00132000.00
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    CommentThis value will increase up to 32250 by the end 2014 when the works of phase 1 are completed
  • Area protected against recurrent flooding through drainage worksValue0.0088.00660.00
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    Commentthe target of 125 hectares is expected at the completion of the phase 1 works
  • Female beneficiariesValue0.009620.0065000.00
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Capacity building program related to flood-risk management and climate change adaptation completed.ValueNo capacity building program exists.06 MoU under implementationEvaluation of training program.
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    Comment
  • Program and National Strategy on integrated urban stormwater management and climate change adaptation developed.ValueNoneA draft Program for the peri-urban area of Dakar dNational strategy validated.
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    CommentThe Department of Urbanism has requested a revision of the ToR, and will take the lead for the execution then.
  • Detailed local urban plans (PUD) for Pikine and Guediawaye which integrate flood prevention developed and promoted.ValuePDD based flood risk mapping launched.Risks map and a GIS architecture finalizedEvaluation and lessons learned from PUD. preparati
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    CommentThe study is underway and expected to be completed by the end of October 2014
  • People reached by IEC strategy at local and national level.Value0.0018500.0080000.00
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    CommentSensitization sessions were organized by a recruited expert and the social facilitators in the emergency civil works areas
  • Primary drainage system in place.Value0.002800.0028200.00
    DateSeptember 1, 2012July 7, 2014December 31, 2017
    CommentEmergency drainage works completed. The 2014target of 3520 will be reached upon completion of the complementary works of phase 1byend of august
  • AN O&M stormwater drainage management system is functional.ValueNo system in place.The sudies were validated, and the creation of a FOM system in Pikine and Guediawaye functional.
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    CommentThe institutional arrangements and the Fund will be introduced to the Government for approval this year
  • Drainage channels cleaned at least once per year before rainy season in project areaValue0.000.00100.00
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    CommentThe Phase 1 civil works are expected to be completed later 2014
  • Local flood management committees in Pikine and Guediawaye are engaged in stormwater management activities.ValueLocal committees identifiedConsensus is being made to create new committees (Additional committees are strengthened.
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    CommentThe identified existing committees/associations seem difficult to mobilize
  • Eligible flood risk reduction community investments completed.Value0.003.0050.00
    DateSeptember 1, 2012June 30, 2014December 31, 2017
    Comment01 approved and 02 to be validated by end of July. The expected target by end of 2014 was 10, but the consultation process tooktoolong.