Financier | Commitments |
---|---|
IDA Credit | 35.00 |
Borrower/Recipient | 3.00 |
P152150
Closed
Isabelle Kane
N/A
March 20, 2015
(as of board presentation)
May 27, 2015
N/A
US$ 38.00 million
Agence de Developpement Municipal -ADM-
2015
US$ 35.00 million
A
August 5, 2024
May 31, 2020
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 35.00 |
Borrower/Recipient | 3.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 35.00 |
IBRD + IDA Commitment | 35.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 38.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 18500.00 | 132000.00 |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | This value will increase up to 32250 by the end 2014 when the works of phase 1 are completed |
Area protected against recurrent flooding through drainage works | Value | 0.00 | 88.00 | 660.00 |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | the target of 125 hectares is expected at the completion of the phase 1 works |
Female beneficiaries | Value | 0.00 | 9620.00 | 65000.00 |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Capacity building program related to flood-risk management and climate change adaptation completed. | Value | No capacity building program exists. | 06 MoU under implementation | Evaluation of training program. |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment |
Program and National Strategy on integrated urban stormwater management and climate change adaptation developed. | Value | None | A draft Program for the peri-urban area of Dakar d | National strategy validated. |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | The Department of Urbanism has requested a revision of the ToR, and will take the lead for the execution then. |
Detailed local urban plans (PUD) for Pikine and Guediawaye which integrate flood prevention developed and promoted. | Value | PDD based flood risk mapping launched. | Risks map and a GIS architecture finalized | Evaluation and lessons learned from PUD. preparati |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | The study is underway and expected to be completed by the end of October 2014 |
People reached by IEC strategy at local and national level. | Value | 0.00 | 18500.00 | 80000.00 |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | Sensitization sessions were organized by a recruited expert and the social facilitators in the emergency civil works areas |
Primary drainage system in place. | Value | 0.00 | 2800.00 | 28200.00 |
Date | September 1, 2012 | July 7, 2014 | December 31, 2017 | |
Comment | Emergency drainage works completed. The 2014target of 3520 will be reached upon completion of the complementary works of phase 1byend of august |
AN O&M stormwater drainage management system is functional. | Value | No system in place. | The sudies were validated, and the creation of a F | OM system in Pikine and Guediawaye functional. |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | The institutional arrangements and the Fund will be introduced to the Government for approval this year |
Drainage channels cleaned at least once per year before rainy season in project area | Value | 0.00 | 0.00 | 100.00 |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | The Phase 1 civil works are expected to be completed later 2014 |
Local flood management committees in Pikine and Guediawaye are engaged in stormwater management activities. | Value | Local committees identified | Consensus is being made to create new committees ( | Additional committees are strengthened. |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | The identified existing committees/associations seem difficult to mobilize |
Eligible flood risk reduction community investments completed. | Value | 0.00 | 3.00 | 50.00 |
Date | September 1, 2012 | June 30, 2014 | December 31, 2017 | |
Comment | 01 approved and 02 to be validated by end of July. The expected target by end of 2014 was 10, but the consultation process tooktoolong. |