Financier | Commitments |
---|---|
Somalia Multi-Partner Fund | 28.50 |
P152241
Closed
Thilasoni Musuku
Ministry of Finance
January 12, 2016
(as of board presentation)
January 20, 2016
May 16, 2016
US$ 28.50 million
Government of Somaliland Ministry of Planning and Development,Federal Republic of Somalia Ministry of Finance
2016
US$ 28.50 million
B
July 15, 2022
September 30, 2020
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Somalia Multi-Partner Fund | 28.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 28.50 |
Total Project Cost** | 28.50 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2020-06-01 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-06-01 |
Procurement | Moderately Satisfactory | 2020-06-01 |
Project Management | Moderately Satisfactory | 2020-06-01 |
Financial Management | Moderately Satisfactory | 2020-06-01 |
Monitoring and Evaluation | Moderately Satisfactory | 2020-06-01 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-26-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-25-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Total number of direct jobs for youth | Value | 0.00 | 1343.00 | 800.00 |
Date | April 15, 2016 | May 18, 2020 | April 8, 2018 | |
Comment |
Number of recommended laws/regulations/amendments/codes enacted or policies adopted | Value | 0.00 | 5.00 | 5.00 |
Date | April 15, 2016 | September 30, 2020 | August 8, 2018 | |
Comment |
Private Capital Mobilized | Value | 0.00 | 6539382.00 | 7000000.00 |
Date | April 15, 2016 | September 30, 2020 | April 8, 2018 | |
Comment |
Additional number of direct jobs created in enterprises supported by the SBCF | Value | 0.00 | 2217.00 | 2000.00 |
Date | April 15, 2016 | September 30, 2020 | April 8, 2018 | |
Comment |
Number of recommended laws/regulations/amendments/codes enacted in Somaliland | Value | 0.00 | 1.00 | 1.00 |
Date | April 15, 2016 | September 30, 2020 | August 8, 2018 | |
Comment |
Total number of addtional direct jobs created in enterprises supported by the project | Value | 0.00 | 2217.00 | 2000.00 |
Date | April 15, 2016 | September 30, 2020 | April 8, 2018 | |
Comment |
Total number of direct jobs for women | Value | 0.00 | 634.00 | 650.00 |
Date | April 15, 2016 | September 30, 2020 | April 8, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component 1(c): Total number of diagnostic reports on port sector | Value | 0.00 | 2.00 | 2.00 |
Date | April 15, 2016 | May 18, 2020 | April 8, 2018 | |
Comment |
Total annual increase in revenue of firms supported by SBCF and SMEF that received training and advisory services | Value | 0.00 | 194.00 | 15.00 |
Date | April 15, 2016 | September 30, 2020 | ||
Comment |
Component 1 (c): Number of FGS/Ports Authority officials trained on management of ports concession agreements | Value | 0.00 | 5.00 | 5.00 |
Date | April 15, 2016 | September 30, 2020 | April 8, 2018 | |
Comment |
Component 1 (a): Core-banking and accounting system at CBS live and operational | Value | No | Yes | |
Date | July 2, 2018 | September 30, 2020 | ||
Comment |
Total annual number of actionable on-site and off-site examination reports issued | Value | 0.00 | 21.00 | 21.00 |
Date | April 15, 2016 | May 18, 2020 | September 28, 2018 | |
Comment |
Number of individuals receiving subsidized TVET or other forms of training financed by the SMEF | Value | 0.00 | 1175.00 | 800.00 |
Date | May 18, 2020 | September 30, 2020 | ||
Comment |
Component 1 (b): Total number of diagnostic reports on legal, regulatory, institutional and infrastructure setting aimed at supporting business registration and operations | Value | 0.00 | 2.00 | 2.00 |
Date | April 15, 2016 | September 30, 2020 | April 8, 2018 | |
Comment |
Citizen engagement: Proportion of STEP beneficiaries who consider that design and/or implementation of project subjected to consultation is responsive to their view | Value | 0.00 | 99.00 | 50.00 |
Date | April 15, 2016 | September 30, 2020 | ||
Comment |
Component 1 (a): Inter-bank payment, clearing and settlement system live and operational | Value | No | No | |
Date | April 15, 2016 | September 30, 2020 | ||
Comment |
Number of individuals receiving subsidized BDS or advice financed by the SMEF | Value | 0.00 | 861.00 | 500.00 |
Date | May 30, 2016 | September 30, 2020 | ||
Comment |
Component 2 (b) : Percentage of Business Development Services (BDS) providers with repeat clientele and/or new clientele because ofSMEF TA support disaggregated to show female workers and women enter | Value | 0.00 | 26.00 | 0.00 |
Date | July 16, 2018 | September 30, 2020 | ||
Comment |
Component 2 (b): Percentage of businesses incorporating improved business practices or processes because of SMEF TA support | Value | 0.00 | 91.00 | 0.00 |
Date | July 16, 2018 | September 30, 2020 | ||
Comment |