Sudan - FCPF REDD Readiness

Development Objective

The Project Development Objective (PDO) is to strengthen Sudan’s capacity to design a socially and environmentally sound national Reducing Emissions from Deforestation and Forest Degradation Plus (REDD+) strategy.

Key Details

Project Details

  • P152322

  • Closed

  • Dora Cudjoe

  • Ministry of Finance and Economic Planning

  • Sudan

  • December 8, 2017

  • (as of board presentation)

    December 8, 2017

  • N/A

  • US$ 8.73 million

  • B

  • Not Applicable

  • December 31, 2021

  • BANK APPROVED

  • July 29, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Readiness Fund of the Forest Carbon Partnership Facility 8.73

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.73
Total Project Cost** 8.73

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2020-11-30
Financial Management Moderately Satisfactory 2020-11-30
Progress towards achievement of PDO Satisfactory 2020-11-30
Project Management Satisfactory 2020-11-30
Monitoring and Evaluation Moderately Satisfactory 2020-11-30
Overall Implementation Progress (IP) Moderately Satisfactory 2020-11-30

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator One: Institutional framework for delivery of REDD+ is in place at national and state levelsValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Indicator Two: A National REDD+ Strategy, incorporating Strategic Environmental and Social Assessment (SESA) outcomes and recommendations, is prepared and validated by national stakeholders.ValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Indicator Three: An Environmental and Social Management Framework (ESMF) for managing potential social and environmental risks of agreed REDD+ strategy options is prepared and validated.ValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Indicator Four: Direct project beneficiaries (of which women)Value0.0020.0020.00
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Intermediate Result indicator One: REDD+ Management Unit and Inter-Sectoral Technical Advisory Committee establishedValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator Two: Feedback and Grievance Redress Mechanism for REDD+ is designed .ValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator One: Key studies conducted related to strategic options for addressing deforestation and degradation.Value0.003.003.00
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator Two: Review of key policies conducted.ValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator Three: Strategic Environmental and Social Assessment mechanism established.ValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator One: Consultation and participation activities on forest management conductedValue0.00153.00153.00
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator Two: Civil society platforms establishedValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator One: National Forest Inventory (NFI) developed in priority statesValue0.003.003.00
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment
  • Intermediate Result indicator Two: Monitoring and Evaluation system developedValueNoYesYes
    DateJanuary 28, 2015November 19, 2020December 31, 2020
    Comment