P152379
Closed
Suhail Kassim
Government of Somaliland Ministry of Finance
February 20, 2015
(as of board presentation)
October 2, 2015
October 19, 2015
US$ 4.90 million
Somaliland Port Authority (SPA)
2016
US$ 4.90 million
C
Not Applicable
June 30, 2017
BANK APPROVED
February 27, 2020
Financier | Commitments |
---|---|
State and Peace Building Fund | 4.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.90 |
Total Project Cost** | 4.90 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Towage capacity (Dead weight tons) | Value | 30000.00 | 30000.00 | 45000.00 |
Date | April 30, 2015 | June 30, 2017 | June 30, 2017 | |
Comment |
Towage operability (percent of yearly gross time available) | Value | 30.00 | 30.00 | 95.00 |
Date | April 30, 2015 | June 30, 2017 | June 30, 2017 | |
Comment |
Port throughput (volume of cargo handled in tons) | Value | 1065762.00 | 1065762.00 | 1600000.00 |
Date | April 30, 2015 | June 30, 2017 | June 30, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Berbera Port Authority trained in procurement | Value | No | Yes | Yes |
Date | April 30, 2015 | July 31, 2016 | June 30, 2016 | |
Comment |
Competitive procurement of a tugboat according to guidelines | Value | No | No | Yes |
Date | April 30, 2015 | June 30, 2017 | June 30, 2017 | |
Comment |
Replacement of the current tugboat with a new tugboat conforming to technical specifications | Value | No | No | Yes |
Date | April 30, 2015 | June 30, 2017 | June 30, 2017 | |
Comment |