Public Sector Modernisation Project

Abstract*

The objective of the Public Sector Modernization Project for Lesotho is to strengthen strategic-level planning and to improve efficiency in the fiscal and human resource management of selected ministries. There are four components to the project, the first component being strategic planning and fiscal management. The objectives of this component are to strengthen strategic and fiscal planning and the decision-making processes and improve expenditure...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to strengthen strategic-level planning, and to improve efficiency in the fiscal and human resource management of Selected Ministries.

Key Details

Project Details

  • P152398

  • Closed

  • Joanna Watkins , Kirstin Conti

  • Kingdom of Lesotho

  • Lesotho

  • May 20, 2015

  • (as of board presentation)

    March 24, 2016

  • May 25, 2016

  • US$ 10.00 million

  • Ministry of Development and Planning,Ministry of Public Service,Ministry of Finance

  • Eastern and Southern Africa

  • 2016

  • US$ 10.00 million

  • C

  • Not Applicable

  • November 30, 2021

  • TBD

  • BANK APPROVED

  • June 1, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 10.00
IBRD + IDA Commitment 10.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 10.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 24, 2017 IDA-57720 Loan Disb 184,514.62
Feb 15, 2020 IDA-57720 Int Charges 2,843.00
Feb 15, 2020 IDA-57720 Int Charges 20,538.13
Feb 15, 2020 IDA-57720 Int Charges 20,538.13
Aug 15, 2022 IDA-57720 Int Charges 3.26
Aug 15, 2022 IDA-57720 Int Charges 5.44
Aug 15, 2022 IDA-57720 Int Charges 1,110.61
Aug 31, 2018 IDA-57720 Loan Disb 75,212.76
Jun 14, 2018 IDA-57720 Loan Disb 176,342.64
Aug 15, 2018 IDA-57720 Int Charges 561.07
Aug 15, 2018 IDA-57720 Int Charges 8,843.02
Aug 15, 2018 IDA-57720 Int Charges 8,843.02
Aug 15, 2018 IDA-57720 Int Charges 14,738.42
Nov 19, 2018 IDA-57720 Loan Disb 125,361.39
Jul 13, 2017 IDA-57720 Loan Disb 110,774.07
May 23, 2017 IDA-57720 Loan Disb 14,179.37
Jun 12, 2017 IDA-57720 Loan Disb 142,772.78
Oct 19, 2017 IDA-57720 Loan Disb 150,297.98
Sep 12, 2017 IDA-57720 Loan Disb 82,197.65
Mar 1, 2017 IDA-57720 Int Charges 120.93
Mar 1, 2017 IDA-57720 Int Charges 120.93
Mar 1, 2017 IDA-57720 Int Charges 1,100.48
Mar 1, 2017 IDA-57720 Int Charges 201.54
Mar 1, 2017 IDA-57720 Int Charges 819.81
Mar 1, 2017 IDA-57720 Int Charges 819.81
Aug 30, 2017 IDA-57720 Loan Disb 117,408.91
Aug 16, 2017 IDA-57720 Int Charges 3,360.44
Aug 16, 2017 IDA-57720 Int Charges 2,192.89
Aug 16, 2017 IDA-57720 Int Charges 2,192.89
Dec 6, 2017 IDA-57720 Loan Disb 128,392.81
Nov 16, 2017 IDA-57720 Loan Disb 147,842.98
Aug 16, 2017 IDA-57720 Int Charges 276.94
Feb 15, 2018 IDA-57720 Int Charges 4,918.98
Feb 15, 2018 IDA-57720 Int Charges 4,918.98
Mar 8, 2018 IDA-57720 Loan Disb 460,134.06
Apr 24, 2018 IDA-57720 Loan Disb 184,248.30
Mar 9, 2018 IDA-57720 Loan Disb 149,767.50
Feb 22, 2018 IDA-57720 Loan Disb 36,860.95
Feb 15, 2018 IDA-57720 Int Charges 305.71
Jul 15, 2016 IDA-57720 Loan Disb 200,000.00
Dec 23, 2016 IDA-57720 Loan Disb 74,169.16
Feb 9, 2017 IDA-57720 Loan Disb 107,684.85
Feb 16, 2022 IDA-57720 Loan Repay 166,156.80
Feb 16, 2022 IDA-57720 Int Charges 36,749.20
Feb 16, 2022 IDA-57720 Int Charges 36,749.20
Feb 16, 2022 IDA-57720 Int Charges 60,068.78
Aug 15, 2022 IDA-57720 Int Charges 58,247.16
Jul 8, 2022 IDA-57720 Loan Disb -1,117.07
Nov 23, 2021 IDA-57720 Loan Disb 64,000.00
Jun 17, 2022 IDA-57720 Loan Disb -83.48
Aug 15, 2021 IDA-57720 Int Charges 159.02
Aug 15, 2021 IDA-57720 Loan Repay 171,081.16
Aug 15, 2021 IDA-57720 Int Charges 33,723.98
Aug 15, 2021 IDA-57720 Int Charges 33,723.98
Aug 15, 2021 IDA-57720 Int Charges 56,206.66
Oct 14, 2021 IDA-57720 Loan Disb 722,869.30
Apr 12, 2021 IDA-57720 Loan Disb 501,478.90
Feb 15, 2021 IDA-57720 Int Charges 30,303.93
Feb 15, 2021 IDA-57720 Int Charges 30,303.93
Feb 15, 2021 IDA-57720 Int Charges 50,345.19
Feb 15, 2021 IDA-57720 Int Charges 2,930.40
Mar 19, 2021 IDA-57720 Loan Disb 410,219.80
Jun 15, 2021 IDA-57720 Loan Disb 125,439.17
Jul 29, 2021 IDA-57720 Loan Disb 268,561.78
Mar 2, 2021 IDA-57720 Loan Disb 225,056.31
Jul 8, 2020 IDA-57720 Loan Disb 144,836.47
Aug 15, 2020 IDA-57720 Int Charges 315.91
Aug 15, 2020 IDA-57720 Int Charges 315.91
Aug 15, 2020 IDA-57720 Int Charges 26,262.37
Aug 15, 2020 IDA-57720 Int Charges 26,262.37
Aug 15, 2020 IDA-57720 Int Charges 41,429.90
Aug 17, 2020 IDA-57720 Loan Disb 63,973.61
Nov 3, 2020 IDA-57720 Loan Disb 198,951.73
Mar 24, 2016 IDA-57720 Loan Commitment 10,000,000.00
Aug 15, 2024 IDA-57720 Int Charges 33,007.82
Aug 15, 2024 IDA-57720 Int Charges 33,007.82
Aug 15, 2024 IDA-57720 Int Charges 51,112.61
Aug 15, 2024 IDA-57720 Loan Repay 3,367.28
Aug 15, 2024 IDA-57720 Loan Repay 157,825.30
Feb 15, 2024 IDA-57720 Loan Repay 158,863.83
Feb 15, 2024 IDA-57720 Loan Repay 432.10
Feb 15, 2024 IDA-57720 Int Charges 55,361.37
Feb 15, 2024 IDA-57720 Int Charges 33,216.80
Feb 15, 2024 IDA-57720 Int Charges 33,216.80
Feb 15, 2023 IDA-57720 Int Charges -1.12
Feb 15, 2023 IDA-57720 Int Charges 1.12
Feb 15, 2023 IDA-57720 Loan Repay 2,195.78
Feb 15, 2023 IDA-57720 Int Charges 34,790.31
Feb 15, 2023 IDA-57720 Int Charges 34,790.31
Feb 15, 2023 IDA-57720 Loan Repay 158,853.48
Aug 15, 2023 IDA-57720 Int Charges 1,242.24
Aug 15, 2023 IDA-57720 Loan Repay 160,443.55
Aug 15, 2023 IDA-57720 Int Charges 34,057.82
Aug 15, 2023 IDA-57720 Int Charges 34,057.82
Feb 15, 2023 IDA-57720 Int Charges 56,736.92
Aug 15, 2023 IDA-57720 Int Charges 56,762.99
Jul 8, 2022 IDA-57720 Loan Cancel 2,164.31
Aug 15, 2022 IDA-57720 Int Charges 34,948.27
Aug 15, 2022 IDA-57720 Int Charges 34,948.27
Aug 15, 2022 IDA-57720 Loan Repay 115,759.34
Aug 15, 2022 IDA-57720 Loan Repay 43,281.63
Aug 15, 2022 IDA-57720 Int Charges 3.26
Feb 15, 2020 IDA-57720 Int Charges 34,230.20
Dec 16, 2019 IDA-57720 Loan Disb 102,049.01
Apr 30, 2020 IDA-57720 Loan Disb 701,507.70
Jun 17, 2020 IDA-57720 Loan Disb 324,479.06
Nov 19, 2019 IDA-57720 Loan Disb 710,720.90
Aug 15, 2019 IDA-57720 Int Charges 25,054.31
Aug 15, 2019 IDA-57720 Int Charges 2,651.31
Aug 15, 2019 IDA-57720 Int Charges 16,746.98
Aug 15, 2019 IDA-57720 Int Charges 16,746.98
Feb 13, 2020 IDA-57720 Loan Disb 424,330.90
Jun 17, 2019 IDA-57720 Loan Disb 980,500.75
Feb 15, 2019 IDA-57720 Int Charges 482.89
Feb 15, 2019 IDA-57720 Int Charges 482.89
Dec 21, 2018 IDA-57720 Loan Disb 800,000.00
Dec 21, 2018 IDA-57720 Loan Disb 34,391.35
Oct 17, 2018 IDA-57720 Loan Disb 254,419.50
Oct 1, 2018 IDA-57720 Loan Disb 118,151.80
Feb 15, 2019 IDA-57720 Int Charges 18,673.17
Feb 15, 2019 IDA-57720 Int Charges 12,325.93
Feb 15, 2019 IDA-57720 Int Charges 12,325.93
Jan 16, 2018 IDA-57720 Loan Disb 114,786.20
May 29, 2018 IDA-57720 Loan Disb 4,557.34
Jun 11, 2018 IDA-57720 Loan Disb 254,419.48
Feb 15, 2018 IDA-57720 Int Charges 7,606.75
Feb 15, 2022 IDA-57720 Loan Repay 2,801.81

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2021-11-30
Project Management Satisfactory 2021-11-30
Financial Management Satisfactory 2021-11-30
Overall Implementation Progress (IP) Moderately Satisfactory 2021-11-30
Progress towards achievement of PDO Moderately Satisfactory 2021-11-30
Monitoring and Evaluation Moderately Satisfactory 2021-11-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-01-2022
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • New capital investment projects appraised according to PIM manualValue0.0095.0075.00
    DateMarch 24, 2016November 30, 2021November 30, 2021
    Comment
  • Irregular HR and payroll records corrected/removedValueIrregular human resource and payroll records not i98% of irregular records corrected or removed from90
    DateMarch 24, 2016November 30, 2021November 30, 2021
    Comment
  • Credibility of budget frameworkValue10.002.508.50
    DateMarch 24, 2016November 30, 2021November 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Revised Institutional Plan implemented by the Ministry of Development PlanningValueN/AStrategic Plan is approved and under implementatioRevised institutional plan under implementation
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Improved availability of reliable statistical data to enhance strategic level planningValueNo survey conductedA second household survey was completed using the Survey methodology revised and implemented
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Citizen feedback collected in one pilot sectorValueNo feedback collectedThe citizen feedback management tool was piloted wCitizen feedback collected in one pilot sector
    DateMay 24, 2016November 30, 2021March 24, 2020
    Comment
  • Quarterly time series published consistent with SDDS requirementsValueNo quarterly GDP publishedQuarterly GDP is published on the Bureau of StatisQuarterly GDP current price and volume time series
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Training on new business procedures complete for HR officersValueTraining not commenced, as new HR business processTraining on the new business processes and the new50%
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Of which are womenValue0.0075.0075.00
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Annual report on SOE fiscal impact published on MOF websiteValueNo report on SOE fiscal impact developedThe 2018/19 report was not published at project clAnnual report on SOE fiscal impact published on MO
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • PIM manual updated and operationalValuePIM manual not updatedPIM manual updated and operationalPIM manual operational
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Revised establishment lists in MOET completeValueNo revised establishment list in MOETA MOET Establishment List was completed, but not eRevised establishment list in MOET complete
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Core HR business processes automated and operationalizedValueHRMIS payroll module in use. HRMIS assessment and All core HR business processes have been automatedCore HR business processes automated and operation
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Civil servants and civil pensioners with accurate National ID number captured in HRMISValue34.0095.4095.00
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment
  • Staff on MOET and MOH payroll mapped to an established position in HRMISValueMOET and MOH staff are not mapped to established pMOET – The exercise to map MOET staff to establishStaff on MOET and MOH payroll mapped to an establi
    DateMay 24, 2016November 30, 2021November 30, 2021
    Comment