Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 24.62 |
P152860
Closed
Ning Fu
People's Republic of China
November 25, 2015
(as of board presentation)
December 9, 2016
June 1, 2017
US$ 74.62 million
Yunnan Provincial Department of Education
2017
US$ 50.00 million
B
Not Applicable
December 31, 2021
Yes
BANK APPROVED
August 15, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 24.62 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 50.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 74.62 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 9, 2016 | IBRD-86710 | Loan Commitment | 50,000,000.00 |
Apr 15, 2018 | IBRD-86710 | Int Charges | 24,398.54 |
Apr 15, 2024 | IBRD-86710 | Int Charges | 1,596,329.90 |
Apr 15, 2024 | IBRD-86710 | Loan Repay | 891,057.60 |
Oct 15, 2023 | IBRD-86710 | Int Charges | 25,333.15 |
Oct 15, 2023 | IBRD-86710 | Int Charges | 1,503,271.40 |
Oct 15, 2023 | IBRD-86710 | Loan Repay | 891,057.60 |
Apr 15, 2023 | IBRD-86710 | Int Charges | 50,001.67 |
Apr 15, 2023 | IBRD-86710 | Int Charges | 1,258,505.40 |
Apr 15, 2023 | IBRD-86710 | Loan Repay | 891,057.60 |
Oct 15, 2022 | IBRD-86710 | Int Charges | 747,623.44 |
Oct 15, 2022 | IBRD-86710 | Loan Repay | 891,057.60 |
Oct 15, 2022 | IBRD-86710 | Int Charges | -0.01 |
Oct 15, 2022 | IBRD-86710 | Int Charges | 0.01 |
May 20, 2022 | IBRD-86710 | Loan Disb | -216,302.34 |
Apr 15, 2022 | IBRD-86710 | Int Charges | 1,131.90 |
Apr 15, 2022 | IBRD-86710 | Int Charges | 295,342.94 |
Apr 15, 2022 | IBRD-86710 | Loan Repay | 895,000.00 |
May 20, 2022 | IBRD-86710 | Loan Cancel | 216,302.34 |
Dec 13, 2021 | IBRD-86710 | Loan Disb | 2,603,498.00 |
Apr 15, 2021 | IBRD-86710 | Int Charges | 214,505.40 |
Apr 26, 2021 | IBRD-86710 | Loan Disb | 4,042,384.20 |
Apr 15, 2021 | IBRD-86710 | Int Charges | 19,989.65 |
Jun 28, 2021 | IBRD-86710 | Loan Disb | 4,363,306.00 |
Oct 15, 2021 | IBRD-86710 | Int Charges | 10,646.73 |
Oct 15, 2021 | IBRD-86710 | Int Charges | 263,735.30 |
Oct 18, 2021 | IBRD-86710 | Loan Disb | 3,883,232.80 |
Oct 15, 2020 | IBRD-86710 | Int Charges | 23,958.86 |
Oct 15, 2020 | IBRD-86710 | Int Charges | 347,949.28 |
Dec 7, 2020 | IBRD-86710 | Loan Disb | 3,996,665.50 |
Feb 4, 2020 | IBRD-86710 | Loan Disb | 4,916,639.00 |
Apr 27, 2020 | IBRD-86710 | Loan Disb | 4,239,716.00 |
Apr 15, 2020 | IBRD-86710 | Int Charges | 1,316.49 |
Apr 15, 2020 | IBRD-86710 | Int Charges | 32,713.29 |
Apr 15, 2020 | IBRD-86710 | Int Charges | 360,258.16 |
Apr 15, 2020 | IBRD-86710 | Int Charges | 95.94 |
Apr 15, 2019 | IBRD-86710 | Int Charges | 42,198.90 |
Apr 15, 2019 | IBRD-86710 | Int Charges | 296,345.10 |
Oct 11, 2019 | IBRD-86710 | Loan Disb | 3,501,863.20 |
Oct 15, 2019 | IBRD-86710 | Int Charges | 39,446.22 |
Oct 15, 2019 | IBRD-86710 | Int Charges | 340,498.34 |
May 11, 2018 | IBRD-86710 | Loan Disb | 3,496,834.00 |
May 30, 2018 | IBRD-86710 | Loan Disb | 1,179,156.80 |
Aug 7, 2018 | IBRD-86710 | Loan Disb | 4,189,673.80 |
Jan 17, 2019 | IBRD-86710 | Loan Disb | 4,462,030.50 |
Oct 15, 2018 | IBRD-86710 | Int Charges | 49,392.54 |
Oct 15, 2018 | IBRD-86710 | Int Charges | 185,791.03 |
Jun 1, 2017 | IBRD-86710 | Fee Charges | 125,000.00 |
Jun 1, 2017 | IBRD-86710 | Loan Disb | 125,000.00 |
Oct 15, 2017 | IBRD-86710 | Int Charges | 55,705.48 |
Oct 15, 2017 | IBRD-86710 | Int Charges | 1,109.73 |
Feb 8, 2018 | IBRD-86710 | Loan Disb | 2,000,000.00 |
Feb 8, 2018 | IBRD-86710 | Loan Disb | 3,000,000.00 |
Apr 15, 2018 | IBRD-86710 | Int Charges | 4.72 |
Apr 15, 2018 | IBRD-86710 | Int Charges | 59,912.67 |
Apr 15, 2024 | IBRD-86710 | Int Charges | 16,339.04 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2021-06-25 |
Monitoring and Evaluation | Satisfactory | 2021-06-25 |
Overall Implementation Progress (IP) | Satisfactory | 2021-06-25 |
Progress towards achievement of PDO | Satisfactory | 2021-06-25 |
Procurement | Satisfactory | 2021-06-25 |
Project Management | Satisfactory | 2021-06-25 |
Financial Management | Satisfactory | 2021-06-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-23-2022 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Highly Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | High | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
3-year kindergarten GER in the Project counties | Value | 54.00 | 69.00 | 60.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
3-year kindergarten GER in rural areas in the Project counties | Value | 45.00 | 69.00 | 60.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Percentage of preschool teachers and staff with professional certificates in project counties | Value | 0.00 | 62.00 | 59.00 |
Date | December 1, 2016 | December 31, 2021 | December 1, 2020 | |
Comment |
3-year kindergarten GER (ethnic minorities) in the Project counties | Value | 64.00 | 69.00 | 66.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 17291.00 | 2586.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Female beneficiaries | Value | 0.00 | 47.50 | 47.50 |
Date | November 30, 2015 | April 30, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of kindergarten classes constructed or renovated under the Project | Value | 0.00 | 170.00 | 109.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Percentage of rural and private teachers that participate in training under the Project | Value | 0.00 | 90.00 | 68.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Number of kindergartens that comply with the new kindergarten quality standards | Value | 0.00 | 158.00 | 80.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Number of kindergartens that use child development measurement instrument | Value | 0.00 | 88.00 | 46.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Student-teacher ratio (Project county) | Value | 20.00 | 14.00 | 17.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Number of policy suggestions adopted | Value | 0.00 | 2.00 | 0.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Student-teacher ratio in rural areas (Project county) | Value | 24.00 | 14.50 | 20.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Number of newly recruited university faculty with PhD or Masters | Value | 0.00 | 20.00 | 8.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
University graduate employment rate in ECE sector | Value | 68.00 | 91.00 | 79.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |
Parental satisfaction towards kindergarten quality | Value | 0.00 | 90.00 | 80.00 |
Date | November 30, 2015 | December 31, 2021 | ||
Comment |