AF Additional Financing: Irrigation Restoration and Development

Development Objective

Improve access to irrigation in targeted areas and strengthen capacity for water resources management.

Key Details

Project Details

  • P152892

  • Closed

  • Mir Ahmad , Sana Kh.H. Agha Al Nimer, Francois Onimus

  • Government of Afghanistan

  • Afghanistan

  • March 29, 2016

  • (as of board presentation)

    May 23, 2016

  • N/A

  • US$ 70.00 million

  • A

  • Not Applicable

  • June 30, 2025

  • TBD

  • BANK APPROVED

  • P122235

  • February 1, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Afghanistan Resilience Trust Fund 70.00
Borrower/Recipient 1.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 70.00
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2017-12-01
Progress towards achievement of PDO Moderately Satisfactory 2017-12-01
Project Management Satisfactory 2017-12-01
Financial Management Satisfactory 2017-12-01
Monitoring and Evaluation Satisfactory 2017-12-01
Overall Implementation Progress (IP) Moderately Satisfactory 2017-12-01
Counterpart Funding Satisfactory 2017-12-01

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in irrigated areaValue0.0034.0015.00
    DateMarch 31, 2011September 30, 2015December 31, 2017
    Comment
  • Increase in agricultural ProductivityValue0.0032.0020.00
    DateJanuary 31, 2012March 23, 2015December 31, 2017
    Comment
  • Area provided with irrigation and drainage services (ha)Value75000.00120000.00215000.00
    DateMarch 31, 2011December 31, 2015December 31, 2020
    Comment
  • Area provided with irrigation and drainage services - New (ha)Value0.009815.000.00
    DateMarch 31, 2011March 26, 2014December 31, 2017
    Comment
  • Dams which have undergone dam safety reviewValue0.000.003.00
    DateMarch 21, 2012March 26, 2014December 31, 2020
    Comment
  • Water users provided with new/improved irrigation and drainage services (number)Value0.00206000.00385000.00
    DateMarch 31, 2011December 31, 2015December 31, 2020
    Comment
  • Dams for which detailed preparation studies have been completedValue0.000.002.00
    DateFebruary 28, 2013February 15, 2016December 31, 2020
    Comment
  • Water Disaster Risk Management Plan (including flood/drought forecasting and early warning systems), two basin development plans, and the river bank protection plan for the Panju-Amu river preparedValue0.000.003.00
    DateJanuary 31, 2012March 23, 2015December 31, 2020
    Comment
  • Water users provided with irrigation and drainage services - female (number)Value0.00100000.00200000.00
    DateMarch 31, 2011December 31, 2015December 31, 2020
    Comment
  • Mirabs strengthenedValue0.00120.00212.00
    DateDecember 31, 2015February 15, 2016December 31, 2020
    Comment
  • Direct project beneficiariesValue100000.00200000.00400000.00
    DateJanuary 31, 2012December 31, 2015December 31, 2020
    Comment
  • Female beneficiariesValue48.0048.0048.00
    DateJanuary 31, 2012December 31, 2015December 31, 2020
    Comment
  • Area provided with irrigation and drainage services â?? Improved (ha)Value75000.00120000.00215000.00
    DateMarch 31, 2011December 31, 2015December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water related disputesValue100.000.000.00
    DateSeptember 30, 2014
    Comment
  • Number of small dams completedValue0.000.003.00
    DateMarch 31, 2011March 23, 2015December 31, 2017
    Comment
  • % of sub-projects designed using data from the established hydro-meteorological facilities and servicesValue0.000.00100.00
    DateMarch 31, 2011March 23, 2015December 31, 2017
    Comment
  • % of trainees who agree that the training has helped them to do their job betterValue0.000.0070.00
    DateMarch 31, 2011March 23, 2015December 31, 2017
    Comment
  • River bank protected from erosionValue0.000.0026.30
    DateDecember 31, 2015February 15, 2016December 31, 2020
    Comment
  • Dams having undergone minor dam safety worksValue0.000.002.00
    DateDecember 31, 2015February 15, 2016December 31, 2020
    Comment
  • Dam safety and O&M guidelines and manuals preparedValue0.000.005.00
    DateDecember 31, 2015February 15, 2016December 31, 2020
    Comment
  • Hydromet/weather/snow measurement stations installedValue183.00183.00230.00
    DateDecember 31, 2015February 15, 2016December 31, 2020
    Comment
  • Transboundary water unit established at MEWValueNoNoYes
    DateMarch 31, 2011March 23, 2015December 31, 2020
    Comment
  • Government staff trained on topics related to river bank protection, dam planning and management, water resources management and development (of which female)Value5.005.0030.00
    DateDecember 31, 2015February 15, 2016December 31, 2020
    Comment
  • Irrigation canals rehabilitatedValue0.00500.00900.00
    DateFebruary 14, 2012February 15, 2016December 31, 2020
    Comment
  • Beneficiary satisfaction with involvement in rehabilitation design and implementationValue0.0080.0090.00
    DateDecember 31, 2015February 15, 2016December 31, 2020
    Comment
  • Mandate for irrigation between MAIL and MEW clarifiedValueNoNoYes
    DateApril 5, 2016April 5, 2016December 31, 2020
    Comment