Afghanistan Power System Development Project Additional Financing

Development Objective

The development objective of the project is to increase the number of electricity connections for the urban centers of Charikar, Gulbahar and Jabul-es-Seraj and Pul-e-Khumri and to improve the availability of power from Naghlu and Mahipar switchyards.

Key Details

Project Details

  • P152975

  • Closed

  • Fanny Missfeldt-Ringius , Jie Li

  • N/A

  • Afghanistan

  • June 23, 2015

  • (as of board presentation)

    July 7, 2015

  • N/A

  • US$ 15.00 million

  • N/A

  • South Asia

  • 2016

  • US$ 15.00 million

  • B

  • Not Applicable

  • May 31, 2017

  • Yes

  • BANK APPROVED

  • P111943

  • February 28, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Afghanistan Resilience Trust Fund 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 15.00
Total Project Cost** 15.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Distribution lines constructed or rehabilitated under the projectValue0.00411.00626.00
    DateMarch 30, 2009August 31, 2014May 31, 2017
    Comment
  • The number of households that are connected to the grid through this project in the target area of Charikar, Gulbahar and Jabul-es-S erajValue0.000.0012500.00
    DateMarch 30, 2009December 31, 2014May 31, 2017
    Comment
  • The number of households that are connected to the grid through this project in the target area of Pul-e-KhumriValue0.000.005500.00
    DateMarch 30, 2009December 31, 2014May 31, 2017
    Comment
  • Satisfactory completion of project activities and closing of contracts on time and within budget.ValueNoNoYes
    DateMarch 30, 2009December 31, 2014May 31, 2017
    Comment
  • Distribution lines rehabilitated under the projectValue0.00411.00626.00
    DateMarch 30, 2009August 31, 2014May 31, 2017
    Comment
  • Total power supply outages in a year as a result of Naghlu switchyardValue18.0018.003.00
    DateDecember 31, 2014December 31, 2014May 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Progress in installation work at Charikar, Gulbahar and Jabul-es-SerajValue0.0017224.0023000.00
    DateMarch 30, 2009August 31, 2014May 31, 2017
    Comment
  • Progress in installation work at Pul-e-KhumriValue0.0014982.0017000.00
    DateMarch 30, 2009August 31, 2014May 31, 2017
    Comment
  • Timely submission of quarterly progress reports and quarterly interim unaudited financial management reports acceptable to the BankValueNoYesYes
    DateMarch 30, 2009December 31, 2014May 31, 2017
    Comment
  • Switchyards rehabilitated with all equipment installedValue1.001.002.00
    DateDecember 31, 2014December 31, 2014May 31, 2017
    Comment