Financier | Commitments |
---|---|
Afghanistan Resilience Trust Fund | 15.00 |
P152975
Closed
Fanny Missfeldt-Ringius , Jie Li
N/A
June 23, 2015
(as of board presentation)
July 7, 2015
N/A
US$ 15.00 million
N/A
2016
US$ 15.00 million
B
Not Applicable
May 31, 2017
Yes
BANK APPROVED
February 28, 2022
Financier | Commitments |
---|---|
Afghanistan Resilience Trust Fund | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 15.00 |
Total Project Cost** | 15.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 411.00 | 626.00 |
Date | March 30, 2009 | August 31, 2014 | May 31, 2017 | |
Comment |
The number of households that are connected to the grid through this project in the target area of Charikar, Gulbahar and Jabul-es-S eraj | Value | 0.00 | 0.00 | 12500.00 |
Date | March 30, 2009 | December 31, 2014 | May 31, 2017 | |
Comment |
The number of households that are connected to the grid through this project in the target area of Pul-e-Khumri | Value | 0.00 | 0.00 | 5500.00 |
Date | March 30, 2009 | December 31, 2014 | May 31, 2017 | |
Comment |
Satisfactory completion of project activities and closing of contracts on time and within budget. | Value | No | No | Yes |
Date | March 30, 2009 | December 31, 2014 | May 31, 2017 | |
Comment |
Distribution lines rehabilitated under the project | Value | 0.00 | 411.00 | 626.00 |
Date | March 30, 2009 | August 31, 2014 | May 31, 2017 | |
Comment |
Total power supply outages in a year as a result of Naghlu switchyard | Value | 18.00 | 18.00 | 3.00 |
Date | December 31, 2014 | December 31, 2014 | May 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Progress in installation work at Charikar, Gulbahar and Jabul-es-Seraj | Value | 0.00 | 17224.00 | 23000.00 |
Date | March 30, 2009 | August 31, 2014 | May 31, 2017 | |
Comment |
Progress in installation work at Pul-e-Khumri | Value | 0.00 | 14982.00 | 17000.00 |
Date | March 30, 2009 | August 31, 2014 | May 31, 2017 | |
Comment |
Timely submission of quarterly progress reports and quarterly interim unaudited financial management reports acceptable to the Bank | Value | No | Yes | Yes |
Date | March 30, 2009 | December 31, 2014 | May 31, 2017 | |
Comment |
Switchyards rehabilitated with all equipment installed | Value | 1.00 | 1.00 | 2.00 |
Date | December 31, 2014 | December 31, 2014 | May 31, 2017 | |
Comment |