Financier | Commitments |
---|---|
IDA Credit | 15.00 |
Borrower/Recipient | 15.00 |
P153111
Closed
Andreas Blom
N/A
Western and Central Africa
August 27, 2015
(as of board presentation)
September 10, 2015
N/A
US$ 30.00 million
N/A
2016
US$ 15.00 million
B
Not Applicable
September 30, 2020
Yes
BANK APPROVED
September 13, 2022
Financier | Commitments |
---|---|
IDA Credit | 15.00 |
Borrower/Recipient | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.00 |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 30.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
No of students enrolled in new specialized Master, PhD, post-grad, post-doc and/or short-term courses/ programs | Value | 1580.00 | 3510.00 | 17375.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 1775 students |
No. of internationally (regionally/sub-regioanally) accredited education programs. | Value | 3.00 | 0.00 | 18.00 |
Date | November 30, 2013 | December 31, 2018 | ||
Comment | Addition of 3 accredited education programs. |
Amount of externally generated revenue by the ACEs. | Value | 976877.00 | 5872424.00 | 9551250.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of USD$1,551,250 |
Number of Students with at least 1 month internship in a private sector company or a local institutions relevant to their field/ sector. | Value | 1037.00 | 2281.00 | 6928.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 1028 students |
Number of regional students enrolled in new specialized short-term courses, Master and PhD programs | Value | 987.00 | 1458.00 | 9432.00 |
Date | November 30, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 532 students to end target |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
No of faculty trained by the ACEs | Value | 100.00 | 329.00 | 1200.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2014 | |
Comment | Addition of 300 faculty to original target |
No of newly established or revised curricula (meeting labor market skills), as approved by the appropriate institutional organ. | Value | 0.00 | 48.00 | 66.00 |
Date | November 1, 2013 | June 9, 2015 | March 31, 2018 | |
Comment | Addition of 6 new established or revised curricula. |
Increase of internationally recognized research publications in disciplines supported by the ACE-Programme | Value | 1098.00 | 1222.00 | 1335.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 135. |
No of ACE-Institutions reporting on at least 85% of their indicators, submitting the RF to the AAU in time. | Value | 0.00 | 6.00 | 14.00 |
Date | November 1, 2013 | December 1, 2014 | December 31, 2018 | |
Comment | Addition of 2. |
No of partnership agreements between ACEs and engaged partner institutions | Value | 48.00 | 107.00 | 208.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 38 partnership agreements. |
ACE project implementation team meetings with openedly disclosed minutes | Value | 0.00 | 30.00 | 136.00 |
Date | November 15, 2015 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 16. |
Annual program report prepared and submitted to WB | Value | N/A | Two semi-annual activity program reports have been | Done |
Date | November 1, 2013 | December 1, 2014 | December 31, 2018 | |
Comment |
Annual disclosed unqualified external financial audit with the ACE annual budget (planned and executed). | Value | 0.00 | 0.00 | 37.00 |
Date | November 1, 2013 | December 31, 2018 | ||
Comment |
RFU holding regular meetings with at least 15 ACEs participating | Value | 0.00 | 2.00 | 8.00 |
Date | November 1, 2013 | December 1, 2014 | December 31, 2018 | |
Comment |
Level of satisfaction of ACE and ACE Steering Committee on quality of support provided by the Regional Facilitation Unit (AAU). | Value | 73.00 | 0.00 | 75.00 |
Date | May 20, 2014 | December 31, 2018 | ||
Comment |
Direct project beneficiaries | Value | 2717.00 | 0.00 | 18765.00 |
Date | November 1, 2013 | December 31, 2018 | ||
Comment | Addition of 2075 beneficiaries (300 faculty and 1775 students). (including 858 female beneficiaries.) |
Number of regional faculty trained by the ACEs | Value | 27.00 | 44.00 | 415.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 80 faculty |
Number of regional faculty trained by the ACEs | Value | 27.00 | 44.00 | 415.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 80 faculty. |
Number of national faculty trained by the ACEs | Value | 73.00 | 285.00 | 685.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 120 faculty. |
Female beneficiaries | Value | 332.00 | 0.00 | 4464.00 |
Date | November 1, 2013 | December 31, 2018 | ||
Comment |
Number of female faculty regionally trained by the ACEs | Value | 7.00 | 10.00 | 131.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 30 faculty |
Number of national female faculty trained by the ACEs | Value | 14.00 | 69.00 | 195.00 |
Date | November 1, 2013 | June 9, 2015 | December 31, 2018 | |
Comment | Addition of 40 faculty. |