Financier | Commitments |
---|---|
IDA Credit | 60.00 |
P153124
Closed
Clemencia Torres De Mastle
N/A
April 23, 2015
(as of board presentation)
June 24, 2015
N/A
US$ 60.00 million
N/A
2015
US$ 60.00 million
B
November 15, 2023
July 31, 2022
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 60.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 60.00 |
IBRD + IDA Commitment | 60.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 60.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Commercial and institutional customers provided with access to electricity under the project | Value | 0.00 | 0.00 | 450.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Adjusted end target and date of completion according to the additional investments. |
People provided with access to electricity by household connections | Value | 0.00 | 0.00 | 46650.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Adjusted end target and date of completion according to the additional investments. |
MLME has established a framework for private sector participation in electricity generation | Value | No | No | Yes |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 233000.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Adjusted end target and date of completion according to the additional investments. |
People provided with access to electricity by hhold connections-Grid | Value | 0.00 | 0.00 | 46650.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Adjusted end target and date of completion according to the additional investments. |
Female beneficiaries | Value | 0.00 | 0.00 | 49.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
HFO Storage capacity | Value | 0.00 | 0.00 | 16200.00 |
Date | May 30, 2013 | April 30, 2015 | June 30, 2018 | |
Comment |
Assessment of options for launching procurement of fuel on a competitive basis completed | Value | No | No | Yes |
Date | May 30, 2013 | April 30, 2015 | June 30, 2016 | |
Comment |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 110.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Revised end target and completion date to include the transmission line to be constructed from Monrovia to Madina via Kle undertheadditional financing. |
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 250.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Adjusted end target and date of completion according to the new investments to be done in T&D under the additional financing. |
MLME and LEC staff trained | Value | No | No | Yes |
Date | May 30, 2013 | April 30, 2015 | June 30, 2018 | |
Comment |
Length of pipeline for HFO fuel transportation constructed | Value | 0.00 | 0.00 | 1.50 |
Date | May 30, 2013 | January 30, 2015 | June 30, 2016 | |
Comment |
HFO pipeline, pumping station and storage facility in operation | Value | No | No | Yes |
Date | May 30, 2013 | April 30, 2015 | June 30, 2016 | |
Comment |
Market sounding analysis for power generation projects with private sector participation completed | Value | No | No | Yes |
Date | May 30, 2013 | April 30, 2015 | June 30, 2016 | |
Comment |
Transmission lines constructed under the project | Value | 0.00 | 0.00 | 110.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Revised end target and completion date to include the 60km transmission line to be constructed from Monrovia to Madina via Kleunder the additional financing. |
Distribution lines constructed under the project | Value | 0.00 | 0.00 | 250.00 |
Date | May 30, 2013 | April 30, 2015 | April 30, 2020 | |
Comment | Adjusted end target and date of completion according to the new investments to be done in Transmission and Distribution (T&D)underthe additional financing. |
LEC's Action plan for improving commercial management and strengthening local managerial capacity approved by LEC Board of Directors | Value | No | No | Yes |
Date | January 30, 2015 | April 30, 2015 | March 31, 2016 | |
Comment |
LEC's customers billed using the CMS | Value | 0.00 | 0.00 | 95.00 |
Date | January 30, 2015 | April 30, 2015 | April 30, 2020 | |
Comment |
Percentage of grievances processed from total grievance received | Value | 0.00 | 0.00 | 100.00 |
Date | January 30, 2015 | April 30, 2015 | April 30, 2020 | |
Comment |
CMS and IMS fully implemented | Value | No | No | Yes |
Date | January 30, 2015 | April 30, 2015 | June 30, 2018 | |
Comment |