Liberia: LACEEP Additional Financing

Development Objective

The project development objectives are to increase access to electricity and strengthen institutional capacity in the electricity sector.

Key Details

Project Details

  • P153124

  • Closed

  • Clemencia Torres De Mastle

  • N/A

  • Liberia

  • April 23, 2015

  • (as of board presentation)

    June 24, 2015

  • N/A

  • US$ 60.00 million

  • B

  • November 15, 2023

  • July 31, 2022

  • Yes

  • BANK APPROVED

  • P133445

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 60.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 60.00
IBRD + IDA Commitment 60.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 60.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Commercial and institutional customers provided with access to electricity under the projectValue0.000.00450.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentAdjusted end target and date of completion according to the additional investments.
  • People provided with access to electricity by household connectionsValue0.000.0046650.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentAdjusted end target and date of completion according to the additional investments.
  • MLME has established a framework for private sector participation in electricity generationValueNoNoYes
    DateMay 30, 2013April 30, 2015April 30, 2020
    Comment
  • Direct project beneficiariesValue0.000.00233000.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentAdjusted end target and date of completion according to the additional investments.
  • People provided with access to electricity by hhold connections-GridValue0.000.0046650.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentAdjusted end target and date of completion according to the additional investments.
  • Female beneficiariesValue0.000.0049.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • HFO Storage capacityValue0.000.0016200.00
    DateMay 30, 2013April 30, 2015June 30, 2018
    Comment
  • Assessment of options for launching procurement of fuel on a competitive basis completedValueNoNoYes
    DateMay 30, 2013April 30, 2015June 30, 2016
    Comment
  • Transmission lines constructed or rehabilitated under the projectValue0.000.00110.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentRevised end target and completion date to include the transmission line to be constructed from Monrovia to Madina via Kle undertheadditional financing.
  • Distribution lines constructed or rehabilitated under the projectValue0.000.00250.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentAdjusted end target and date of completion according to the new investments to be done in T&D under the additional financing.
  • MLME and LEC staff trainedValueNoNoYes
    DateMay 30, 2013April 30, 2015June 30, 2018
    Comment
  • Length of pipeline for HFO fuel transportation constructedValue0.000.001.50
    DateMay 30, 2013January 30, 2015June 30, 2016
    Comment
  • HFO pipeline, pumping station and storage facility in operationValueNoNoYes
    DateMay 30, 2013April 30, 2015June 30, 2016
    Comment
  • Market sounding analysis for power generation projects with private sector participation completedValueNoNoYes
    DateMay 30, 2013April 30, 2015June 30, 2016
    Comment
  • Transmission lines constructed under the projectValue0.000.00110.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentRevised end target and completion date to include the 60km transmission line to be constructed from Monrovia to Madina via Kleunder the additional financing.
  • Distribution lines constructed under the projectValue0.000.00250.00
    DateMay 30, 2013April 30, 2015April 30, 2020
    CommentAdjusted end target and date of completion according to the new investments to be done in Transmission and Distribution (T&D)underthe additional financing.
  • LEC's Action plan for improving commercial management and strengthening local managerial capacity approved by LEC Board of DirectorsValueNoNoYes
    DateJanuary 30, 2015April 30, 2015March 31, 2016
    Comment
  • LEC's customers billed using the CMSValue0.000.0095.00
    DateJanuary 30, 2015April 30, 2015April 30, 2020
    Comment
  • Percentage of grievances processed from total grievance receivedValue0.000.00100.00
    DateJanuary 30, 2015April 30, 2015April 30, 2020
    Comment
  • CMS and IMS fully implementedValueNoNoYes
    DateJanuary 30, 2015April 30, 2015June 30, 2018
    Comment