Financier | Commitments |
---|---|
Global Partnership on Output-based Aid | 3.00 |
IDA Credit | 68.00 |
P153179
Closed
Sudeshna Banerjee , Laurencia Njagi
N/A
April 18, 2016
(as of board presentation)
June 15, 2016
N/A
US$ 71.00 million
N/A
2016
US$ 71.00 million
A
Not Applicable
December 31, 2017
Yes
BANK APPROVED
September 16, 2021
Financier | Commitments |
---|---|
Global Partnership on Output-based Aid | 3.00 |
IDA Credit | 68.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 68.00 |
IBRD + IDA Commitment | 68.00 |
Lending Instrument | |
---|---|
Grant Amount | 3.00 |
Total Project Cost** | 71.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Electricity losses per year in the project area- Non-Technical | Value | 0.00 | 0.00 | 0.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
Electricity losses per year in the project area- Technical | Value | 0.00 | 0.00 | 0.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
Total net injected generation | Value | 0.00 | 1270.00 | 2020.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
People provided with access to electricity by KPLC | Value | 0.00 | 10733505.00 | 11000000.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment | This indicator captures the number of people connected to the grid by KPLC during the project period; assumes 5 people perhousehold. |
New slum consumers connected to the grid | Value | 120000.00 | 120000.00 | 174000.00 |
Date | April 30, 2016 | April 30, 2016 | December 31, 2017 | |
Comment | Consumers are households. |
Electricity losses per year in the project area | Value | 16.30 | 17.51 | 15.90 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment | The sub-indicators on non-technical and technical losses are not separately measured due to the lack of appropriate metering system. |
1. Electricity generation from renewable generation capacity constructed under the project, net | Value | 0.00 | 1270.70 | 2020.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
3. Interruptions per 1,000 customers | Value | 9.10 | 9.79 | 8.50 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
5. Direct project beneficiaries (CORE) | Value | 0.00 | 10733505.00 | 11000000.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
8. Distribution lines constructed or rehabilitated under the project (CORE) | Value | 0.00 | 4452.00 | 2280.00 |
Date | June 30, 2015 | December 31, 2017 | ||
Comment |
9. Substations constructed or rehabilitated by KPLC under the project | Value | 0.00 | 0.00 | 26.00 |
Date | June 30, 2014 | December 31, 2017 | ||
Comment |
12. Community (public facilities) electricity connections provided under the project (CORE) | Value | 0.00 | 6471.00 | 450.00 |
Date | June 30, 2015 | December 31, 2017 | ||
Comment |
13. Business electricity connections provided under the project (CORE) | Value | 0.00 | 8692.00 | 15000.00 |
Date | June 30, 2015 | December 31, 2017 | ||
Comment |
14. Roadmap for implementation of the wholesale electricity market is adopted by MoE | Value | No | Yes | Yes |
Date | June 30, 2015 | September 30, 2016 | ||
Comment | Achieved. |
15. Rural Electrification Master Plan (REMP) annually updated | Value | No | Yes | Yes |
Date | June 30, 2015 | September 30, 2016 | ||
Comment | Achieved. |
16. Cost of service study completed one year before 2014 tariff review is launched | Value | No | Yes | Yes |
Date | June 30, 2015 | September 30, 2016 | ||
Comment | Achieved. |
Community electricity connections constructed –Grid | Value | 0.00 | 6471.00 | 450.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
Distribution lines constructed under the project | Value | 0.00 | 4452.00 | 2280.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
Distribution lines rehabilitated under the project | Value | 0.00 | 0.00 | 0.00 |
Date | June 30, 2010 | June 30, 2015 | September 30, 2016 | |
Comment | Sub-indicator not applicable. |
Transmission lines rehabilitated under the project | Value | 0.00 | 0.00 | 0.00 |
Date | June 30, 2010 | June 30, 2014 | September 30, 2016 | |
Comment | Sub-indicator not applicable. |
Transmission lines constructed under the project | Value | 0.00 | 76.00 | 334.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
Generation Capacity of Renewable Energy constructed - Other | Value | 0.00 | 280.00 | 280.00 |
Date | June 30, 2010 | June 30, 2015 | September 30, 2016 | |
Comment | Achieved. |
Generation Capacity of Renewable Energy constructed-Geo-thermal | Value | 0.00 | 280.00 | 280.00 |
Date | June 30, 2010 | June 30, 2015 | September 30, 2016 | |
Comment | Achieved. |
Community Center | Value | 0.00 | 6471.00 | 450.00 |
Date | June 30, 2015 | December 31, 2017 | ||
Comment |
Meters installed under the project | Value | 0.00 | 255000.00 | 255000.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
KPLC conducts an annual customer satisfaction survey for slum consumers | Value | No | No | Yes |
Date | April 30, 2016 | April 30, 2016 | December 31, 2017 | |
Comment |
Community electricity connections constructed under the project | Value | 0.00 | 5946.00 | 450.00 |
Date | June 30, 2010 | June 30, 2014 | December 31, 2017 | |
Comment | . |
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 4452.00 | 2280.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 76.00 | 334.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |
Generation Capacity of Renewable Energy (other than hydropower) constructed | Value | 0.00 | 280.00 | 280.00 |
Date | June 30, 2010 | June 30, 2015 | September 30, 2016 | |
Comment | Achieved. |
6. Generation capacity of renewable energy (geothermal) constructed or rehabilitated under the project (CORE) | Value | 0.00 | 280.00 | 280.00 |
Date | June 30, 2010 | June 30, 2015 | September 30, 2016 | |
Comment | Achieved. |
7. Transmission lines constructed or rehabilitated under the project (CORE) | Value | 0.00 | 76.00 | 334.00 |
Date | June 30, 2010 | June 30, 2015 | December 31, 2017 | |
Comment |