Skip to Main Navigation

Additional Financing: Kenya Electricity Expansion Project

Development Objective

The project has two development objectives: (a) increase the capacity, efficiency, and quality of electricity supply; and (b) expand access to electricity in urban, peri-urban, and rural areas

Key Details

Project Details

  • P153179

  • Closed

  • Sudeshna Banerjee , Laurencia Njagi

  • N/A

  • Kenya

  • April 18, 2016

  • (as of board presentation)

    June 15, 2016

  • N/A

  • US$ 71.00 million

  • A

  • Not Applicable

  • December 31, 2017

  • Yes

  • BANK APPROVED

  • P103037

  • September 16, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Partnership on Output-based Aid 3.00
IDA Credit 68.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 68.00
IBRD + IDA Commitment 68.00
Lending Instrument
Grant Amount 3.00
Total Project Cost** 71.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Electricity losses per year in the project area- Non-TechnicalValue0.000.000.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • Electricity losses per year in the project area- TechnicalValue0.000.000.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • Total net injected generationValue0.001270.002020.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • People provided with access to electricity by KPLCValue0.0010733505.0011000000.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    CommentThis indicator captures the number of people connected to the grid by KPLC during the project period; assumes 5 people perhousehold.
  • New slum consumers connected to the gridValue120000.00120000.00174000.00
    DateApril 30, 2016April 30, 2016December 31, 2017
    CommentConsumers are households.
  • Electricity losses per year in the project areaValue16.3017.5115.90
    DateJune 30, 2010June 30, 2015December 31, 2017
    CommentThe sub-indicators on non-technical and technical losses are not separately measured due to the lack of appropriate metering system.
  • 1. Electricity generation from renewable generation capacity constructed under the project, netValue0.001270.702020.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • 3. Interruptions per 1,000 customersValue9.109.798.50
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • 5. Direct project beneficiaries (CORE)Value0.0010733505.0011000000.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 8. Distribution lines constructed or rehabilitated under the project (CORE)Value0.004452.002280.00
    DateJune 30, 2015December 31, 2017
    Comment
  • 9. Substations constructed or rehabilitated by KPLC under the projectValue0.000.0026.00
    DateJune 30, 2014December 31, 2017
    Comment
  • 12. Community (public facilities) electricity connections provided under the project (CORE)Value0.006471.00450.00
    DateJune 30, 2015December 31, 2017
    Comment
  • 13. Business electricity connections provided under the project (CORE)Value0.008692.0015000.00
    DateJune 30, 2015December 31, 2017
    Comment
  • 14. Roadmap for implementation of the wholesale electricity market is adopted by MoEValueNoYesYes
    DateJune 30, 2015September 30, 2016
    CommentAchieved.
  • 15. Rural Electrification Master Plan (REMP) annually updatedValueNoYesYes
    DateJune 30, 2015September 30, 2016
    CommentAchieved.
  • 16. Cost of service study completed one year before 2014 tariff review is launchedValueNoYesYes
    DateJune 30, 2015September 30, 2016
    CommentAchieved.
  • Community electricity connections constructed –GridValue0.006471.00450.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • Distribution lines constructed under the projectValue0.004452.002280.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • Distribution lines rehabilitated under the projectValue0.000.000.00
    DateJune 30, 2010June 30, 2015September 30, 2016
    CommentSub-indicator not applicable.
  • Transmission lines rehabilitated under the projectValue0.000.000.00
    DateJune 30, 2010June 30, 2014September 30, 2016
    CommentSub-indicator not applicable.
  • Transmission lines constructed under the projectValue0.0076.00334.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • Generation Capacity of Renewable Energy constructed - OtherValue0.00280.00280.00
    DateJune 30, 2010June 30, 2015September 30, 2016
    CommentAchieved.
  • Generation Capacity of Renewable Energy constructed-Geo-thermalValue0.00280.00280.00
    DateJune 30, 2010June 30, 2015September 30, 2016
    CommentAchieved.
  • Community CenterValue0.006471.00450.00
    DateJune 30, 2015December 31, 2017
    Comment
  • Meters installed under the projectValue0.00255000.00255000.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • KPLC conducts an annual customer satisfaction survey for slum consumersValueNoNoYes
    DateApril 30, 2016April 30, 2016December 31, 2017
    Comment
  • Community electricity connections constructed under the projectValue0.005946.00450.00
    DateJune 30, 2010June 30, 2014December 31, 2017
    Comment.
  • Distribution lines constructed or rehabilitated under the projectValue0.004452.002280.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • Transmission lines constructed or rehabilitated under the projectValue0.0076.00334.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment
  • Generation Capacity of Renewable Energy (other than hydropower) constructedValue0.00280.00280.00
    DateJune 30, 2010June 30, 2015September 30, 2016
    CommentAchieved.
  • 6. Generation capacity of renewable energy (geothermal) constructed or rehabilitated under the project (CORE)Value0.00280.00280.00
    DateJune 30, 2010June 30, 2015September 30, 2016
    CommentAchieved.
  • 7. Transmission lines constructed or rehabilitated under the project (CORE)Value0.0076.00334.00
    DateJune 30, 2010June 30, 2015December 31, 2017
    Comment