Kiribati Aviation Investment Project Additional Financing

Development Objective

The project development objective is to improve operational safety and oversight of international air transport and associated infrastructure.

Key Details

Project Details

  • P153381

  • Closed

  • Pierre Graftieaux , Christopher Bennett

  • N/A

  • Kiribati

  • December 30, 2015

  • (as of board presentation)

    March 9, 2016

  • N/A

  • US$ 12.45 million

  • B

  • July 15, 2021

  • June 30, 2019

  • Yes

  • BANK APPROVED

  • P128938

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 1.88
Pacific Regional Infrastructure Facility Trust Fund 5.35
IDA Grant 7.10

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 7.10
IBRD + IDA Commitment 7.10
Lending Instrument
Grant Amount 5.35
Total Project Cost** 14.33

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator One: ICAO certification of safety and security at project airportsValueNeither CXI or TRW certiifedNeither CXI or TRW certifiedCertification of airports in accordance with agree
    DateDecember 13, 2011October 22, 2015December 31, 2018
    CommentAt the onset of KAIP, airports were audited by ICAO and were not certified for safety and security due to a series of shortcomings,which the project aims to address.A detailed assessment of both airports will be undertaken at project end with support from PASO.
  • Indicator Two: State requirement for safety and security reaches global ICAO averageValue95.0095.0049.00
    DateDecember 13, 2011October 22, 2015December 31, 2018
    CommentMeasured by USOAP
  • Indicator Three: Modernization of air traffic managementValueno PASNet or ADS-Bno PASNet or ADS-BPASNet and ADS-B operational
    DateDecember 13, 2011October 22, 2015December 31, 2018
    CommentMeasures the installation of ADS-B, and VSAT.
  • Indicator Four: Implementation of a regional safety and security levy for international passengersValueno levyLevy being collected.AU$5 collected from each departing international p
    DateDecember 13, 2011October 22, 2015June 30, 2013
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of coastal protection constructedValue0.000.00180.00
    DateNovember 15, 2015December 31, 2018
    Comment
  • Component A: Intermediate Result indicator One: Navigation and safety aids fully operationalValue0.0010.00100.00
    DateDecember 13, 2011October 22, 2015December 31, 2018
    Comment100 % of project-financed infrastructure
  • Component A: Intermediate Result indicator Two: Bonriki and Cassidy terminals upgradedValue0.0010.00100.00
    DateDecember 13, 2011October 22, 2015December 31, 2018
    Comment
  • Component A: Intermediate Result indicator Three: Achievement of Fire Safety Standards at Bonriki and Cassidy airportsValueCategory 3Category 3Category 6
    DateDecember 13, 2011October 22, 2015December 31, 2018
    Comment
  • Component B: Intermediate Result indicator One: Adoption of an Air Transport Master PlanValueNo planPlan adoptedPlan adopted
    DateDecember 13, 2011October 22, 2015June 30, 2014
    Comment
  • Component B: Intermediate Result indicator Two: Separation of civil aviation regulatory functions from operationsValueMCTTD performs all functionsMCTTD performs all functionsRegulatory functions separated
    DateDecember 13, 2011October 22, 2015June 30, 2013
    Comment
  • Component B: Intermediate Result indicator Three: Successful implementation of agreed training planValueNo training planTraining needs assessment completed. ImplementatioTraining plan completed
    DateDecember 13, 2011October 22, 2015December 31, 2018
    Comment
  • Component C: Intermediate Result indicator One: Award of contract for airport management and operations supportValueAirport operated by MCTTDAirport operated by MCTTD.Contract awarded and operational
    DateDecember 13, 2011October 22, 2015December 31, 2016
    Comment