Financier | Commitments |
---|---|
Borrower/Recipient | 1.88 |
Pacific Regional Infrastructure Facility Trust Fund | 5.35 |
IDA Grant | 7.10 |
P153381
Closed
Pierre Graftieaux , Christopher Bennett
N/A
December 30, 2015
(as of board presentation)
March 9, 2016
N/A
US$ 14.33 million
N/A
2016
US$ 12.45 million
B
July 15, 2021
June 30, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 1.88 |
Pacific Regional Infrastructure Facility Trust Fund | 5.35 |
IDA Grant | 7.10 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 7.10 |
IBRD + IDA Commitment | 7.10 |
Lending Instrument | |
---|---|
Grant Amount | 5.35 |
Total Project Cost** | 14.33 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Indicator One: ICAO certification of safety and security at project airports | Value | Neither CXI or TRW certiifed | Neither CXI or TRW certified | Certification of airports in accordance with agree |
Date | December 13, 2011 | October 22, 2015 | December 31, 2018 | |
Comment | At the onset of KAIP, airports were audited by ICAO and were not certified for safety and security due to a series of shortcomings,which the project aims to address. | A detailed assessment of both airports will be undertaken at project end with support from PASO. |
Indicator Two: State requirement for safety and security reaches global ICAO average | Value | 95.00 | 95.00 | 49.00 |
Date | December 13, 2011 | October 22, 2015 | December 31, 2018 | |
Comment | Measured by USOAP |
Indicator Three: Modernization of air traffic management | Value | no PASNet or ADS-B | no PASNet or ADS-B | PASNet and ADS-B operational |
Date | December 13, 2011 | October 22, 2015 | December 31, 2018 | |
Comment | Measures the installation of ADS-B, and VSAT. |
Indicator Four: Implementation of a regional safety and security levy for international passengers | Value | no levy | Levy being collected. | AU$5 collected from each departing international p |
Date | December 13, 2011 | October 22, 2015 | June 30, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of coastal protection constructed | Value | 0.00 | 0.00 | 180.00 |
Date | November 15, 2015 | December 31, 2018 | ||
Comment |
Component A: Intermediate Result indicator One: Navigation and safety aids fully operational | Value | 0.00 | 10.00 | 100.00 |
Date | December 13, 2011 | October 22, 2015 | December 31, 2018 | |
Comment | 100 % of project-financed infrastructure |
Component A: Intermediate Result indicator Two: Bonriki and Cassidy terminals upgraded | Value | 0.00 | 10.00 | 100.00 |
Date | December 13, 2011 | October 22, 2015 | December 31, 2018 | |
Comment |
Component A: Intermediate Result indicator Three: Achievement of Fire Safety Standards at Bonriki and Cassidy airports | Value | Category 3 | Category 3 | Category 6 |
Date | December 13, 2011 | October 22, 2015 | December 31, 2018 | |
Comment |
Component B: Intermediate Result indicator One: Adoption of an Air Transport Master Plan | Value | No plan | Plan adopted | Plan adopted |
Date | December 13, 2011 | October 22, 2015 | June 30, 2014 | |
Comment |
Component B: Intermediate Result indicator Two: Separation of civil aviation regulatory functions from operations | Value | MCTTD performs all functions | MCTTD performs all functions | Regulatory functions separated |
Date | December 13, 2011 | October 22, 2015 | June 30, 2013 | |
Comment |
Component B: Intermediate Result indicator Three: Successful implementation of agreed training plan | Value | No training plan | Training needs assessment completed. Implementatio | Training plan completed |
Date | December 13, 2011 | October 22, 2015 | December 31, 2018 | |
Comment |
Component C: Intermediate Result indicator One: Award of contract for airport management and operations support | Value | Airport operated by MCTTD | Airport operated by MCTTD. | Contract awarded and operational |
Date | December 13, 2011 | October 22, 2015 | December 31, 2016 | |
Comment |