LA-Poverty Reduction Fund II - AF

Development Objective

Help improve the access to and the utilization of basic infrastructure and services for the Project's targeted poor communities. The PDO would be achieved through inclusive community and local development processes with emphasis on ensuring sustainability.

Key Details

Project Details

  • P153401

  • Closed

  • Erik Johnson , Sybounheuang Phandanouvong

  • N/A

  • US$ 14.00 million

  • B

  • September 8, 2022

  • December 31, 2016

  • BANK APPROVED

  • P123480

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 11.60
Lao PDR - Free-standing Trust Fund Program 2.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 11.60
IBRD + IDA Commitment 11.60
Lending Instrument
Grant Amount 2.40
Total Project Cost** 14.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Decision-making on allocation of PRF resources involve at least 40% womenValue0.0053.0040.00
    DateJune 9, 2011December 5, 2014December 31, 2016
    CommentInvolvement of 60% of poor in decision making would be dropped due to difficulty to separate poor from non-poor participants ofcommunity meetings. The Deepen CDD pilot would continue to roll out under AF which allows separating poor from non poor
  • Direct project beneficiariesValue0.00474600.00700000.00
    DateJune 9, 2011December 5, 2014December 31, 2016
    CommentTarget value changed to accommodate the AF. The target value of female beneficiaries is modified per implementation experience
  • Improved access to and utilization of basic economic and social services in kum bans supported by PRFValue0The supplementary school enrollment indicator has
    DateOctober 31, 2012December 5, 2014December 31, 2016
    CommentEnd targets have been set for different types of sub-projects.Respective sub-indicators will be assessed through the impact evaluation, and will be available by March 2016
  • Greater than 75% satisfaction levels reported by beneficiaries in targeted villages regarding improved services and local development planningValue0.0080.0075.00
    DateJune 9, 2011December 31, 2013December 31, 2016
    CommentOriginal target which was incorrectly set above the target value in the indicator corrected.. This indicator will be assessedthrough the impact evaluation, and will be available by March 2016
  • Female beneficiariesValue0.0049.6050.00
    DateJune 9, 2011December 5, 2014December 31, 2016
    Comment
  • Lowest two quintiles benefit from above servicesValueNoYesYes
    DateOctober 31, 2012December 5, 2014December 31, 2016
    Comment
  • % increase in school enrollmentValue89.000.006.00
    DateOctober 31, 2012December 5, 2014December 31, 2016
    Comment
  • % of HHs with access to and utilization of health servicesValue37.000.0043.00
    DateOctober 31, 2012December 5, 2014December 31, 2016
    Comment
  • % of HHs with improved access to and utilization of safe water resourcesValue76.000.0084.00
    DateOctober 31, 2012December 5, 2014December 31, 2016
    Comment
  • % of HHs with access to all weather roadsValue30.000.0038.00
    DateOctober 31, 2012December 5, 2014December 31, 2016
    Comment
  • Ethnic beneficiariesValue0.0072.0070.00
    DateJune 9, 2011December 5, 2014December 31, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • #/type of sub-project activities implementedValue0.00988.001600.00
    DateJune 9, 2011December 31, 2014December 31, 2016
    CommentTarget changed to accommodate the AF.
  • x% of sub-project activities are of high technical qualityValue0.0030.0085.00
    DateJune 9, 2011December 31, 2013December 31, 2016
    Comment
  • x% of sub-projects are being maintained and are operational two years after sub-project completionValue0.0098.5090.00
    DateJune 9, 2011December 31, 2013December 31, 2016
    Comment
  • # of communities able to plan, implement and monitor their activitiesValue0.00850.001300.00
    DateJune 9, 2011December 24, 2014December 31, 2016
    CommentSemi annual reportTarget changed to accommodate the AF.
  • % of districts where district officials provide technical assistance and supervision to communitiesValue0.0095.0085.00
    DateJune 9, 2011December 24, 2014December 31, 2016
    CommentSemi annual report
  • Progress reports prepared on timeValue011
    DateJune 9, 2011November 11, 2014December 31, 2016
    Comment
  • % PRF kum ban plans used by government and/or other development actors for planning and fundingValue0.0019.0035.00
    DateJune 9, 2011December 31, 2014December 31, 2016
    CommentSemi annual report
  • X studies/evaluations completed in a timely mannerValue0.006.005.00
    DateJune 9, 2011December 31, 2014December 31, 2016
    Comment
  • Participants in consultation activities during project implementation (number)Value0.00315896.000.00
    DateJune 9, 2011December 31, 2014December 31, 2016
    CommentTarget to be defined by PRF
  • Community contribution in the total project costs (percentage)Value0.0011.000.00
    DateDecember 4, 2014December 31, 2016
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.003.400.00
    DateDecember 5, 2014December 31, 2016
    Comment
  • Sub-projects with post-project community engagement or O&M arrangements (%)Value0.0064.0090.00
    DateJune 9, 2011December 31, 2013December 31, 2016
    CommentEnd target of >90% of sub projects are being maintained and operational two years after sub-project completion.
  • Participants in consultation activities during project implementation - femaleValue0.00155222.000.00
    DateJune 9, 2011December 31, 2014December 31, 2016
    CommentSemi annual report.No target was set, however, PRF will collect information on this indicator through the MIS
  • Total community contribution (US$)Value0.001640000.000.00
    DateDecember 4, 2014December 31, 2016
    Comment
  • Grievances related to delivery of project benefits that are addressed-(number)Value0.009.000.00
    DateDecember 5, 2014December 31, 2016
    Comment
  • Sub-projects that are expected to have a mechanism for post-completion operationValue0.0064.0090.00
    DateJune 9, 2011December 31, 2013December 31, 2016
    Comment
  • Improvement in dietary diversity among pregnant/ lactating women and children aged 6-24 monthsValue0.000.0030.00
    DateSeptember 1, 2015December 31, 2016
    CommentJSDF funded nutrition activities started too recently to achieve outcome yet.Impact data to be collected through Endline survey
  • No. and type of livelihood activities supported by seed grantValue1675.000.002400.00
    DateSeptember 1, 2015December 31, 2016
    CommentCurrent achievement under JSDF funded livelihood activitiesImpact data to be collected through Endline survey
  • % of beneficiary communities that successfully achieved Open Defecation Free (ODF) statusValue0.000.0030.00
    DateSeptember 1, 2015December 31, 2016
    CommentInformation will be collected through MIS
  • Community contribution in the total project costs (%)Value0.0011.0010.00
    DateJune 9, 2011December 4, 2014December 31, 2016
    CommentSemi annual reportThis indicator is re-entered to remove the redundant sub-indicator. No end target was set for this indicator. PRF will monitorthrough the MIS. Data on community contribution after sub-project completion for O&M will be collected under 6/ 12 months followingvisits.
  • Grievances registered related to delivery of project benefits addressed (%)Value0.0085.0090.00
    DateJune 9, 2011December 5, 2014December 31, 2016
    CommentSemi annual reportThis indicator is re-entered as new to remove the redundant sub-indicator. Target is revised to be expressed in %. Only thosegrievances related to the delivery of project benefits are measured.
  • Sub-projects with post-project community engagement or O&M arrangements (%)Value0.0064.0090.00
    DateJune 9, 2011December 31, 2013December 31, 2016
    CommentTechnical and Cost Effectiveness surveyThis indicator is re-entered as new to remove the redundant sub-indicator. Steps already taken to strengthen O&M arrangements. 6/12 months follow-up visits will monitor this indicator. Results will be entered into MIS.