The development objective of the Electricity Access Expansion Project for Niger is to increase access to electricity in Niger. The project comprises of two components. The first component, extension and reinforcement of distribution systems will support the expansion, reinforcement, densification, and rehabilitation of medium and low voltage (MV and LV) distribution systems to allow the connection of 60,000 new connections in seven major urban areas...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

<p>The Project Development Objective (PDO) is to increase access to electricity.</p>

Key Details

Project Details

  • P153743

  • Closed

  • Emmanuel Py , Abdoulaye Magagi Daga

  • Government of the Republic of Niger - Ministre du Plan,Ministere du Plan,Government of the Republic of Niger

  • Niger

  • February 3, 2015

  • (as of board presentation)

    December 16, 2015

  • June 21, 2016

  • US$ 65.00 million

  • B

  • Not Applicable

  • December 31, 2024

  • Yes

  • BANK APPROVED

  • April 22, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 54.50
IDA Grant 10.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 65.00
IBRD + IDA Commitment 65.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 65.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 30, 2024 IDA-57550 Loan Repay 16,073.63
May 3, 2024 IDA-57550 Loan Repay 784,234.94
Jul 18, 2024 IDA-63050 Loan Disb 64,378.18
May 3, 2024 IDA-57550 Loan Repay 832,543.75
May 3, 2024 IDA-63050 Int Charges 138,266.16
May 3, 2024 IDA-63050 Int Charges 138,266.16
May 10, 2024 IDA-57550 Loan Repay 28,243.96
Jul 2, 2024 IDA-63050 Loan Disb 377,239.70
Aug 23, 2024 IDA-63050 Loan Disb 1,515,779.00
Aug 23, 2024 IDA-63050 Loan Disb 1,572,619.00
Apr 30, 2024 IDA-63050 Int Charges 136,502.47
Apr 30, 2024 IDA-63050 Int Charges 136,502.47
Apr 30, 2024 IDA-57550 Loan Repay 188,377.48
Apr 30, 2024 IDA-57550 Int Charges 188,377.48
Apr 30, 2024 IDA-57550 Int Charges 188,377.48
Apr 30, 2024 IDA-57550 Loan Repay -188,377.48
Apr 30, 2024 IDA-57550 Int Charges 3,117.79
Apr 30, 2024 IDA-57550 Int Charges 3,117.79
Apr 30, 2024 IDA-57550 Int Charges 185,259.66
Apr 30, 2024 IDA-57550 Int Charges 185,259.66
Jun 2, 2023 IDA-63050 Loan Disb 289,332.00
Jun 2, 2023 IDA-63050 Loan Disb 474,900.30
Jun 2, 2023 IDA-63050 Loan Disb 375,811.60
Jun 2, 2023 IDA-63050 Loan Disb 40,311.38
Jul 28, 2023 IDA-63050 Loan Disb 161,630.03
Jul 28, 2023 IDA-63050 Loan Disb 41,585.26
Mar 15, 2023 IDA-57550 Loan Repay 189,683.55
Mar 15, 2023 IDA-57550 Loan Repay 633,870.20
Mar 15, 2023 IDA-57550 Int Charges 189,683.55
Mar 15, 2023 IDA-57550 Int Charges 189,683.55
Apr 24, 2023 IDA-57550 Loan Disb -9,726,863.00
Aug 31, 2018 IDA-63050 Loan Commitment 56,000,000.00
Aug 31, 2018 IDA-D3650 Loan Commitment 14,000,000.00
Dec 16, 2015 IDA-57550 Loan Commitment 54,500,000.00
Dec 16, 2015 IDA-D0980 Loan Commitment 10,500,000.00
Dec 12, 2017 IDA-D0980 Loan Disb 354,643.34
Jun 7, 2019 IDA-57550 Loan Disb 9,140,454.00
Mar 19, 2019 IDA-57550 Int Charges 116,233.12
Mar 19, 2019 IDA-57550 Int Charges 116,233.12
Mar 19, 2019 IDA-57550 Int Charges 113.55
Mar 19, 2019 IDA-57550 Int Charges 113.55
Nov 15, 2018 IDA-57550 Loan Disb 5,955,594.00
Nov 15, 2018 IDA-57550 Loan Disb -5,955,594.00
Dec 19, 2018 IDA-57550 Loan Disb 7,757,228.50
Sep 18, 2018 IDA-57550 Int Charges 104,253.80
Sep 18, 2018 IDA-57550 Int Charges 104,253.80
Mar 20, 2018 IDA-57550 Int Charges 69,451.08
Mar 20, 2018 IDA-57550 Int Charges 69,451.08
Mar 20, 2018 IDA-57550 Loan Disb 11,119,196.00
Sep 20, 2017 IDA-57550 Int Charges 55,632.14
Sep 20, 2017 IDA-57550 Int Charges 55,632.14
Mar 21, 2017 IDA-57550 Int Charges 15,436.20
Mar 21, 2017 IDA-57550 Int Charges 15,436.20
Mar 21, 2017 IDA-57550 Int Charges 1,629.37
Mar 21, 2017 IDA-57550 Int Charges 1,629.37
Mar 29, 2017 IDA-57550 Loan Disb 1,768,068.60
May 3, 2017 IDA-57550 Loan Disb 10,465,309.00
Aug 26, 2016 IDA-57550 Loan Disb 4,302,873.50
Aug 16, 2024 IDA-D3650 Loan Disb 10,135,458.00
Aug 27, 2024 IDA-D3650 Loan Disb 449,866.62
Aug 14, 2024 IDA-D3650 Loan Disb 35,790.39
Aug 8, 2024 IDA-D3650 Loan Disb 1,484,389.80
May 19, 2022 IDA-D0980 Loan Disb 1,601,794.00
Apr 1, 2021 IDA-D0980 Loan Disb 8,405,538.00
Apr 15, 2023 IDA-63050 Int Charges 115,663.39
Apr 15, 2023 IDA-63050 Int Charges 115,663.39
Apr 24, 2023 IDA-57550 Loan Disb 9,726,863.00
Sep 15, 2022 IDA-57550 Loan Repay 773,450.00
Sep 15, 2022 IDA-57550 Int Charges 180,029.60
Sep 15, 2022 IDA-57550 Int Charges 180,029.60
Oct 15, 2022 IDA-63050 Int Charges 47,202.05
Oct 15, 2022 IDA-63050 Int Charges 47,202.05
Dec 5, 2022 IDA-63050 Loan Disb 19,588,182.00
May 18, 2022 IDA-63050 Loan Disb 9,012,369.00
Mar 15, 2022 IDA-57550 Loan Repay 652,721.94
Mar 15, 2022 IDA-57550 Int Charges 199,545.58
Mar 15, 2022 IDA-57550 Int Charges 199,545.58
Mar 15, 2022 IDA-57550 Loan Repay 199,545.58
Apr 15, 2022 IDA-63050 Int Charges 22,307.70
Apr 15, 2022 IDA-63050 Int Charges 22,307.70
May 19, 2022 IDA-57550 Loan Disb 802,491.60
Oct 28, 2021 IDA-63050 Loan Disb 6,884,855.50
Sep 17, 2021 IDA-57550 Int Charges 212,525.16
Sep 17, 2021 IDA-57550 Int Charges 212,525.16
Apr 7, 2021 IDA-57550 Loan Disb 2,844,477.20
Mar 15, 2021 IDA-57550 Int Charges 205,783.05
Mar 15, 2021 IDA-57550 Int Charges 205,783.05
Sep 18, 2020 IDA-57550 Int Charges 202,511.19
Sep 18, 2020 IDA-57550 Int Charges 202,511.19
Mar 15, 2020 IDA-57550 Int Charges 163,161.34
Mar 15, 2020 IDA-57550 Int Charges 163,161.34
Mar 25, 2020 IDA-57550 Loan Disb 7,569,913.00
Mar 15, 2020 IDA-57550 Int Charges 111.59
Mar 15, 2020 IDA-57550 Int Charges 111.59
Sep 17, 2019 IDA-57550 Int Charges 110.25
Sep 17, 2019 IDA-57550 Int Charges 145,800.86
Sep 17, 2019 IDA-57550 Int Charges 145,800.86
Sep 17, 2019 IDA-57550 Int Charges 110.25
Apr 30, 2024 IDA-57550 Loan Repay 4,058.34

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-12-18
Progress towards achievement of PDO Satisfactory 2024-12-18
Financial Management Satisfactory 2024-12-18
Monitoring and Evaluation Satisfactory 2024-12-18
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-18
Procurement Moderately Satisfactory 2024-12-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with new or improved electricity serviceValue0.00652420.00736000.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • of which females (percentage)Value49.6049.6049.60
    Date
    Comment
  • Non-household connections provided with access to electricity under the projectValue0.00554.0015000.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Direct project beneficiariesValue0.00652974.00751000.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • of which, grievances submitted by womenValue0.0014.0030.00
    Date
    Comment
  • Substation supply capacityValue270.00366.00455.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Number of times MV feeders affected by the project are cut offValue85.0080.0040.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • National Electrification Strategy adopted by the GovernmentValueNoYesYes
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Transmission lines rehabilitated under the projectValue0.000.0035.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Household provided with access to electricity under the projectValue0.00102100.00115000.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Cities with completed georeferenced electricity systemsValue1.008.007.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Beneficiary satisfaction survey completed and publishedValueNoNoYes
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • of which, connections provided to female-headed householdsValue0.009.005.00
    Date
    Comment
  • Number of total electricity connections completed in urban areas under the projectValue0.00102654.00125500.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Percent survey completed by womenValue0.000.0050.00
    Date
    Comment
  • Number of total electricity connections completed in rural areas under the projectValue0.000.004500.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Distribution lines constructed or rehabilitated under the projectValue0.00973.502030.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Distribution lines constructed under the project in rural areasValue0.000.00135.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Distribution lines constructed under the project in urban areasValue0.00939.401260.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Distribution lines rehabilitated under the projectValue0.0062.00635.00
    DateDecember 31, 2015October 31, 2022December 31, 2023
    Comment
  • Project-related grievances registered under the project GRM and addressedValue0.00100.00100.00
    DateDecember 31, 2015April 29, 2022December 31, 2023
    Comment