Financier | Commitments |
---|---|
Pacific Regional Infrastructure Facility Trust Fund | 7.00 |
IDA Grant | 6.00 |
P154012
Closed
Pierre Graftieaux , Christopher Bennett
N/A
December 18, 2014
(as of board presentation)
March 31, 2015
N/A
US$ 18.97 million
N/A
2015
US$ 13.00 million
B
July 15, 2021
June 30, 2018
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Pacific Regional Infrastructure Facility Trust Fund | 7.00 |
IDA Grant | 6.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 6.00 |
IBRD + IDA Commitment | 6.00 |
Lending Instrument | |
---|---|
Grant Amount | 7.00 |
Total Project Cost** | 18.97 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Rural roads rehabilitated | Value | 0.00 | 3.00 | 8.10 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment | Indicator changed to be consistent with IDA Core indicators. | Civil works are not scheduled to be completed until mid-2015. Rural roads consist of Buota (2.0 km) and part of Temaiku Loop (6.1km). |
An agreed plan for reform of road sector management and financing under implementation | Value | No plan for sector reform | Assignment awarded. | Sector reform plan under implementation |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment | This activity will now be undertaken under the Kiribati Aviation Investment Project as it has become a multi-sector studyincludingmaritime and aviation. The assignment has been awarded. |
Roads rehabilitated, Non-rural | Value | 0.00 | 0.00 | 32.70 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment | The non-rural roads consist of the main road (23.9 km), airport road (2.2 km), Betio feeder roads (3.5 km), and Bikenibeu feederroads (3.1 km). |
Roads in good and fair condition as a share of total classified roads | Value | 18.00 | 18.00 | 90.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment | New IDA core indicator. | IRI of 5-8 and 8-15 respectively. |
Direct project beneficiaries | Value | 50100.00 | 50100.00 | 60000.00 |
Date | January 1, 2010 | November 7, 2014 | June 30, 2018 | |
Comment |
Size of the total classified network | Value | 45.00 | 45.00 | 45.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment |
Female beneficiaries | Value | 51.70 | 51.70 | 51.70 |
Date | January 1, 2010 | November 7, 2014 | June 30, 2018 | |
Comment |
Number of kilometers of roads under regular maintenance | Value | 0.00 | 3.00 | 56.00 |
Date | June 1, 2010 | June 30, 2016 | ||
Comment | Based on all the primary and secondary roads receiving regular maintenance. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component A - Intermediate Result Indicator 1: Number of kilometers of paved roads improved | Value | 0.00 | 3.15 | 26.10 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment | Pavements completed on two causeways, other sections will soon be paved. Kerbing and U-drains making good progress. |
Component A - Intermediate Result Indicator 3: Number of kilometers of unpaved roads improved | Value | 0.00 | 0.00 | 2.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment | Unpaved road improvements will start during the next six months. |
Roads in good and fair condition as a share of total classified roads | Value | 20.00 | 17.00 | 95.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment | Road network deterioration on existing sections is slowing as many are now being maintained by the Contractor. Pavements completedon two causeways. |
Component A - Intermediate Result Indicator 4: Average travel speed St Anne’s to Ananau Causeway | Value | 20.00 | 20.00 | 40.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment | Speed measured in km/hour | The short sections of paving completed have slightly increased average speeds. |
Component B - Intermediate Result Indicator 1: Land Transport Institutional Review Study | Value | No study | Assignment awarded | Study under implementation |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment | This activity will now be undertaken under the Kiribati Aviation Investment Project as it has become a multi-sector studyincludingmaritime and aviation. The assignment has been awarded. |
Component B - Intermediate Result Indicator 1: Number of micro-enterprises for routine road maintenance in South Tarawa commercially active for two or more consecutive years | Value | 0.00 | 0.00 | 3.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment | Consultant mobilized. Initial report received. |
Component B - Intermediate Result Indicator 2: Adoption and implementation of National Road Safety Action Plan | Value | No National Road Safety Action Plan | Draft Road Safety Action Plan | Strategy under implementation |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment |
Component B - Intermediate Result Indicator 4: Adoption and implementation of Road Emergency Response Plan | Value | No Road Emergency Response Plan | No Road Emergency Response Plan | Plan under implementation |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment | This activity to be removed from project when restructured as no longer required. |
Component A - Intermediate Result Indicator 5: Number of speed humps | Value | 20.00 | 20.00 | 56.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment |
Component A- Intermediate Results Indicator 6: Length of additional footpath | Value | 0.00 | 0.00 | 67.00 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment |
Component A - Intermediate Result Indicator 2: Number of kilometers of unpaved roads paved. | Value | 0.00 | 0.00 | 12.70 |
Date | June 1, 2010 | November 7, 2014 | June 30, 2015 | |
Comment |
Component B - Intermediate Result Indicator 3: Drafting of revised Road Safety Legislation | Value | No Draft Road Safety Legislation | No Draft Road Safety Legislation | Road Safety Legislation drafted |
Date | June 1, 2010 | November 7, 2014 | June 30, 2016 | |
Comment |