Financier | Commitments |
---|---|
IDA Credit | 176.71 |
Borrower/Recipient | 28.50 |
P154127
Closed
Md. Iqbal , Sheoli Pargal
N/A
September 9, 2015
(as of board presentation)
November 13, 2015
N/A
US$ 205.21 million
N/A
2016
US$ 176.71 million
A
February 28, 2022
December 31, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 176.71 |
Borrower/Recipient | 28.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 176.71 |
IBRD + IDA Commitment | 176.71 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 205.21 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Additional annual electricity delivered to grid (in billion kWh): peak and off-peak: 2.49 | Value | 0 | 0.00 | At least 2.49 billionkWh delivered to grid.Peak: |
Date | April 1, 2009 | August 3, 2015 | December 31, 2017 | |
Comment | No kWh generated as CCPP is under construction. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
O&M Contracts budgeted and implemented | Value | Limited O&M capacity of EGCB | O&M for Siddhirganj 2x120 MW peaking units is prov | EGCB runs the 335 MW CCPP on global O&M protocols. |
Date | April 1, 2009 | August 3, 2015 | December 31, 2019 | |
Comment | Rebidding done as no responsive bids received in the first round bidding. Bids are under evaluation. |
ERP functional and generating reports | Value | Information based on past data and records | Information is based on past data and records. Bot | ERP go live and is generating reports. |
Date | April 1, 2009 | August 3, 2015 | June 30, 2018 | |
Comment | Rebidding done as no responsive bids received in the first round bidding. Bids are under evaluation. |
Transmission lines constructed under the project | Value | 0.00 | 11.00 | 11.00 |
Date | April 1, 2009 | August 3, 2015 | March 31, 2016 | |
Comment | Installation of Power evacuation system is complete and evacuating 235 MW of power of other power stations. | 11 km 230 kV power evacuation system built, transfers at least 2.49 billion kWh to grid. |
Generation Capacity of Conventional Generation constructed under the project | Value | 0.00 | 0.00 | 335.00 |
Date | April 1, 2009 | August 3, 2015 | December 31, 2016 | |
Comment | Construction of the 335 MW Siddhirganj CCPP is ongoing. Pre-commissioning activities of GT has started. | 335 MW CCPP built and operational. |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 11.00 | 11.00 |
Date | April 1, 2009 | April 21, 2015 | March 31, 2016 | |
Comment |
60 km gas transmission line constructed | Value | 0.00 | 60.00 | 60.00 |
Date | April 1, 2009 | August 3, 2015 | June 30, 2016 | |
Comment | Pipeline installation complete and flowing upstream gas. Pre-commissioing gas for CCPP is available. | 60 km gas supply line supplies gas to 335 MW CCPP and the other 1,300 MW power plants at Siddhirganj. |
Projected lifetime fuel savings | Value | 0.00 | 0.00 | 218.60 |
Date | April 1, 2009 | August 3, 2015 | December 31, 2017 | |
Comment | 0.00 The CCPP is not yet ready to burn fuel. | 218.6 petajoule life time fuel saving achieved. |