Local and Regional Competitiveness Project

Abstract*

The objective of the Local and Regional Competitiveness Project (LRCP) for Macedonia is to enhance the contribution of tourism to local economic development and improve the capacity of the government and public entities to foster tourism growth and facilitate destination management. There are four components to the project, the first component being technical assistance for tourism development. This component will improve the capacity of institutions...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

<p>The Project Development Objective (PDO) is to enhance the contribution of tourism to local economic development and improve the capacity of the government and public entities to foster tourism growth and facilitate destination management.</p>

Key Details

Project Details

  • P154263

  • Closed

  • Raha Shahidsaless

  • Government of the Republic of North Macedonia

  • North Macedonia

  • April 8, 2015

  • (as of board presentation)

    January 12, 2016

  • July 28, 2016

  • US$ 26.08 million

  • Cabinet of the Deputy Prime Minister for Economic Affairs

  • Europe and Central Asia

  • 2016

  • US$ 19.36 million

  • B

  • Not Applicable

  • September 30, 2021

  • Yes

  • BANK APPROVED

  • April 29, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Sources of Borrowing Country 3.11
Free-standing TFs for ECA CU4 Country Unit 19.36
Borrower/Recipient 3.62

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 19.36
Total Project Cost** 26.08

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2021-06-24
Monitoring and Evaluation Moderately Satisfactory 2021-06-24
Progress towards achievement of PDO Moderately Unsatisfactory 2021-06-24
Procurement Moderately Satisfactory 2021-06-24
Overall Implementation Progress (IP) Moderately Unsatisfactory 2021-06-24
Project Management Moderately Satisfactory 2021-06-24
Counterpart Funding Moderately Satisfactory 2021-06-24

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 04-29-2022
OutcomesModerately Unsatisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-03-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Additional private investment generated in tourism-related activities at beneficiary destinations (US$, cumulative)Value0.0010018961.000.00
    DateJanuary 12, 2016September 30, 2021
    Comment
  • Destination Management partnerships formedValue0.000.000.00
    DateOctober 31, 2019September 30, 2021
    Comment
  • Increase in tourism-related jobs in beneficiary destinationsValue0.006.877.00
    DateJanuary 12, 2016August 30, 2021December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Destination management capacity built, as measured by public and private stakeholders trained in destination management and developmentValue0.00206.00100.00
    DateJanuary 12, 2016March 31, 2021
    Comment
  • Grant beneficiaries who consider that supported activities are subject to consultation and reflect their views.Value0.0081.9060.00
    DateJanuary 12, 2016December 31, 2020
    Comment
  • Share of local residents that are satisfied with tourism development in the destinations that benefit from the activities in the project.Value0.0041.7030.00
    DateJanuary 12, 2016December 31, 2020
    Comment
  • Private enterprises that benefit from activities funded through the project’s grants, owned or managed by a womanValue0.0020.0010.00
    DateJanuary 12, 2016September 30, 2021
    Comment
  • Destination development plans agreedValue0.000.000.00
    DateOctober 31, 2019September 30, 2021
    Comment
  • Private enterprises that benefit from activities funded through the project’s grants.Value0.00602.0040.00
    DateJanuary 12, 2016September 30, 2021
    Comment
  • Private stakeholders that participate in project-supported capacity-building activities (e.g. training, supplier development, others)Value0.001161.00100.00
    DateJanuary 12, 2016September 30, 2021
    Comment
  • Increase in number of overnights by tourists in beneficiary destinationsValue0.000.602.00
    DateJanuary 12, 2016August 31, 2021
    Comment
  • Number of tour packages offered by tour operators (local and foreign) that include the project-supported destinations as a new offeringValue0.00147.0010.00
    DateJanuary 12, 2016September 30, 2021
    Comment