Financier | Commitments |
---|---|
Development Bank of Latin America (CAF) | 11.50 |
International Bank for Reconstruction and Development | 65.00 |
Borrower/Recipient | 4.70 |
P154275
Closed
Hector Serrano
Republic of Panama
May 18, 2015
(as of board presentation)
March 17, 2017
November 27, 2017
US$ 81.20 million
PCU, under the Ministry of the Presidency
2017
US$ 76.50 million
B
November 14, 2022
June 30, 2020
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Development Bank of Latin America (CAF) | 11.50 |
International Bank for Reconstruction and Development | 65.00 |
Borrower/Recipient | 4.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 65.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 65.00 |
Lending Instrument | |
---|---|
Grant Amount | 11.50 |
Total Project Cost** | 81.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 14, 2018 | IBRD-87080 | Loan Disb | 80,719.00 |
Aug 15, 2018 | IBRD-87080 | Int Charges | 41,261.28 |
Aug 15, 2018 | IBRD-87080 | Int Charges | 69,452.05 |
Aug 15, 2018 | IBRD-87080 | Int Charges | 39,269.50 |
Oct 30, 2020 | IBRD-87080 | Loan Disb | -213,103.84 |
Mar 17, 2017 | IBRD-87080 | Loan Commitment | 65,000,000.00 |
Aug 15, 2018 | IBRD-87080 | Int Charges | 588.03 |
Aug 15, 2020 | IBRD-87080 | Int Charges | -25,188.46 |
Aug 15, 2020 | IBRD-87080 | Int Charges | 4,314.50 |
Dec 20, 2019 | IBRD-87080 | Loan Cancel | 64,657,264.00 |
Feb 15, 2021 | IBRD-87080 | Int Charges | 1,268.20 |
Oct 30, 2020 | IBRD-87080 | Loan Cancel | 213,103.84 |
Jun 4, 2021 | IBRD-87080 | Loan Repay | 28,313.22 |
Jun 4, 2021 | IBRD-87080 | Int Charges | 2,575.98 |
Jun 4, 2021 | IBRD-87080 | Int Charges | 404.29 |
Jun 4, 2021 | IBRD-87080 | Loan Repay | 17,893.69 |
Jun 4, 2021 | IBRD-87080 | Loan Repay | 83,426.24 |
Aug 15, 2019 | IBRD-87080 | Int Charges | 5,198.35 |
Feb 15, 2020 | IBRD-87080 | Int Charges | 81,431.43 |
Feb 15, 2020 | IBRD-87080 | Int Charges | 4,939.98 |
Feb 15, 2019 | IBRD-87080 | Int Charges | 39,966.77 |
Feb 15, 2019 | IBRD-87080 | Int Charges | 1,357.34 |
Feb 15, 2019 | IBRD-87080 | Int Charges | 41,849.31 |
Mar 22, 2019 | IBRD-87080 | Loan Disb | 262,018.00 |
Aug 15, 2019 | IBRD-87080 | Int Charges | 80,220.11 |
Oct 12, 2017 | IBRD-87080 | Fee Charges | 162,500.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Unsatisfactory | 2020-06-27 |
Overall Implementation Progress (IP) | Unsatisfactory | 2020-06-27 |
Procurement | Unsatisfactory | 2020-06-27 |
Monitoring and Evaluation | Satisfactory | 2020-06-27 |
Financial Management | Moderately Unsatisfactory | 2020-06-27 |
Counterpart Funding | Moderately Unsatisfactory | 2020-06-27 |
Project Management | Moderately Unsatisfactory | 2020-06-27 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 0.00 | 20000.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
A monitoring report on water quality for the Panama Bay area published every year | Value | No | No. | Yes |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 49.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Sewerage technical audit identifies prioirty O&M investement needs | Value | No | No | Yes |
Date | June 10, 2019 | June 10, 2019 | June 30, 2021 | |
Comment |
Poor Beneficiaries | Value | 0.00 | 0.00 | 29.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
People provided with access to ‘improved sanitation facilities” under the proj. | Value | 0.00 | 0.00 | 4600.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
People provided with access to “improved sanitation facilities” - urban | Value | 0.00 | 0.00 | 4600.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of inter-domiciliary connection constructed under the Project | Value | 0.00 | 0.00 | 4000.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Number of staff trained on Monitoring and Planning of Hydrodynamic model | Value | 0.00 | 0.00 | 15.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 0.00 | 95.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Percentage of septic tanks that are properly closed down in the Project's intervention area. | Value | 0.00 | 0.00 | 90.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Number of Female staff trained | Value | 0.00 | 0.00 | 8.00 |
Date | March 15, 2017 | May 7, 2018 | December 31, 2021 | |
Comment |
Grievances related to delivery of project benefits that are addressed | Value | 0.00 | 0.00 | 0.00 |
Date | March 15, 2017 | May 7, 2018 | December 31, 2021 | |
Comment |
New household sewer connections constructed under the project | Value | 0.00 | 0.00 | 4000.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Number of Male staff trained | Value | 0.00 | 0.00 | 7.00 |
Date | March 15, 2017 | May 7, 2018 | December 31, 2021 | |
Comment |
Technical studies contribute to the development of an Integrated Urban Water Management Plan | Value | No | No | Yes |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |
Socio-environmental community management committees created and operational | Value | 0.00 | 0.00 | 20.00 |
Date | March 15, 2017 | October 19, 2018 | December 31, 2021 | |
Comment |