Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 28.04 |
P154464
Closed
Tatiana Shadrunova
The Republic of North Macedonia
July 10, 2015
(as of board presentation)
January 11, 2016
July 14, 2016
US$ 28.04 million
Project Management Unit at the Ministry of Finance
2016
US$ 28.04 million
B
October 12, 2023
January 31, 2023
TBD
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 28.04 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 28.04 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 28.04 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 28.04 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2024 | IBRD-85610 | Loan Repay | 1,062,072.10 |
Jan 11, 2016 | IBRD-85610 | Loan Commitment | 28,038,000.00 |
Jan 13, 2023 | IBRD-85610 | Loan Disb | 1,232,472.20 |
Jun 9, 2023 | IBRD-85610 | Loan Disb | -489,594.94 |
Sep 15, 2023 | IBRD-85610 | Int Charges | 336.14 |
Sep 15, 2023 | IBRD-85610 | Int Charges | 456,034.12 |
Sep 15, 2023 | IBRD-85610 | Loan Repay | 1,039,155.30 |
Jun 9, 2023 | IBRD-85610 | Loan Cancel | 1,065,903.60 |
Sep 15, 2022 | IBRD-85610 | Int Charges | 5,579.87 |
Sep 15, 2022 | IBRD-85610 | Int Charges | 25,843.25 |
Sep 15, 2022 | IBRD-85610 | Loan Repay | 853,670.44 |
Sep 15, 2022 | IBRD-85610 | Int Charges | 6.43 |
Sep 15, 2022 | IBRD-85610 | Int Charges | 1.13 |
Oct 5, 2022 | IBRD-85610 | Loan Disb | 1,102,471.80 |
Mar 15, 2023 | IBRD-85610 | Int Charges | 1,862.83 |
Mar 15, 2021 | IBRD-85610 | Int Charges | 22,171.22 |
Mar 15, 2021 | IBRD-85610 | Int Charges | 13,587.94 |
Mar 15, 2021 | IBRD-85610 | Loan Repay | 466,763.94 |
Mar 15, 2021 | IBRD-85610 | Int Charges | 251.70 |
Mar 15, 2021 | IBRD-85610 | Int Charges | 17.42 |
Feb 4, 2021 | IBRD-85610 | Loan Disb | 1,164,398.00 |
Jan 19, 2021 | IBRD-85610 | Loan Disb | 1,293,194.90 |
Mar 22, 2021 | IBRD-85610 | Loan Disb | 985,968.20 |
Jun 3, 2021 | IBRD-85610 | Loan Disb | 867,550.60 |
Apr 12, 2021 | IBRD-85610 | Loan Disb | 1,439,789.20 |
Oct 20, 2020 | IBRD-85610 | Loan Disb | 1,128,465.80 |
Sep 15, 2020 | IBRD-85610 | Int Charges | 17.00 |
Sep 15, 2020 | IBRD-85610 | Int Charges | 28,735.97 |
Sep 15, 2020 | IBRD-85610 | Int Charges | 7,842.57 |
Sep 15, 2020 | IBRD-85610 | Int Charges | 122.67 |
Sep 15, 2019 | IBRD-85610 | Int Charges | 32,738.37 |
Sep 15, 2019 | IBRD-85610 | Int Charges | 4,207.62 |
Sep 15, 2019 | IBRD-85610 | Int Charges | 256.39 |
Jul 14, 2016 | IBRD-85610 | Loan Disb | 69,403.13 |
Jul 14, 2016 | IBRD-85610 | Fee Charges | 69,403.13 |
Sep 15, 2016 | IBRD-85610 | Int Charges | 35,475.51 |
Sep 15, 2016 | IBRD-85610 | Int Charges | 54.08 |
Mar 15, 2017 | IBRD-85610 | Int Charges | 32,791.25 |
Mar 15, 2017 | IBRD-85610 | Int Charges | 136.89 |
Sep 15, 2017 | IBRD-85610 | Int Charges | 37,559.70 |
Sep 15, 2017 | IBRD-85610 | Int Charges | 152.71 |
Oct 3, 2017 | IBRD-85610 | Loan Disb | 587,850.00 |
Mar 15, 2018 | IBRD-85610 | Int Charges | 37,529.37 |
Mar 15, 2018 | IBRD-85610 | Int Charges | 1,211.17 |
Sep 15, 2018 | IBRD-85610 | Int Charges | 36,038.19 |
Sep 15, 2018 | IBRD-85610 | Int Charges | 1,312.02 |
Jan 29, 2019 | IBRD-85610 | Loan Disb | 857,700.00 |
Mar 15, 2019 | IBRD-85610 | Int Charges | 34,031.65 |
Mar 15, 2019 | IBRD-85610 | Int Charges | 1,312.54 |
Jun 17, 2019 | IBRD-85610 | Loan Disb | 611,710.56 |
Mar 15, 2024 | IBRD-85610 | Int Charges | 495,694.44 |
Mar 15, 2023 | IBRD-85610 | Int Charges | 248,372.03 |
Mar 15, 2023 | IBRD-85610 | Loan Repay | 1,059,319.20 |
Mar 15, 2023 | IBRD-85610 | Int Charges | 137.51 |
Mar 15, 2023 | IBRD-85610 | Int Charges | 13.06 |
Aug 24, 2022 | IBRD-85610 | Loan Disb | 852,024.80 |
Dec 28, 2021 | IBRD-85610 | Loan Disb | 403,814.06 |
May 24, 2022 | IBRD-85610 | Loan Disb | 1,189,349.80 |
Mar 14, 2022 | IBRD-85610 | Loan Disb | 1,210,382.20 |
Mar 15, 2022 | IBRD-85610 | Int Charges | 10,053.17 |
Mar 15, 2022 | IBRD-85610 | Int Charges | 19,276.36 |
Mar 15, 2022 | IBRD-85610 | Loan Repay | 793,541.75 |
Mar 15, 2022 | IBRD-85610 | Int Charges | 258.66 |
Mar 15, 2022 | IBRD-85610 | Int Charges | 60.23 |
Dec 7, 2021 | IBRD-85610 | Loan Disb | 1,041,399.80 |
Sep 28, 2021 | IBRD-85610 | Loan Disb | 1,217,174.20 |
Sep 15, 2021 | IBRD-85610 | Int Charges | 15,401.81 |
Sep 15, 2021 | IBRD-85610 | Int Charges | 16,965.13 |
Sep 15, 2021 | IBRD-85610 | Loan Repay | 689,171.00 |
Sep 15, 2021 | IBRD-85610 | Int Charges | 761.15 |
Sep 15, 2021 | IBRD-85610 | Int Charges | 20.83 |
Aug 4, 2021 | IBRD-85610 | Loan Disb | 1,195,128.90 |
Jun 24, 2022 | IBRD-85610 | Loan Disb | 906,843.60 |
Dec 4, 2020 | IBRD-85610 | Loan Disb | 1,436,211.00 |
Aug 12, 2020 | IBRD-85610 | Loan Disb | 1,143,941.80 |
Sep 18, 2020 | IBRD-85610 | Loan Disb | 1,210,437.10 |
Feb 28, 2020 | IBRD-85610 | Loan Disb | 1,037,039.40 |
Mar 30, 2020 | IBRD-85610 | Loan Disb | 716,096.30 |
Mar 15, 2020 | IBRD-85610 | Int Charges | 30,368.89 |
Mar 15, 2020 | IBRD-85610 | Int Charges | 4,836.66 |
Dec 20, 2019 | IBRD-85610 | Loan Disb | 945,015.44 |
Jun 3, 2020 | IBRD-85610 | Loan Disb | 962,691.44 |
Sep 30, 2019 | IBRD-85610 | Loan Disb | 954,350.06 |
Sep 15, 2019 | IBRD-85610 | Int Charges | 169.92 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2022-12-07 |
Overall Implementation Progress (IP) | Satisfactory | 2022-12-07 |
Progress towards achievement of PDO | Satisfactory | 2022-12-07 |
Financial Management | Satisfactory | 2022-12-07 |
Monitoring and Evaluation | Satisfactory | 2022-12-07 |
Procurement | Satisfactory | 2022-12-07 |
Project Management | Satisfactory | 2022-12-07 |
Overall Safeguards Rating | Satisfactory | 2022-12-07 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2023 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-24-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of completed subprojects that generated improved financial performance, including through increased revenue earnings or cost savings | Value | 0.00 | 97.00 | 0.00 |
Date | December 31, 2015 | January 31, 2023 | ||
Comment |
Number of the completed sub-projects that focus on social inclusion | Value | 0.00 | 43.00 | 25.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 425589.00 | 120000.00 |
Date | December 31, 2015 | November 23, 2022 | August 5, 2020 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2015 | June 30, 2018 | ||
Comment |
Vulnerable/marginalized people with marginalized measured as the number of unemployed, social assistance receiving or in other waysvulnerable population that benefits from the project intervention | Value | 0.00 | 0.00 | 0.00 |
Date | December 31, 2015 | June 30, 2018 | ||
Comment |
Number of participating municipalities (i.e. the municipalities which signed sub-loan agreements) that regularly publish sub-project progress information on their official websites or elsewhere | Value | 0.00 | 37.00 | 29.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of sub-loans signed | Value | 0.00 | 38.00 | 29.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
Number poverty/social inclusion investment grants signed | Value | 0.00 | 40.00 | 25.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
Number of jobs generated, measured as the number of employees of contractors and engineering companies that perform works under thesub-projects | Value | 0.00 | 2759.00 | 1800.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
Number of sub-projects, financed by sub-loans or grants, successfully completed | Value | 0.00 | 95.00 | 54.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
Number of visits to websites that publish sub-project progress information | Value | 0.00 | 675500.00 | 0.00 |
Date | December 31, 2015 | January 31, 2023 | ||
Comment |
Number of participants in consultation activities during sub-projects preparation | Value | 0.00 | 2468.00 | 1600.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 2650.00 | 0.00 |
Date | December 31, 2015 | January 31, 2023 | ||
Comment |
Number of participants in consultation activities during sub-projects preparation - female | Value | 0.00 | 871.00 | 500.00 |
Date | December 31, 2015 | January 31, 2023 | August 5, 2020 | |
Comment |
Roads rehabilitated, Rural | Value | 0.00 | 24.40 | 0.00 |
Date | December 31, 2015 | January 31, 2023 | ||
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 32.07 | 0.00 |
Date | December 31, 2015 | January 31, 2023 | ||
Comment |