Financier | Commitments |
---|---|
IDA Credit | 60.00 |
Borrower/Recipient | 20.42 |
IDA Credit provided from the IDA Regional Projects Window | 90.00 |
P154580
Active
Amali Rajapaksa , Nusrat Babi
People's Republic of Bangladesh
June 5, 2016
(as of board presentation)
April 5, 2017
January 8, 2018
US$ 170.42 million
Ministry of Commerce,Ministry of Shipping - Bangladesh Land Port Authority,Ministry of Finance - National Board of Revenue
2017
US$ 150.00 million
B
February 4, 2024
December 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 60.00 |
Borrower/Recipient | 20.42 |
IDA Credit provided from the IDA Regional Projects Window | 90.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 150.00 |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 170.42 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 23, 2022 | IDA-60020 | Loan Disb | 253,149.80 |
May 15, 2022 | IDA-60020 | Int Charges | 2,119.12 |
May 15, 2022 | IDA-60020 | Int Charges | 2,119.12 |
May 15, 2022 | IDA-60020 | Int Charges | 172,107.67 |
May 15, 2022 | IDA-60020 | Int Charges | 172,107.67 |
May 15, 2019 | IDA-60020 | Int Charges | 6,701.74 |
May 15, 2019 | IDA-60020 | Int Charges | 6,701.74 |
Feb 27, 2020 | IDA-60020 | Loan Disb | 3,413,537.20 |
Sep 19, 2019 | IDA-60020 | Loan Disb | 4,657,988.00 |
Sep 19, 2019 | IDA-60020 | Loan Disb | 550,295.90 |
May 15, 2020 | IDA-60020 | Int Charges | 6,041.25 |
May 15, 2020 | IDA-60020 | Int Charges | 6,041.25 |
May 15, 2020 | IDA-60020 | Int Charges | 41,119.59 |
May 15, 2020 | IDA-60020 | Int Charges | 41,119.59 |
Feb 25, 2021 | IDA-60020 | Loan Disb | 471,698.12 |
Sep 9, 2020 | IDA-60020 | Loan Disb | 117,924.53 |
Aug 24, 2020 | IDA-60020 | Loan Disb | 5,830,306.50 |
Aug 27, 2020 | IDA-60020 | Loan Disb | 1,539,622.60 |
Feb 25, 2021 | IDA-60020 | Loan Disb | 10,806,368.00 |
Feb 27, 2018 | IDA-60020 | Loan Disb | 1,205,690.90 |
May 15, 2018 | IDA-60020 | Int Charges | 1,928.05 |
May 15, 2018 | IDA-60020 | Int Charges | 1,928.05 |
Feb 6, 2019 | IDA-60020 | Loan Disb | 231,340.27 |
Feb 11, 2019 | IDA-60020 | Loan Disb | 279,928.53 |
Nov 15, 2018 | IDA-60020 | Int Charges | 33.85 |
Nov 15, 2018 | IDA-60020 | Int Charges | 33.85 |
Nov 15, 2018 | IDA-60020 | Int Charges | 4,270.49 |
Nov 15, 2018 | IDA-60020 | Int Charges | 4,270.49 |
Jan 22, 2019 | IDA-60020 | Loan Disb | 595,230.50 |
Apr 18, 2019 | IDA-60020 | Loan Disb | 1,008,891.50 |
Apr 18, 2019 | IDA-60020 | Loan Disb | 1,157,676.40 |
Nov 15, 2019 | IDA-60020 | Int Charges | 1,158.68 |
Nov 15, 2019 | IDA-60020 | Int Charges | 1,158.68 |
Nov 15, 2019 | IDA-60020 | Int Charges | 16,413.97 |
Nov 15, 2019 | IDA-60020 | Int Charges | 16,413.97 |
May 15, 2019 | IDA-60020 | Int Charges | 65.52 |
May 15, 2019 | IDA-60020 | Int Charges | 65.52 |
Apr 5, 2017 | IDA-60020 | Loan Commitment | 150,000,000.00 |
Dec 18, 2023 | IDA-60020 | Loan Disb | 9,350.00 |
Feb 13, 2024 | IDA-60020 | Loan Disb | 24,600.01 |
Feb 1, 2024 | IDA-60020 | Loan Disb | 718,365.00 |
Feb 1, 2024 | IDA-60020 | Loan Disb | 11,850.00 |
Feb 29, 2024 | IDA-60020 | Loan Disb | 20,764,000.00 |
May 15, 2024 | IDA-60020 | Loan Repay | 223,279.40 |
Jun 27, 2024 | IDA-60020 | Loan Disb | 598,134.80 |
May 15, 2024 | IDA-60020 | Int Charges | 14,428.82 |
May 15, 2024 | IDA-60020 | Int Charges | 14,428.82 |
Jun 18, 2024 | IDA-60020 | Loan Disb | 2,155,095.00 |
May 15, 2024 | IDA-60020 | Loan Repay | 2,067,718.40 |
May 15, 2024 | IDA-60020 | Int Charges | 221,801.31 |
May 15, 2024 | IDA-60020 | Int Charges | 221,801.31 |
Nov 15, 2022 | IDA-60020 | Int Charges | 4,200.06 |
Nov 15, 2022 | IDA-60020 | Int Charges | 195,856.03 |
Nov 15, 2022 | IDA-60020 | Int Charges | 195,856.03 |
Sep 1, 2022 | IDA-60020 | Loan Disb | 1,263,157.90 |
Nov 15, 2022 | IDA-60020 | Int Charges | 4,200.06 |
Mar 9, 2023 | IDA-60020 | Loan Disb | 401,960.78 |
May 15, 2023 | IDA-60020 | Int Charges | 185,028.22 |
May 15, 2023 | IDA-60020 | Int Charges | 185,028.22 |
May 15, 2023 | IDA-60020 | Int Charges | 3,319.63 |
May 15, 2023 | IDA-60020 | Int Charges | 3,319.63 |
May 15, 2023 | IDA-60020 | Loan Repay | 2,324,480.20 |
Nov 15, 2023 | IDA-60020 | Int Charges | 21,294.36 |
Nov 15, 2023 | IDA-60020 | Int Charges | 21,294.36 |
Nov 15, 2023 | IDA-60020 | Loan Repay | 2,296,243.50 |
Nov 15, 2023 | IDA-60020 | Int Charges | 181,957.19 |
Nov 15, 2023 | IDA-60020 | Int Charges | 181,957.19 |
May 15, 2021 | IDA-60020 | Int Charges | 97,730.88 |
May 15, 2021 | IDA-60020 | Int Charges | 97,730.88 |
May 15, 2021 | IDA-60020 | Int Charges | 143.05 |
May 15, 2021 | IDA-60020 | Int Charges | 143.05 |
Nov 15, 2020 | IDA-60020 | Int Charges | 651.19 |
Nov 15, 2020 | IDA-60020 | Int Charges | 651.19 |
Nov 15, 2020 | IDA-60020 | Int Charges | 62,241.64 |
Nov 15, 2020 | IDA-60020 | Int Charges | 62,241.64 |
Sep 8, 2021 | IDA-60020 | Loan Disb | 14,961,854.00 |
Sep 14, 2021 | IDA-60020 | Loan Disb | 848,686.60 |
Nov 15, 2021 | IDA-60020 | Int Charges | 683.79 |
Nov 15, 2021 | IDA-60020 | Int Charges | 683.79 |
Nov 15, 2021 | IDA-60020 | Int Charges | 140,617.34 |
Nov 15, 2021 | IDA-60020 | Int Charges | 140,617.34 |
Mar 15, 2022 | IDA-60020 | Loan Disb | 8,388,372.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-11-12 |
Financial Management | Moderately Satisfactory | 2024-11-12 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-12 |
Project Management | Moderately Satisfactory | 2024-11-12 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-12 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-12 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average time taken to meet regulatory requirements associated with import activities | Value | 187.00 | 187.00 | 112.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Speed of truck clearance at land ports supported by the Project (truck in truck out) - Bhomra | Value | 72.00 | 72.00 | 12.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Freight volume at land ports supported by the Project | Value | 1995000.00 | 4950000.00 | 3000000.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Freight volume at Land Ports supported by the Project - Bhomra | Value | 1995000.00 | 4776000.00 | 3000000.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Freight volume at Land Ports supported by the Project - Sheola | Value | 174000.00 | 174000.00 | 500000.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Average time taken to meet regulatory requirements associated with export activities | Value | 147.00 | 147.00 | 88.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of grievances related to Project implementation addressed | Value | 0.00 | 100.00 | 100.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Number of programs instituted to facilitate female traders and entrepreneurs | Value | 0.00 | 3.00 | 5.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Number of agencies connected to the National Single Window | Value | 0.00 | 0.00 | 19.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |
Number of Land Ports Built or Improved/Rehabilitated | Value | 0.00 | 1.00 | 4.00 |
Date | December 1, 2016 | October 17, 2023 | June 30, 2023 | |
Comment |