The development objective of the Hebei Air Pollution Prevention and Control Program (HAP) Project for China is to reduce emissions of specific air pollutants in the key sectors in Hebei. The part of the government program supported under the proposed HAP includes the following activities: (i) comprehensive control of industrial enterprises and reduced emission of multipollutants; (ii) area pollution control and dust control; (iii) prevention and control...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To reduce emissions of specific air pollutants in the key sectors in Hebei

Key Details

Project Details

  • P154672

  • Closed

  • Dafei Huang

  • N/A

  • China

  • April 13, 2016

  • (as of board presentation)

    June 6, 2016

  • October 11, 2016

  • US$ 500.00 million

  • N/A

  • July 16, 2024

  • December 31, 2019

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 468.00
International Bank for Reconstruction and Development 500.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 500.00
IDA Commitment N/A
IBRD + IDA Commitment 500.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 968.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 6, 2016 IBRD-86230 Loan Commitment 500,000,000.00
Aug 15, 2018 IBRD-86230 Int Charges 1,678,674.50
Feb 15, 2024 IBRD-86230 Int Charges 124,632.89
Feb 15, 2024 IBRD-86230 Int Charges 13,441,990.00
Aug 15, 2024 IBRD-86230 Int Charges 75,487.08
Aug 15, 2024 IBRD-86230 Int Charges 12,896,280.00
Aug 15, 2024 IBRD-86230 Loan Repay 17,850,000.00
Feb 15, 2023 IBRD-86230 Int Charges 749,786.25
Feb 15, 2023 IBRD-86230 Int Charges 10,295,047.00
Feb 15, 2023 IBRD-86230 Loan Repay 17,850,000.00
Aug 15, 2023 IBRD-86230 Loan Repay 17,850,000.00
Aug 15, 2023 IBRD-86230 Int Charges 468,135.30
Aug 15, 2023 IBRD-86230 Int Charges 12,128,128.00
Aug 15, 2022 IBRD-86230 Loan Repay 17,850,000.00
Aug 15, 2022 IBRD-86230 Int Charges 3,205,238.80
Aug 15, 2021 IBRD-86230 Int Charges 2,337,916.80
Aug 15, 2021 IBRD-86230 Loan Repay 17,850,000.00
Feb 15, 2022 IBRD-86230 Int Charges 2,193,246.80
Feb 15, 2022 IBRD-86230 Loan Repay 17,850,000.00
Feb 15, 2021 IBRD-86230 Int Charges 2,657,777.80
Aug 15, 2020 IBRD-86230 Int Charges 6,041,389.00
Aug 15, 2019 IBRD-86230 Int Charges 336,695.06
Aug 15, 2019 IBRD-86230 Int Charges 46,923.30
Aug 15, 2019 IBRD-86230 Int Charges 7,699,870.50
Aug 15, 2019 IBRD-86230 Int Charges 28,205.48
Feb 15, 2020 IBRD-86230 Int Charges 21,021.64
Feb 15, 2020 IBRD-86230 Int Charges 272,253.50
Feb 15, 2020 IBRD-86230 Int Charges 6,951,111.00
Jun 20, 2019 IBRD-86230 Loan Disb 54,806,400.00
Sep 4, 2018 IBRD-86230 Loan Disb 180,000,000.00
Dec 19, 2018 IBRD-86230 Loan Disb 71,000,000.00
Feb 15, 2019 IBRD-86230 Int Charges 196,596.47
Feb 15, 2019 IBRD-86230 Int Charges 5,243,909.50
Nov 8, 2018 IBRD-86230 Loan Disb 71,443,600.00
Feb 15, 2017 IBRD-86230 Int Charges 7,981.59
Oct 11, 2016 IBRD-86230 Loan Disb 1,250,000.00
Oct 11, 2016 IBRD-86230 Fee Charges 1,250,000.00
Feb 15, 2017 IBRD-86230 Int Charges 538,953.10
Apr 28, 2017 IBRD-86230 Loan Disb 121,500,000.00
Aug 15, 2017 IBRD-86230 Int Charges 527,604.44
Aug 15, 2017 IBRD-86230 Int Charges 740,836.25
Feb 15, 2018 IBRD-86230 Int Charges 475,438.38
Feb 15, 2018 IBRD-86230 Int Charges 1,323,790.50
Aug 15, 2018 IBRD-86230 Int Charges 467,686.66
Feb 15, 2024 IBRD-86230 Loan Repay 17,850,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2019-12-30
Monitoring and Evaluation Satisfactory 2019-12-30
Overall Implementation Progress (IP) Satisfactory 2019-12-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-22-2020
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceHighly Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-17-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceHighly SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityHighN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction of SO2 emissions from enterprises included in the CEM (tons)Value0.00454000.000.00
    DateDecember 2, 2013December 16, 2019
    Comment
  • Reduction of NOx emissions from enterprises included in the CEM (tons)Value0.00331100.000.00
    DateJanuary 1, 2014December 16, 2019
    Comment
  • Reduction of PM2.5 emissions from the 800,000 clean stoves deployed (tons)Value0.003269.000.00
    DateJanuary 1, 2014December 16, 2019
    Comment
  • Reduction of NOx emissions from the transport sector (tons)Value0.0042170.000.00
    DateJanuary 1, 2014December 16, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of EPBs at the provincial and prefecture level implementing Standard Protocols on CEM Systems for emissions of air pollutantsValue0.0012.000.00
    DateJune 6, 2016December 31, 2018
    Comment
  • Number of clean stoves installedValue0.00800000.000.00
    DateJune 6, 2016December 31, 2018
    Comment
  • Number of Clean Energy Buses replacing diesel buses, which are disposed of, in accordance with the National RegulationsValue0.004632.000.00
    DateJune 6, 2016December 19, 2019
    Comment
  • Percentage of enterprises in State-controlled Lists and Municipal-controlled Lists integrated in the Improved CEM and Enforcement Systems for Air PollutantsValue0.00100.000.00
    DateJune 6, 2016December 31, 2018
    Comment