Sustainable Landscape Management Project

Abstract*

The development objective of Sustainable Landscape Management Project for Madagascar is to increase access to improved irrigation services and agricultural inputs, and strengthen the integrated management of natural resources in the Selected Landscapes by the local actors and, to provide immediate and effective response to an Eligible Crisis or Emergency. This project has four components. 1) The first component, Information and planning, has the following...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Global Environmental Objective is: To increase access to improved irrigation services and agricultural inputs, and strengthen the integrated management of natural resources in the Selected Landscapes by the local actors and, to provide immediate and effective response to an Eligible Crisis or Emergency.

Key Details

Project Details

  • P154698

  • Closed

  • Andrew Zakharenka , Sachiko Kondo, Mampionona Amboarasoa

  • Republic of Madagascar

  • Madagascar

  • January 26, 2017

  • (as of board presentation)

    March 23, 2017

  • October 26, 2017

  • US$ 107.06 million

  • Ministry of Agriculture and Livestock,Ministry of Water, Sanitation and Hygiene,Project Implementation Unit-PADAP,Ministry of Environment and Sustainable Development

  • Eastern and Southern Africa

  • 2017

  • US$ 105.33 million

  • B

  • May 8, 2024

  • April 30, 2024

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Beneficiaries 1.50
FRANCE: French Agency for Development 26.63
IDA Credit 65.00
Global Environment Facility - IBRD as Implementing Agency 13.70
Borrower/Recipient 0.23

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 65.00
IBRD + IDA Commitment 65.00
Lending Instrument
Grant Amount 40.33
Total Project Cost** 107.06

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 18, 2023 IDA-59790 Int Charges 210,376.48
Jan 18, 2023 IDA-59790 Int Charges 210,376.48
Mar 31, 2023 IDA-59790 Loan Disb 278,889.40
Jan 15, 2023 IDA-59790 Int Charges 1,185.06
Jan 15, 2023 IDA-59790 Int Charges 1,185.06
Jun 15, 2023 IDA-D8740 Loan Disb 3,149,601.00
Sep 8, 2022 IDA-59790 Loan Disb 9,720.25
Sep 13, 2022 IDA-59790 Loan Disb 572,408.25
Jan 5, 2023 IDA-59790 Loan Disb 745,720.94
Nov 4, 2022 IDA-59790 Loan Disb 653,590.90
Dec 7, 2022 IDA-59790 Loan Disb 235,280.61
Jan 30, 2023 IDA-59790 Loan Disb 194,950.77
Mar 8, 2023 IDA-59790 Loan Disb 3,835,832.00
Jun 8, 2022 IDA-59790 Loan Disb 518,008.00
Apr 4, 2022 IDA-59790 Loan Disb 578,690.00
Jul 19, 2022 IDA-59790 Int Charges 202,000.70
Jul 19, 2022 IDA-59790 Int Charges 202,000.70
Jul 19, 2022 IDA-59790 Int Charges 2,938.58
Jul 19, 2022 IDA-59790 Int Charges 2,938.58
Feb 2, 2022 IDA-59790 Int Charges 183,862.62
Feb 2, 2022 IDA-59790 Int Charges 183,862.62
Dec 29, 2021 IDA-59790 Loan Disb 58,212.48
Feb 11, 2022 IDA-59790 Loan Disb 38,487.28
Feb 14, 2022 IDA-59790 Loan Disb 578,690.00
Jan 15, 2022 IDA-59790 Int Charges 692.05
Jan 15, 2022 IDA-59790 Int Charges 692.05
Aug 2, 2022 IDA-59790 Loan Disb 144,076.66
Sep 28, 2022 IDA-59790 Loan Disb 747,382.30
Aug 30, 2021 IDA-59790 Loan Disb 7,640,963.50
Aug 19, 2021 IDA-59790 Loan Disb 470,697.70
Nov 19, 2021 IDA-59790 Loan Disb 509,943.30
Oct 6, 2021 IDA-59790 Loan Disb 322,400.10
Jun 24, 2022 IDA-59790 Loan Disb 186,316.22
Dec 14, 2021 IDA-59790 Loan Disb 639,289.56
Dec 14, 2021 IDA-59790 Loan Disb 1,183,173.60
Mar 15, 2022 IDA-59790 Loan Disb 5,043.71
Apr 12, 2022 IDA-59790 Loan Disb 951,214.80
Mar 2, 2022 IDA-59790 Loan Disb -578,675.00
May 28, 2024 IDA-D8740 Loan Disb 256,571.95
Jul 15, 2024 IDA-59790 Int Charges 228,405.23
Jul 17, 2024 IDA-59790 Int Charges 3,333.83
Jul 17, 2024 IDA-59790 Int Charges 3,333.83
Jul 17, 2024 IDA-59790 Loan Repay 231,984.44
May 6, 2024 IDA-D8740 Loan Disb 794,340.10
Feb 6, 2024 IDA-D8740 Loan Disb 685,924.00
Jul 15, 2024 IDA-59790 Int Charges 273.18
Jul 15, 2024 IDA-59790 Int Charges 273.18
Jun 30, 2021 IDA-D8740 Loan Commitment 40,000,000.00
Mar 23, 2017 IDA-59790 Loan Commitment 65,000,000.00
Jul 23, 2024 IDA-D8740 Loan Disb -999,967.25
Apr 3, 2024 IDA-D8740 Loan Disb 749,658.06
Feb 1, 2024 IDA-D8740 Loan Disb 1,401,195.00
Mar 26, 2024 IDA-D8740 Loan Disb 218.78
Jan 25, 2024 IDA-59790 Int Charges 10,162.77
May 17, 2024 IDA-D8740 Loan Disb 721,840.70
Apr 17, 2024 IDA-D8740 Loan Disb 192,639.66
May 14, 2024 IDA-D8740 Loan Disb 1,192,001.10
Mar 25, 2024 IDA-D8740 Loan Cancel 7,361,112.50
Jul 15, 2024 IDA-59790 Loan Repay 772,082.30
Jul 15, 2024 IDA-59790 Int Charges 228,405.23
Oct 31, 2017 IDA-59790 Loan Disb 672,620.90
Jan 15, 2018 IDA-59790 Int Charges 1,057.13
Jan 15, 2018 IDA-59790 Int Charges 1,057.13
Jun 26, 2018 IDA-59790 Loan Disb 3,617,700.00
Jul 18, 2018 IDA-59790 Int Charges 2,564.84
Jul 18, 2018 IDA-59790 Int Charges 2,564.84
Oct 16, 2020 IDA-59790 Loan Disb 305,159.60
Aug 10, 2020 IDA-59790 Loan Disb 293,597.70
Nov 13, 2020 IDA-59790 Loan Disb 779,252.80
Jul 16, 2020 IDA-59790 Int Charges 545.40
Jul 16, 2020 IDA-59790 Int Charges 545.40
Jul 16, 2020 IDA-59790 Int Charges 28,025.08
Jul 16, 2020 IDA-59790 Int Charges 28,025.08
Sep 3, 2019 IDA-59790 Loan Disb 113,269.23
Nov 27, 2019 IDA-59790 Loan Disb 439,445.90
Oct 15, 2019 IDA-59790 Loan Disb 284,856.66
Oct 3, 2019 IDA-59790 Loan Disb 221,857.56
Mar 18, 2020 IDA-59790 Loan Disb 219,073.30
Feb 27, 2020 IDA-59790 Loan Disb 946,406.90
Jan 15, 2020 IDA-59790 Int Charges 47.54
Jan 15, 2020 IDA-59790 Int Charges 47.54
Jan 15, 2020 IDA-59790 Int Charges 19,906.76
Jan 15, 2020 IDA-59790 Int Charges 19,906.76
Jan 17, 2020 IDA-59790 Loan Disb 203,769.16
May 6, 2019 IDA-59790 Loan Disb 93,501.76
Jun 11, 2019 IDA-59790 Loan Disb 87,095.41
Apr 10, 2019 IDA-59790 Loan Disb 103,440.69
Jun 21, 2019 IDA-59790 Loan Disb 466,826.60
Jul 24, 2019 IDA-59790 Loan Disb 184,409.94
Jul 15, 2019 IDA-59790 Int Charges 167.83
Jul 15, 2019 IDA-59790 Int Charges 167.83
Jul 15, 2019 IDA-59790 Int Charges 16,245.26
Jul 15, 2019 IDA-59790 Int Charges 16,245.26
Jul 18, 2018 IDA-59790 Int Charges 14.63
Jul 18, 2018 IDA-59790 Int Charges 14.63
Jan 15, 2019 IDA-59790 Int Charges 1,365.06
Jan 15, 2019 IDA-59790 Int Charges 1,365.06
Jan 15, 2019 IDA-59790 Int Charges 15,753.13
Jan 15, 2019 IDA-59790 Int Charges 15,753.13
Feb 11, 2019 IDA-59790 Loan Disb 19,898.16
Apr 16, 2019 IDA-59790 Loan Disb -200,768.10
Mar 12, 2019 IDA-59790 Loan Disb 46,125.56
Dec 7, 2021 IDA-59790 Loan Disb 310,722.25
Dec 6, 2021 IDA-59790 Loan Disb 1,000,000.00
Dec 6, 2021 IDA-59790 Loan Disb 1,000,000.00
May 11, 2022 IDA-59790 Loan Disb 413,393.88
Jan 19, 2021 IDA-59790 Int Charges 867.73
Jan 19, 2021 IDA-59790 Int Charges 867.73
Apr 8, 2021 IDA-59790 Loan Disb 2,624,760.20
Aug 3, 2021 IDA-59790 Loan Disb 570,649.90
Apr 14, 2021 IDA-59790 Loan Disb 3,501,654.20
Jun 30, 2021 IDA-59790 Loan Disb 228,389.28
Jun 2, 2021 IDA-59790 Loan Disb 892,119.25
May 4, 2021 IDA-59790 Loan Disb 562,438.00
Apr 12, 2021 IDA-59790 Loan Disb 819,978.56
Jul 16, 2021 IDA-59790 Int Charges 4,219.34
Jul 16, 2021 IDA-59790 Int Charges 4,219.34
Jul 16, 2021 IDA-59790 Int Charges 134,338.86
Jul 16, 2021 IDA-59790 Int Charges 134,338.86
Feb 12, 2021 IDA-59790 Loan Disb 726,001.94
Sep 11, 2020 IDA-59790 Loan Disb 154,832.50
Dec 29, 2020 IDA-59790 Loan Disb 551,753.50
Dec 29, 2020 IDA-59790 Loan Disb 1,198,439.00
Dec 17, 2020 IDA-59790 Loan Disb 660,096.94
Jan 25, 2024 IDA-59790 Int Charges 10,162.77
Jan 25, 2024 IDA-59790 Loan Repay 235,988.88
Jan 29, 2024 IDA-59790 Loan Repay 769,844.50
Jan 29, 2024 IDA-59790 Int Charges 19.46
Jan 29, 2024 IDA-59790 Int Charges 19.46
Jan 29, 2024 IDA-59790 Int Charges 233,188.27
Jan 29, 2024 IDA-59790 Int Charges 233,188.27
Jan 24, 2024 IDA-D8740 Loan Disb 757,797.44
Aug 9, 2024 IDA-D8740 Loan Disb -402,806.28
Jul 19, 2023 IDA-59790 Int Charges 5,784.77
Jul 19, 2023 IDA-59790 Int Charges 5,784.77
Jul 19, 2023 IDA-59790 Loan Repay 237,142.11
Sep 1, 2023 IDA-D8740 Loan Disb 1,575,381.50
Jul 15, 2023 IDA-59790 Int Charges 228,939.30
Jul 15, 2023 IDA-59790 Int Charges 228,939.30
Nov 8, 2023 IDA-D8740 Loan Disb 775,417.10
Jul 15, 2023 IDA-59790 Loan Repay 786,447.30
Dec 8, 2023 IDA-D8740 Loan Disb 1,006,266.90
Dec 21, 2023 IDA-D8740 Loan Disb 398,711.25
Feb 27, 2023 IDA-59790 Loan Disb 859,904.44
Dec 17, 2020 IDA-59790 Loan Disb 413,497.50
Jan 22, 2021 IDA-59790 Loan Disb 1,288,892.80
Dec 8, 2020 IDA-59790 Loan Disb 682,220.10
Dec 8, 2020 IDA-59790 Loan Disb 749,942.70
Mar 3, 2021 IDA-59790 Loan Disb 207,767.33
Dec 23, 2020 IDA-59790 Loan Disb 1,375,301.00
Feb 16, 2021 IDA-59790 Loan Disb 12,164,500.00
Dec 3, 2020 IDA-59790 Loan Disb 585,417.25
Feb 8, 2021 IDA-59790 Loan Disb 854,452.25
Feb 8, 2021 IDA-59790 Loan Disb 594,189.80
Dec 21, 2020 IDA-59790 Loan Disb 547,904.44
Feb 10, 2021 IDA-59790 Loan Disb 1,469,070.00
Jan 19, 2021 IDA-59790 Int Charges 37,146.94
Jan 19, 2021 IDA-59790 Int Charges 37,146.94
Apr 7, 2020 IDA-59790 Loan Disb 461,414.40
May 5, 2020 IDA-59790 Loan Disb 493,070.03
Jun 12, 2020 IDA-59790 Loan Disb 202,817.00
Jun 25, 2020 IDA-59790 Loan Disb 257,575.16
May 10, 2023 IDA-D8740 Loan Disb 7,601,485.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2023-12-22
Project Management Satisfactory 2023-12-22
Financial Management Moderately Satisfactory 2023-12-22
Progress towards achievement of PDO Satisfactory 2023-12-22
Monitoring and Evaluation Satisfactory 2023-12-22
Overall Implementation Progress (IP) Satisfactory 2023-12-22
Counterpart Funding Satisfactory 2023-12-22

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area provided with irrigation and drainage services (ha)Value0.0010000.000.00
    DateAugust 1, 2017April 30, 2024
    Comment
  • Clients who have adopted an improved agr. technology promoted by the projectValue0.0014149.100.00
    DateAugust 1, 2017April 30, 2024
    Comment
  • Land area where sustainable land mgt. practices were adopted as a result of projValue0.00652105.500.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Direct project beneficiariesValue0.0049803.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Area provided with irrigation and drainage services - Improved (ha)Value0.0010260.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Clients who adopted an improved agr. technology promoted by project – femaleValue0.004462.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Female beneficiariesValue0.0016.000.00
    DateAugust 1, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Landscape management plans approved by the National Steering Committee and Regional Monitoring CommitteesValue0.005.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • COBA operationalValue0.0077.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Spatial information system established and operationalValueNoYes
    DateAugust 1, 2017December 6, 2023
    Comment
  • Pilot payment for environmental services mechanism established (Number, Custom)Value0.005.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Number of Covid-19 tests conductedValue82195.00272799.000.00
    DateNovember 2, 2020December 6, 2023
    Comment
  • Policy Briefs prepared, validated and disseminated to stakeholdersValue0.005.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Area under conservation with a management plan (Hectare(Ha), Custom)Value0.00303508.400.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Percentage of health facilities with no stock-outs of PPE during the last 30 daysValue0.00100.000.00
    DateSeptember 30, 2021December 6, 2023
    Comment
  • Share of target beneficiaries with score Satisfied or above on application of integrated landscape approach in targeted landscapes (disaggregated by sex)Value0.000.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Area in protected areas in the targeted landscapes with Management Effectiveness Tracking Tool (METT)/IEG score over 70 (Number, Custom)Value0.00195651.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Irrigation systems managed by Water User AssociationsValue12.0056.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • FemaleValue0.000.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • CSAs, STDs and CTDs operational (disaggregated by institution)Value0.0021.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • MaleValue0.000.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • STDsValue0.0077.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • Farmers reached with agricultural assets and services (disaggregated by sex)Value0.0028204.000.00
    DateAugust 1, 2017December 6, 2023
    Comment
  • FemaleValue0.008148.000.00
    DateNovember 11, 2021December 6, 2023
    Comment