Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 216.50 |
Asian Infrastructure Investment Bank | 216.50 |
Indonesia - Free-standing Trust Fund Program | 5.50 |
Borrower/Recipient | 981.70 |
P154782
Closed
Evi Hermirasari , Andre Bald
Republic of Indonesia
December 10, 2015
(as of board presentation)
July 12, 2016
October 11, 2016
US$ 1420.20 million
Ministry of Public Works and Housing,Ministry of Agrarian and Spatial Planning,Bappenas
2017
US$ 438.50 million
B
Not Applicable
June 30, 2023
Yes
BANK APPROVED
January 24, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 216.50 |
Asian Infrastructure Investment Bank | 216.50 |
Indonesia - Free-standing Trust Fund Program | 5.50 |
Borrower/Recipient | 981.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 216.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 216.50 |
Lending Instrument | |
---|---|
Grant Amount | 222.00 |
Total Project Cost** | 1420.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 15, 2024 | IBRD-86360 | Int Charges | 685.62 |
Jan 15, 2024 | IBRD-86360 | Int Charges | 16,915.31 |
Jan 15, 2024 | IBRD-86360 | Int Charges | 874.43 |
May 13, 2024 | IBRD-86360 | Loan Cancel | 1,172,420.20 |
Jul 15, 2024 | IBRD-86360 | Int Charges | 6,656,903.50 |
Jul 15, 2024 | IBRD-86360 | Loan Repay | 9,052,210.00 |
Jul 15, 2024 | IBRD-86360 | Int Charges | 42,399.77 |
Jul 15, 2024 | IBRD-86360 | Int Charges | 963.87 |
Jul 12, 2016 | IBRD-86360 | Loan Commitment | 216,500,000.00 |
Jul 15, 2023 | IBRD-86360 | Int Charges | 2,313.41 |
Jul 15, 2023 | IBRD-86360 | Int Charges | 1,901.24 |
Jul 15, 2023 | IBRD-86360 | Int Charges | 1,019.64 |
Jul 15, 2023 | IBRD-86360 | Int Charges | 6,505,992.50 |
Jul 15, 2023 | IBRD-86360 | Loan Repay | 8,557,087.00 |
May 24, 2023 | IBRD-86360 | Loan Disb | 1,925,000.00 |
Nov 28, 2023 | IBRD-86360 | Loan Disb | -703.21 |
Jan 15, 2024 | IBRD-86360 | Int Charges | 7,042,982.50 |
Jan 15, 2024 | IBRD-86360 | Loan Repay | 8,847,850.00 |
Jan 22, 2024 | IBRD-86360 | Loan Disb | -388,757.60 |
Nov 28, 2023 | IBRD-86360 | Loan Disb | -88,965.41 |
Nov 30, 2022 | IBRD-86360 | Loan Disb | 425,000.00 |
Nov 11, 2022 | IBRD-86360 | Loan Cancel | 9,166,006.00 |
Mar 15, 2023 | IBRD-86360 | Loan Disb | 890,000.00 |
Jan 15, 2023 | IBRD-86360 | Int Charges | 8,526.58 |
Jan 15, 2023 | IBRD-86360 | Int Charges | 13,149.73 |
Jan 15, 2023 | IBRD-86360 | Int Charges | 4,413,928.00 |
Jan 15, 2023 | IBRD-86360 | Int Charges | 1,553.43 |
Aug 31, 2021 | IBRD-86360 | Loan Disb | 17,550,000.00 |
Jun 21, 2022 | IBRD-86360 | Loan Disb | 9,450,000.00 |
Dec 9, 2021 | IBRD-86360 | Loan Disb | 2,350,000.00 |
Jul 15, 2022 | IBRD-86360 | Int Charges | 1,524,348.90 |
Jul 15, 2022 | IBRD-86360 | Int Charges | 595.55 |
Jul 15, 2022 | IBRD-86360 | Int Charges | 2,665.08 |
Jul 15, 2022 | IBRD-86360 | Int Charges | 31,930.49 |
Aug 23, 2022 | IBRD-86360 | Loan Disb | 3,200,000.00 |
Mar 9, 2022 | IBRD-86360 | Loan Disb | 4,300,000.00 |
Jan 15, 2022 | IBRD-86360 | Int Charges | 6,328.76 |
Jan 15, 2022 | IBRD-86360 | Int Charges | 30,887.90 |
Jan 15, 2022 | IBRD-86360 | Int Charges | 45,886.98 |
Jan 15, 2022 | IBRD-86360 | Int Charges | 1,239,358.10 |
Jan 15, 2021 | IBRD-86360 | Int Charges | 946,128.94 |
Jan 15, 2021 | IBRD-86360 | Int Charges | 4,282.79 |
Jan 15, 2021 | IBRD-86360 | Int Charges | 49,186.38 |
Jan 15, 2021 | IBRD-86360 | Int Charges | 115,782.85 |
Mar 16, 2021 | IBRD-86360 | Loan Disb | 8,800,000.00 |
Nov 23, 2020 | IBRD-86360 | Loan Disb | 14,550,000.00 |
Jun 1, 2021 | IBRD-86360 | Loan Disb | 21,000,000.00 |
Jul 15, 2021 | IBRD-86360 | Int Charges | 27,716.85 |
Jul 15, 2021 | IBRD-86360 | Int Charges | 85,246.23 |
Jul 15, 2021 | IBRD-86360 | Int Charges | 1,039,833.25 |
Jul 15, 2021 | IBRD-86360 | Int Charges | 5,271.24 |
Jan 15, 2020 | IBRD-86360 | Int Charges | 160,207.95 |
Jan 15, 2020 | IBRD-86360 | Int Charges | 1,557,347.00 |
Jun 1, 2020 | IBRD-86360 | Loan Disb | 14,250,000.00 |
Sep 2, 2020 | IBRD-86360 | Loan Disb | 7,500,000.00 |
Jul 15, 2020 | IBRD-86360 | Int Charges | 139,987.03 |
Jul 15, 2020 | IBRD-86360 | Int Charges | 1,559,039.80 |
May 13, 2019 | IBRD-86360 | Loan Disb | 12,000,000.00 |
Feb 22, 2019 | IBRD-86360 | Loan Disb | 15,650,000.00 |
Jul 15, 2019 | IBRD-86360 | Int Charges | 179,461.30 |
Jul 15, 2019 | IBRD-86360 | Int Charges | 1,464,436.40 |
Nov 8, 2019 | IBRD-86360 | Loan Disb | 17,600,000.00 |
Nov 7, 2016 | IBRD-86360 | Fee Charges | 541,250.00 |
Feb 27, 2017 | IBRD-86360 | Loan Disb | 14,500,000.00 |
Jan 15, 2017 | IBRD-86360 | Int Charges | 127,235.68 |
Nov 21, 2017 | IBRD-86360 | Loan Disb | 1,200,000.00 |
Jul 15, 2017 | IBRD-86360 | Int Charges | 254,695.19 |
Jul 15, 2017 | IBRD-86360 | Int Charges | 140,625.83 |
Aug 18, 2017 | IBRD-86360 | Loan Disb | 4,500,000.00 |
Feb 23, 2018 | IBRD-86360 | Loan Disb | 25,000,000.00 |
Jun 1, 2018 | IBRD-86360 | Loan Disb | 10,000,000.00 |
Jan 15, 2018 | IBRD-86360 | Int Charges | 249,500.02 |
Jan 15, 2018 | IBRD-86360 | Int Charges | 247,010.55 |
Jul 15, 2018 | IBRD-86360 | Int Charges | 4,424.62 |
Jul 15, 2018 | IBRD-86360 | Int Charges | 452.05 |
Jul 15, 2018 | IBRD-86360 | Int Charges | 216,029.45 |
Jul 15, 2018 | IBRD-86360 | Int Charges | 616,530.44 |
Jan 15, 2019 | IBRD-86360 | Int Charges | 3,013.70 |
Jan 15, 2019 | IBRD-86360 | Int Charges | 34,630.74 |
Jan 15, 2019 | IBRD-86360 | Int Charges | 203,282.19 |
Jan 15, 2019 | IBRD-86360 | Int Charges | 1,049,536.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2023-06-14 |
Monitoring and Evaluation | Satisfactory | 2023-06-14 |
Overall Implementation Progress (IP) | Satisfactory | 2023-06-14 |
Progress towards achievement of PDO | Satisfactory | 2023-06-14 |
Procurement | Satisfactory | 2023-06-14 |
Project Management | Satisfactory | 2023-06-14 |
Financial Management | Moderately Satisfactory | 2023-06-14 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-24-2024 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Highly Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-12-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with improved infrastructure under the project | Value | 0.00 | 8660311.00 | 7000000.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 88848.00 | 40000.00 |
Date | November 14, 2018 | June 30, 2023 | August 12, 2020 | |
Comment |
People provided with "improved water sources" under the project (of which women) | Value | 0.00 | 968225.00 | 560000.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Female beneficiaries | Value | 0.00 | 44416.00 | 20000.00 |
Date | November 14, 2018 | June 30, 2023 | August 12, 2020 | |
Comment |
People provided with "improved sanitation" under the project (of which women) | Value | 0.00 | 938172.00 | 800000.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
People provided with access to all-season roads within 500 meter range under the project (of which women) | Value | 0.00 | 5157486.00 | 3700000.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
People provided with regular solid waste collection under the project (of which women) | Value | 0.00 | 2538372.00 | 1500000.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
People provided with "improved drainage" under the project (of which women) | Value | 0.00 | 3813623.00 | 2320000.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Slum Area Alleviated | Value | 0.00 | 11382.00 | 6360.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Percentage of slum dwellers who are satisfied with the quality of urban infrastructure and services (of which women, of which bottom 40%, of which poor) | Value | 0.00 | 95.50 | 80.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Percentage of complaints resolved | Value | 0.00 | 100.00 | 90.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Establishment of functional task forces for slum alleviation at local level (%Local Governments) | Value | 0.00 | 93.50 | 90.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 8956579.00 | 7200000.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Female beneficiaries | Value | 0.00 | 51.30 | 0.00 |
Date | April 1, 2016 | March 7, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Indicator 2.1 Percentage of local governments that have completed Slum Improvement Action Plans (SIAPs) which have been approved byBupati/Walikota | Value | 0.00 | 94.00 | 90.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 3.1. Number of cities which have completed 80% of primary and secondary infrastructure works and services connected to slum areas | Value | 0.00 | 37.00 | 30.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 4.1. Percentage of local governments that have project monitoring structure and provide regular information on project implementation | Value | 0.00 | 84.00 | 70.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 5.1 Percentage of housing constructed to project resilience standards | Value | 0.00 | 100.00 | 70.00 |
Date | November 14, 2018 | June 30, 2023 | December 31, 2022 | |
Comment |
Indicator 1.2. Establishment of slum inventory database/profiling | Value | No | Done and updated | Done and updated |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 2.2. Percentage of kelurahans which have Community Settlement Plans (CSPs) that have been consolidated with SIAPs | Value | 0.00 | 100.00 | 90.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 3.2. Number of kelurahans that have completed 90% of tertiary infrastructure and services implemented in slum areas | Value | 0.00 | 2507.00 | 2500.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 4.2. Percentage of kelurahans with completed annual financial audits | Value | 0.00 | 94.00 | 90.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 5.2 Percentage of water supply facilities has been built | Value | 0.00 | 100.00 | 65.00 |
Date | November 14, 2018 | June 30, 2023 | June 30, 2021 | |
Comment |
Indicator 3.3. Percentage of good quality of infrastructure and services | Value | 0.00 | 98.00 | 90.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 5.3 Percentage of sanitation facilities have been built | Value | 0.00 | 100.00 | 75.00 |
Date | November 14, 2018 | June 30, 2023 | June 30, 2021 | |
Comment |
Indicator 3.4. Percentage of infrastructure built that is fully functioning | Value | 0.00 | 98.00 | 70.00 |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |
Indicator 5.4 Percentage of schools and higher education building rehabilitated or reconstructed to project’s resilience standards | Value | 0.00 | 100.00 | 75.00 |
Date | November 14, 2018 | June 30, 2023 | June 30, 2021 | |
Comment |
Indicator 5.5 Percentage of health facilities and public service building rehabilitated to project’s resilience standards | Value | 0.00 | 100.00 | 75.00 |
Date | November 14, 2018 | June 30, 2023 | June 30, 2021 | |
Comment |
Indicator 1.1. Establishment of functional task force for slum alleviation at national level | Value | No | Yes | Yes |
Date | June 9, 2016 | June 30, 2023 | August 12, 2020 | |
Comment |