Power Distribution Development Program-for-Results

Abstract*

The development objective of the Power Distribution Development Program for Results (PforR) Project for Indonesia is to increase access to electricity services and to improve the efficiency and reliability of their delivery in selected areas of Indonesia. The PforR program to be supported by the Bank is a geographic slice of the distribution component of the Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) in that it will only cover Indonesia’s Sumatra...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project's development objective is to increase access to electricity services and to improve the efficiency and reliability oftheir delivery in selected areas of Indonesia.

Key Details

Project Details

  • P154805

  • Closed

  • Stephan Garnier

  • PT. Perusahaan Listrik Negara (PLN)

  • Indonesia

  • January 15, 2016

  • (as of board presentation)

    April 22, 2016

  • November 18, 2016

  • US$ 1450.00 million

  • PT Perusahaan Listrik Negara (PLN)

  • East Asia and Pacific

  • 2016

  • US$ 920.00 million

  • N/A

  • Not Applicable

  • April 30, 2020

  • BANK APPROVED

  • December 14, 2020

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 500.00
Asian Development Bank 420.00
Borrower/Recipient 530.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 500.00
IDA Commitment N/A
IBRD + IDA Commitment 500.00
Lending Instrument
Grant Amount 420.00
Total Project Cost** 1450.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 15, 2016 IBRD-86100 Fee Charges 1,250,000.00
Mar 15, 2024 IBRD-86100 Int Charges 232,208.39
Mar 15, 2017 IBRD-86100 Int Charges 380,961.38
Sep 15, 2018 IBRD-86100 Int Charges 360,609.12
Sep 15, 2018 IBRD-86100 Int Charges 3,344,840.80
Jun 22, 2018 IBRD-86100 Loan Disb 229,923,152.00
Sep 15, 2017 IBRD-86100 Int Charges 1,193,908.10
Sep 15, 2017 IBRD-86100 Int Charges 494,468.47
Mar 15, 2017 IBRD-86100 Int Charges 769,013.56
Mar 15, 2018 IBRD-86100 Int Charges 50.00
Mar 15, 2018 IBRD-86100 Int Charges 486,406.50
Mar 15, 2018 IBRD-86100 Int Charges 1,196,141.00
Mar 15, 2019 IBRD-86100 Int Charges 201,364.78
Mar 15, 2019 IBRD-86100 Int Charges 5,685,763.50
Sep 13, 2019 IBRD-86100 Loan Disb 62,500,000.00
Sep 15, 2019 IBRD-86100 Int Charges 165,871.40
Sep 15, 2019 IBRD-86100 Int Charges 6,540,251.50
Jun 18, 2019 IBRD-86100 Loan Disb 62,295,672.00
Mar 15, 2020 IBRD-86100 Int Charges 6,638,589.00
Mar 15, 2020 IBRD-86100 Int Charges 11,227.18
Mar 15, 2020 IBRD-86100 Int Charges 46,857.97
Mar 15, 2020 IBRD-86100 Int Charges 856.16
Jun 8, 2020 IBRD-86100 Loan Disb 37,611,000.00
Sep 15, 2020 IBRD-86100 Int Charges 21,862.34
Sep 15, 2020 IBRD-86100 Int Charges 3,749,306.00
Sep 15, 2021 IBRD-86100 Int Charges 18.62
Sep 15, 2021 IBRD-86100 Int Charges 2,580,988.50
Sep 15, 2021 IBRD-86100 Loan Repay 11,399,540.00
Mar 15, 2021 IBRD-86100 Int Charges 6.33
Mar 15, 2021 IBRD-86100 Int Charges 2,714,890.50
Oct 31, 2020 IBRD-86100 Loan Cancel 20,172.00
Mar 15, 2022 IBRD-86100 Int Charges 2,407,343.80
Mar 15, 2022 IBRD-86100 Loan Repay 11,699,528.00
Sep 15, 2023 IBRD-86100 Int Charges 177,555.61
Sep 15, 2023 IBRD-86100 Int Charges 13,440,443.00
Sep 15, 2023 IBRD-86100 Loan Repay 12,599,492.00
Sep 15, 2022 IBRD-86100 Int Charges 4,719,303.00
Sep 15, 2022 IBRD-86100 Loan Repay 11,999,516.00
Mar 15, 2023 IBRD-86100 Int Charges 543,928.25
Mar 15, 2023 IBRD-86100 Int Charges 11,962,623.00
Mar 15, 2023 IBRD-86100 Loan Repay 12,299,504.00
Mar 15, 2024 IBRD-86100 Int Charges 14,482,876.00
Mar 15, 2024 IBRD-86100 Loan Repay 12,899,480.00
Apr 22, 2016 IBRD-86100 Loan Commitment 500,000,000.00
Jan 9, 2017 IBRD-86100 Loan Disb 107,650,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2020-05-26
Monitoring and Evaluation Satisfactory 2020-05-26
Overall Implementation Progress (IP) Satisfactory 2020-05-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-14-2020
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceHighly Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-27-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with access to electricity by household connectionsValue11180000.0012749000.0014410000.00
    DateJanuary 1, 2015December 31, 2019April 5, 2019
    Comment
  • Electricity losses per year in the project areaValue11.9210.000.00
    DateJanuary 1, 2015December 31, 2019
    Comment
  • System average interruption duration index (SAIDI) in minutes per customer yearValue1989.00463.001650.00
    DateJanuary 1, 2018December 31, 2019April 5, 2019
    Comment
  • System average interruptions frequency index (interruptions per customer per year)Value17.818.1115.50
    DateJanuary 1, 2018December 31, 2020April 5, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of MV feeder technical interruptions per 100 kmValue21.2221.0216.00
    DateJanuary 1, 2015December 31, 2019April 5, 2019
    Comment
  • Number of distribution transformer units addedValue80130.0097904.0098338.00
    DateJanuary 1, 2015December 31, 2020April 5, 2019
    Comment
  • Increased volume in power sales to residential customers (GWh)Value15850.0021471.0018438.00
    DateDecember 31, 2014December 31, 2019April 5, 2019
    Comment
  • PLN collaborated with development partners in the hiring of an independent verification agentValueNoYes
    DateJanuary 1, 2015April 24, 2020
    Comment
  • Percentage of planned capital expenditures realizedValue82.0085.000.00
    DateDecember 31, 2014December 31, 2020
    Comment
  • Increase in distribution transformer capacity (MVA)Value7981000.009717000.009880000.00
    DateJanuary 1, 2015December 31, 2019April 5, 2019
    Comment
  • Integrate budgeting with ERP in participating WilayahsValueNoYes
    DateJanuary 1, 2015April 24, 2020
    Comment
  • Distribution lines constructed or rehabilitated under the projectValue92716.00104510.00106228.00
    DateJanuary 1, 2015December 31, 2020April 5, 2019
    Comment
  • Issue revised distribution planning guidelines acceptable to the BankValueNoYes
    DateJanuary 1, 2015April 30, 2020
    Comment
  • Integrate distribution planning software with GIS facilitiesValueNoYes
    DateJanuary 1, 2015April 24, 2020
    Comment
  • Distribution lines constructed under the projectValue92716.00104510.00106228.00
    DateJanuary 1, 2015December 31, 2019April 5, 2019
    Comment
  • Conduct procurement audits for at least 15% of contracts issued by each procuring unit and share results with the BankValueNoYes
    DateJanuary 1, 2015December 31, 2020
    Comment
  • Annual work plans approved (on time)ValueNoYes
    DateJanuary 1, 2015December 31, 2019
    Comment