Financier | Commitments |
---|---|
Zimbabwe Reconstruction Fund (ZIMREF) | 20.00 |
P154861
Closed
Chloe Viola , Christiaan Heymans
Republic of Zimbabwe
July 20, 2015
(as of board presentation)
January 29, 2016
June 16, 2016
US$ 20.00 million
Zimbabwe National Water Authority
2016
US$ 20.00 million
B
Not Applicable
June 30, 2020
Yes
BANK APPROVED
September 6, 2024
Financier | Commitments |
---|---|
Zimbabwe Reconstruction Fund (ZIMREF) | 20.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 20.00 |
Total Project Cost** | 20.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2020-06-06 |
Monitoring and Evaluation | Satisfactory | 2020-06-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-06-06 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2020-06-06 |
Procurement | Satisfactory | 2020-06-06 |
Project Management | Moderately Satisfactory | 2020-06-06 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-12-2021 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-15-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 34810.00 | 12480.00 |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
National Water Resources Master Plan completed and endorsed | Value | No | No | Yes |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Road map for establishing the WSS regulator endorsed | Value | No | No | Yes |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Female beneficiaries | Value | 0.00 | 52.00 | 50.00 |
Date | November 1, 2015 | May 12, 2018 | ||
Comment |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 33410.00 | 7020.00 |
Date | November 2, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Improved collection rates for 3 ZINWA stations supported by project | Value | 0.00 | 70.00 | 70.00 |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 1400.00 | 5460.00 |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Reduced NRW in the 3 ZINWA stations supported by the project | Value | 0.00 | 30.00 | 25.00 |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 1120.00 | 2018.00 |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 2696.00 | 1276.00 |
Date | November 1, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Water Service Agreements signed and implemented between ZINWA and Local Authorities | Value | 0.00 | 0.00 | 3.00 |
Date | November 23, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Complaints addressed satisfactorily | Value | 38.00 | 80.00 | 90.00 |
Date | November 2, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |
Sanitation plans prepared for growth centers | Value | 0.00 | 7.00 | 7.00 |
Date | November 23, 2015 | June 5, 2020 | May 5, 2020 | |
Comment |