Financier | Commitments |
---|---|
Borrower/Recipient | 510.00 |
International Bank for Reconstruction and Development | 450.00 |
P154948
Closed
Dao Harrison , Andre Bald
Republic of Indonesia
November 17, 2016
(as of board presentation)
March 17, 2017
January 24, 2018
US$ 450.00 million
Ministry of Public Works and Housing
2017
US$ 450.00 million
B
September 6, 2023
February 28, 2023
TBD
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 510.00 |
International Bank for Reconstruction and Development | 450.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 450.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 450.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 450.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 2, 2019 | IBRD-87170 | Loan Disb | 35,640,000.00 |
Apr 9, 2018 | IBRD-87170 | Loan Disb | 17,500,800.00 |
Feb 15, 2018 | IBRD-87170 | Fee Charges | 1,125,000.00 |
Sep 15, 2018 | IBRD-87170 | Int Charges | 138,698.62 |
Sep 15, 2018 | IBRD-87170 | Int Charges | 548,064.20 |
Sep 15, 2018 | IBRD-87170 | Int Charges | 247,344.64 |
Oct 30, 2018 | IBRD-87170 | Loan Disb | 23,900,000.00 |
Mar 15, 2019 | IBRD-87170 | Int Charges | 513,917.50 |
Mar 15, 2019 | IBRD-87170 | Int Charges | 618,628.20 |
Mar 17, 2017 | IBRD-87170 | Loan Commitment | 450,000,000.00 |
Apr 5, 2024 | IBRD-87170 | Loan Disb | -25,280.69 |
Jan 17, 2024 | IBRD-87170 | Loan Disb | -342,755.56 |
Mar 15, 2024 | IBRD-87170 | Loan Repay | 18,622,074.00 |
Mar 15, 2024 | IBRD-87170 | Int Charges | 164,939.40 |
Mar 15, 2024 | IBRD-87170 | Int Charges | 11,128,898.00 |
Jul 30, 2024 | IBRD-87170 | Loan Disb | -16,917.60 |
Jul 18, 2023 | IBRD-87170 | Loan Cancel | 49,355,208.00 |
Jul 18, 2023 | IBRD-87170 | Loan Disb | -15,511,950.00 |
Sep 15, 2023 | IBRD-87170 | Int Charges | 28,975.39 |
Sep 15, 2023 | IBRD-87170 | Int Charges | 11,059,823.00 |
Sep 15, 2023 | IBRD-87170 | Loan Repay | 19,181,282.00 |
Mar 15, 2023 | IBRD-87170 | Int Charges | 49,756.90 |
Oct 17, 2022 | IBRD-87170 | Loan Disb | 35,590,000.00 |
Sep 15, 2022 | IBRD-87170 | Int Charges | 5,971.51 |
Sep 15, 2022 | IBRD-87170 | Int Charges | 19,457.16 |
Sep 15, 2022 | IBRD-87170 | Int Charges | 87,504.92 |
Sep 15, 2022 | IBRD-87170 | Int Charges | 3,826,859.80 |
Sep 15, 2022 | IBRD-87170 | Loan Repay | 16,886,784.00 |
Mar 15, 2023 | IBRD-87170 | Int Charges | 9,085,710.00 |
Mar 15, 2023 | IBRD-87170 | Loan Repay | 18,886,412.00 |
Mar 15, 2022 | IBRD-87170 | Loan Repay | 11,732,547.00 |
Mar 15, 2022 | IBRD-87170 | Int Charges | 215,212.06 |
Mar 15, 2022 | IBRD-87170 | Int Charges | 1,433,751.60 |
Sep 15, 2021 | IBRD-87170 | Int Charges | 256,060.75 |
Sep 15, 2021 | IBRD-87170 | Int Charges | 1,375,069.20 |
Mar 7, 2022 | IBRD-87170 | Loan Disb | 108,980,000.00 |
Mar 15, 2021 | IBRD-87170 | Int Charges | 287,965.90 |
Mar 15, 2021 | IBRD-87170 | Int Charges | 1,289,422.80 |
Jun 7, 2021 | IBRD-87170 | Loan Disb | 54,247,944.00 |
Apr 15, 2020 | IBRD-87170 | Loan Disb | 15,920,000.00 |
Jun 18, 2020 | IBRD-87170 | Loan Disb | 70,107,992.00 |
Sep 15, 2020 | IBRD-87170 | Int Charges | 341,280.34 |
Sep 15, 2020 | IBRD-87170 | Int Charges | 1,495,887.60 |
May 8, 2019 | IBRD-87170 | Loan Disb | 27,000,000.00 |
Oct 4, 2019 | IBRD-87170 | Loan Disb | 27,270,000.00 |
Sep 15, 2019 | IBRD-87170 | Int Charges | 490,905.84 |
Sep 15, 2019 | IBRD-87170 | Int Charges | 1,106,592.60 |
Mar 15, 2020 | IBRD-87170 | Int Charges | 1,688,097.90 |
Mar 15, 2020 | IBRD-87170 | Int Charges | 419,418.16 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Satisfactory | 2022-12-02 |
Progress towards achievement of PDO | Moderately Satisfactory | 2022-12-02 |
Counterpart Funding | Moderately Satisfactory | 2022-12-02 |
Procurement | Moderately Satisfactory | 2022-12-02 |
Monitoring and Evaluation | Moderately Satisfactory | 2022-12-02 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2022-12-02 |
Project Management | Moderately Satisfactory | 2022-12-02 |
Financial Management | Satisfactory | 2022-12-02 |
Overall Safeguards Rating | Moderately Satisfactory | 2022-12-02 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-01-2023 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 02-05-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Households assisted for affordable house ownership | Value | 0.00 | 30422.00 | 32000.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Households receiving a house improvement/ reconstruction stimulant through enhanced Home Improvement Assistance Program | Value | 0.00 | 983606.00 | 823000.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
A Housing and Real Estate Information System (HREIS) developed created and implemented | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Reconstructed and/or improved housing units verified as accurate in beneficiary targeting | Value | 0.00 | 98.00 | 90.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
BP2BT beneficiaries who are in the bottom 60 percent of the income distribution | Value | 0.00 | 93.46 | 80.00 |
Date | October 3, 2016 | March 31, 2022 | December 30, 2022 | |
Comment |
BSPS implementation in urban area | Value | 20.00 | 4.80 | 35.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Beneficiaries from non-salaried sector | Value | 0.00 | 59.55 | 10.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Housing Policy Grand Design developed and submitted to key stakeholders | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Complaints recorded and processed within the service standard applied (disaggregated by gender) | Value | 0.00 | 100.00 | 75.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Participating lenders with >5 percent of program-financed BP2BT annual volume | Value | 0.00 | 2.00 | 3.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Beneficiaries satisfied or highly satisfied with BSPS Program for home reconstruction/improvement (disaggregated by gender) | Value | 0.00 | 93.80 | 80.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
BP2BT assistance-linked mortgage finance leveraged | Value | 0.00 | 224197903.13 | 200000000.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Institutional arrangement for housing sector developed and presented to key stakeholders | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Beneficiaries satisfied or highly satisfied with BP2BT Program | Value | 0.00 | 82.87 | 80.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Local Government Affordable Housing Plans developed | Value | 0.00 | 0.00 | 15.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Swadaya Management Information System developed and operationalized | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 31, 2021 | |
Comment |
BP2BT IT System developed and operationalized | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 31, 2021 | |
Comment |
PPP for Affordable Housing Development | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
System that tracks and enforces BSPS housing construction compliance towards the structural integrity and health standards developed | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
BP2BT housing units fulfilling minimum construction standard requirements | Value | 0.00 | 41.00 | 55.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
BSPS upgraded and/or re-constructed housing units verified as fulfilling construction quality - structural integrity standards | Value | 0.00 | 75.28 | 55.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Recommendation on a sustainable housing subsidy model developed | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Wire-mesh technology applied to improve the resilience of BSPS upgraded and/or reconstructed housing units | Value | 0.00 | 2.91 | 3.00 |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |
Development and piloting of HMF scheme for low income households | Value | No | Yes | Yes |
Date | October 3, 2016 | February 28, 2023 | December 30, 2022 | |
Comment |