Skip to Main Navigation

National Affordable Housing Program

Abstract*

The development objective of the National Affordable Housing Program Project aims to improve access to affordable housing through a mix of demand and supply side interventions targeting both lower-middle income and lower-income households. The projects are comprises into three components. The first components mortgage-linked down payment assistance targets lower middle income households that are unable to access commercial mortgage finance for home...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective of the Program is to improve access to affordable housing for lower income households

Key Details

Project Details

  • P154948

  • Closed

  • Dao Harrison , Andre Bald

  • Republic of Indonesia

  • Indonesia

  • November 17, 2016

  • (as of board presentation)

    March 17, 2017

  • January 24, 2018

  • US$ 450.00 million

  • Ministry of Public Works and Housing

  • East Asia and Pacific

  • 2017

  • US$ 450.00 million

  • B

  • September 6, 2023

  • February 28, 2023

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 510.00
International Bank for Reconstruction and Development 450.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 450.00
IDA Commitment N/A
IBRD + IDA Commitment 450.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 450.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 2, 2019 IBRD-87170 Loan Disb 35,640,000.00
Apr 9, 2018 IBRD-87170 Loan Disb 17,500,800.00
Feb 15, 2018 IBRD-87170 Fee Charges 1,125,000.00
Sep 15, 2018 IBRD-87170 Int Charges 138,698.62
Sep 15, 2018 IBRD-87170 Int Charges 548,064.20
Sep 15, 2018 IBRD-87170 Int Charges 247,344.64
Oct 30, 2018 IBRD-87170 Loan Disb 23,900,000.00
Mar 15, 2019 IBRD-87170 Int Charges 513,917.50
Mar 15, 2019 IBRD-87170 Int Charges 618,628.20
Mar 17, 2017 IBRD-87170 Loan Commitment 450,000,000.00
Apr 5, 2024 IBRD-87170 Loan Disb -25,280.69
Jan 17, 2024 IBRD-87170 Loan Disb -342,755.56
Mar 15, 2024 IBRD-87170 Loan Repay 18,622,074.00
Mar 15, 2024 IBRD-87170 Int Charges 164,939.40
Mar 15, 2024 IBRD-87170 Int Charges 11,128,898.00
Jul 30, 2024 IBRD-87170 Loan Disb -16,917.60
Jul 18, 2023 IBRD-87170 Loan Cancel 49,355,208.00
Jul 18, 2023 IBRD-87170 Loan Disb -15,511,950.00
Sep 15, 2023 IBRD-87170 Int Charges 28,975.39
Sep 15, 2023 IBRD-87170 Int Charges 11,059,823.00
Sep 15, 2023 IBRD-87170 Loan Repay 19,181,282.00
Mar 15, 2023 IBRD-87170 Int Charges 49,756.90
Oct 17, 2022 IBRD-87170 Loan Disb 35,590,000.00
Sep 15, 2022 IBRD-87170 Int Charges 5,971.51
Sep 15, 2022 IBRD-87170 Int Charges 19,457.16
Sep 15, 2022 IBRD-87170 Int Charges 87,504.92
Sep 15, 2022 IBRD-87170 Int Charges 3,826,859.80
Sep 15, 2022 IBRD-87170 Loan Repay 16,886,784.00
Mar 15, 2023 IBRD-87170 Int Charges 9,085,710.00
Mar 15, 2023 IBRD-87170 Loan Repay 18,886,412.00
Mar 15, 2022 IBRD-87170 Loan Repay 11,732,547.00
Mar 15, 2022 IBRD-87170 Int Charges 215,212.06
Mar 15, 2022 IBRD-87170 Int Charges 1,433,751.60
Sep 15, 2021 IBRD-87170 Int Charges 256,060.75
Sep 15, 2021 IBRD-87170 Int Charges 1,375,069.20
Mar 7, 2022 IBRD-87170 Loan Disb 108,980,000.00
Mar 15, 2021 IBRD-87170 Int Charges 287,965.90
Mar 15, 2021 IBRD-87170 Int Charges 1,289,422.80
Jun 7, 2021 IBRD-87170 Loan Disb 54,247,944.00
Apr 15, 2020 IBRD-87170 Loan Disb 15,920,000.00
Jun 18, 2020 IBRD-87170 Loan Disb 70,107,992.00
Sep 15, 2020 IBRD-87170 Int Charges 341,280.34
Sep 15, 2020 IBRD-87170 Int Charges 1,495,887.60
May 8, 2019 IBRD-87170 Loan Disb 27,000,000.00
Oct 4, 2019 IBRD-87170 Loan Disb 27,270,000.00
Sep 15, 2019 IBRD-87170 Int Charges 490,905.84
Sep 15, 2019 IBRD-87170 Int Charges 1,106,592.60
Mar 15, 2020 IBRD-87170 Int Charges 1,688,097.90
Mar 15, 2020 IBRD-87170 Int Charges 419,418.16

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Moderately Satisfactory 2022-12-02
Progress towards achievement of PDO Moderately Satisfactory 2022-12-02
Counterpart Funding Moderately Satisfactory 2022-12-02
Procurement Moderately Satisfactory 2022-12-02
Monitoring and Evaluation Moderately Satisfactory 2022-12-02
Overall Implementation Progress (IP) Moderately Satisfactory 2022-12-02
Project Management Moderately Satisfactory 2022-12-02
Financial Management Satisfactory 2022-12-02
Overall Safeguards Rating Moderately Satisfactory 2022-12-02

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-01-2023
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-05-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Households assisted for affordable house ownershipValue0.0030422.0032000.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Households receiving a house improvement/ reconstruction stimulant through enhanced Home Improvement Assistance ProgramValue0.00983606.00823000.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • A Housing and Real Estate Information System (HREIS) developed created and implementedValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Reconstructed and/or improved housing units verified as accurate in beneficiary targetingValue0.0098.0090.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • BP2BT beneficiaries who are in the bottom 60 percent of the income distributionValue0.0093.4680.00
    DateOctober 3, 2016March 31, 2022December 30, 2022
    Comment
  • BSPS implementation in urban areaValue20.004.8035.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Beneficiaries from non-salaried sectorValue0.0059.5510.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Housing Policy Grand Design developed and submitted to key stakeholdersValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Complaints recorded and processed within the service standard applied (disaggregated by gender)Value0.00100.0075.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Participating lenders with >5 percent of program-financed BP2BT annual volumeValue0.002.003.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Beneficiaries satisfied or highly satisfied with BSPS Program for home reconstruction/improvement (disaggregated by gender)Value0.0093.8080.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • BP2BT assistance-linked mortgage finance leveragedValue0.00224197903.13200000000.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Institutional arrangement for housing sector developed and presented to key stakeholdersValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Beneficiaries satisfied or highly satisfied with BP2BT ProgramValue0.0082.8780.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Local Government Affordable Housing Plans developedValue0.000.0015.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Swadaya Management Information System developed and operationalizedValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 31, 2021
    Comment
  • BP2BT IT System developed and operationalizedValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 31, 2021
    Comment
  • PPP for Affordable Housing DevelopmentValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • System that tracks and enforces BSPS housing construction compliance towards the structural integrity and health standards developedValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • BP2BT housing units fulfilling minimum construction standard requirementsValue0.0041.0055.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • BSPS upgraded and/or re-constructed housing units verified as fulfilling construction quality - structural integrity standardsValue0.0075.2855.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Recommendation on a sustainable housing subsidy model developedValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Wire-mesh technology applied to improve the resilience of BSPS upgraded and/or reconstructed housing unitsValue0.002.913.00
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment
  • Development and piloting of HMF scheme for low income householdsValueNoYesYes
    DateOctober 3, 2016February 28, 2023December 30, 2022
    Comment