Financier | Commitments |
---|---|
IDA Credit | 250.00 |
P154990
Active
Deepak Singh , Sebastian Forsch
India
June 2, 2015
(as of board presentation)
June 2, 2015
April 19, 2016
US$ 250.00 million
Project Implementing Entity
2015
US$ 250.00 million
B
March 21, 2024
August 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 250.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 250.00 |
IBRD + IDA Commitment | 250.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 250.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 2, 2015 | IDA-56950 | Loan Commitment | 250,000,000.00 |
Jun 26, 2018 | IDA-56950 | Loan Disb | 2,928,833.50 |
Jun 15, 2023 | IDA-56950 | Loan Disb | 5,235,084.50 |
Nov 15, 2023 | IDA-56950 | Loan Repay | 6,250,000.00 |
Nov 15, 2023 | IDA-56950 | Int Charges | 4,356,430.50 |
Nov 22, 2023 | IDA-56950 | Loan Disb | 2,903,818.50 |
Feb 29, 2024 | IDA-56950 | Loan Disb | 7,209,268.00 |
Aug 9, 2024 | IDA-56950 | Loan Disb | 7,327,657.50 |
May 15, 2024 | IDA-56950 | Loan Repay | 6,250,000.00 |
May 15, 2024 | IDA-56950 | Int Charges | 4,621,702.50 |
May 13, 2022 | IDA-56950 | Loan Disb | 20,208,952.00 |
May 15, 2022 | IDA-56950 | Int Charges | 16,908.33 |
May 15, 2022 | IDA-56950 | Loan Repay | 6,250,000.00 |
May 15, 2022 | IDA-56950 | Int Charges | 652,622.60 |
Jun 29, 2022 | IDA-56950 | Loan Disb | 9,523,734.00 |
Feb 2, 2022 | IDA-56950 | Loan Disb | 19,692,216.00 |
Nov 15, 2022 | IDA-56950 | Int Charges | 1,616.71 |
Nov 15, 2022 | IDA-56950 | Loan Repay | 6,250,000.00 |
Nov 15, 2022 | IDA-56950 | Int Charges | 1,942,479.50 |
Feb 21, 2023 | IDA-56950 | Loan Disb | 6,967,432.50 |
Nov 4, 2022 | IDA-56950 | Loan Disb | 7,389,008.50 |
May 15, 2023 | IDA-56950 | Int Charges | 7,157.07 |
May 15, 2023 | IDA-56950 | Loan Repay | 6,250,000.00 |
May 15, 2023 | IDA-56950 | Int Charges | 4,002,200.00 |
Jan 13, 2021 | IDA-56950 | Loan Disb | 11,394,836.00 |
Apr 13, 2021 | IDA-56950 | Loan Disb | 25,750,654.00 |
Jun 23, 2021 | IDA-56950 | Loan Disb | 13,679,538.00 |
May 15, 2021 | IDA-56950 | Int Charges | 10,211.21 |
May 15, 2021 | IDA-56950 | Int Charges | 222,296.80 |
Nov 15, 2020 | IDA-56950 | Int Charges | 6,047.15 |
Nov 15, 2020 | IDA-56950 | Loan Repay | 3,467,387.20 |
May 15, 2021 | IDA-56950 | Loan Repay | 6,250,000.00 |
Nov 15, 2020 | IDA-56950 | Loan Repay | 2,782,612.80 |
Nov 15, 2020 | IDA-56950 | Int Charges | 214,653.11 |
Nov 15, 2021 | IDA-56950 | Int Charges | 33,418.63 |
Nov 15, 2021 | IDA-56950 | Loan Repay | 6,250,000.00 |
Nov 15, 2021 | IDA-56950 | Int Charges | 459,947.97 |
Oct 22, 2021 | IDA-56950 | Loan Disb | 18,116,068.00 |
May 15, 2019 | IDA-56950 | Int Charges | 106,316.69 |
May 15, 2019 | IDA-56950 | Loan Disb | 3,187,532.50 |
Mar 1, 2019 | IDA-56950 | Loan Disb | 893,313.00 |
Nov 15, 2018 | IDA-56950 | Int Charges | 50,302.59 |
Dec 17, 2018 | IDA-56950 | Loan Disb | 1,844,367.50 |
Nov 15, 2019 | IDA-56950 | Int Charges | 227,519.22 |
Jun 26, 2019 | IDA-56950 | Loan Disb | 3,216,203.50 |
Nov 22, 2019 | IDA-56950 | Loan Disb | 1,983,079.20 |
Feb 24, 2020 | IDA-56950 | Loan Disb | 2,022,948.80 |
Jun 30, 2020 | IDA-56950 | Loan Disb | 1,625,367.00 |
Jun 29, 2020 | IDA-56950 | Loan Disb | 603,587.40 |
May 15, 2020 | IDA-56950 | Int Charges | 241,403.55 |
Apr 28, 2020 | IDA-56950 | Loan Disb | 4,091,284.50 |
Oct 14, 2020 | IDA-56950 | Loan Disb | 6,078,099.50 |
Sep 26, 2017 | IDA-56950 | Loan Disb | 378,260.53 |
May 15, 2018 | IDA-56950 | Int Charges | 1,392.21 |
May 15, 2018 | IDA-56950 | Int Charges | 5,382.12 |
Jun 26, 2023 | IDA-56950 | Loan Disb | 1,946,589.80 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-09-13 |
Project Management | Moderately Satisfactory | 2024-09-13 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-09-13 |
Financial Management | Moderately Satisfactory | 2024-09-13 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-09-13 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-09-13 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2024-09-13 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people served by restored and improved public buildings | Value | 0.00 | 104866.00 | 500000.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Number of people benefiting from improved flood management | Value | 0.00 | 377821.00 | 0.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Of which female | Value | 0.00 | 0.00 | 235000.00 |
Date | May 22, 2015 | April 26, 2018 | ||
Comment |
Of which female | Value | 0.00 | 0.00 | 0.00 |
Date | May 22, 2015 | April 26, 2018 | ||
Comment |
Number of people with access to restored and improved roads and bridges | Value | 0.00 | 492427.00 | 800000.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Seismic code guidelines for urban infrastructure updated with inputs from the urban vulnerability assessment and design standards study | Value | No | Yes | No |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Of which female | Value | 0.00 | 0.00 | 376000.00 |
Date | May 22, 2015 | April 26, 2018 | ||
Comment |
Number of people who received support to restoration of livelihoods | Value | 0.00 | 40000.00 | 15000.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Of which female | Value | 0.00 | 0.00 | 7500.00 |
Date | May 22, 2015 | April 26, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Health facilities constructed, renovated, and/or equipped (number) | Value | 0.00 | 36.00 | 0.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 33.00 | 100.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Number of pumping stations restored and rehabilitated | Value | 0.00 | 0.00 | 0.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Training workshop and display building within the main handloom market in Srinagar restored and improved | Value | No | Yes | No |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
SDMA strengthened and operating working DSS | Value | No | No | No |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Number of higher and technical education and other public buildings restored | Value | 0.00 | 18.00 | 4.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Number of non-farm livelihood beneficiaries that received skills training | Value | 0.00 | 2100.00 | 4000.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Guidelines for construction design and materials issued by SDMA | Value | No | Yes | No |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 492427.00 | 850000.00 |
Date | May 22, 2015 | November 24, 2021 | ||
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | May 22, 2015 | April 26, 2018 | ||
Comment |