Financier | Commitments |
---|---|
IDA Grant | 166.00 |
P155266
Closed
Madio Fall
N/A
February 25, 2016
(as of board presentation)
February 25, 2016
N/A
US$ 166.00 million
N/A
2016
US$ 166.00 million
B
Not Applicable
June 30, 2021
TBD
BANK APPROVED
August 5, 2024
Financier | Commitments |
---|---|
IDA Grant | 166.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 166.00 |
IBRD + IDA Commitment | 166.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 166.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 1653060.00 | 2600000.00 |
Date | April 25, 2014 | December 31, 2015 | December 31, 2018 | |
Comment |
Operating cost coverage ratio in utilities targeted by the project | Value | 88.00 | 101.20 | 104.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Secondary and tertiary water networks constructed | Value | 0.00 | 769.82 | 1390.00 |
Date | November 18, 2008 | July 28, 2015 | December 31, 2018 | |
Comment |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 405.00 | 450.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 42382.00 | 87000.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 50100.00 | 110000.00 |
Date | November 18, 2008 | July 28, 2015 | December 31, 2015 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 165306000.00 | 260000000.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Services contract is bid, signed and under implementation | Value | No | Yes | Yes |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Number of water utilities that the project is supporting | Value | 0.00 | 1.00 | 1.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Number of other water service providers that the project is supporting | Value | 0.00 | 0.00 | 0.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Preparation of water sanitation strategies and programm | Value | 1.00 | 3.00 | 3.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Availability rate of production plants | Value | 87.60 | 96.00 | 94.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Non-revenue water | Value | 45.00 | 43.00 | 29.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Rate of inactive connections per city | Value | 36.00 | 33.00 | 20.00 |
Date | April 25, 2014 | December 31, 2015 | December 31, 2018 | |
Comment |
Metering distribution rate | Value | 33.00 | 53.00 | 90.00 |
Date | April 25, 2014 | December 31, 2015 | December 31, 2018 | |
Comment |
Bill collection rate from private connections | Value | 73.00 | 67.00 | 97.00 |
Date | April 25, 2014 | December 31, 2015 | December 31, 2018 | |
Comment |
Number of staff/1000 active connections (after severance plan) | Value | 17.70 | 11.30 | 9.60 |
Date | April 25, 2014 | December 31, 2015 | December 31, 2018 | |
Comment |
Rate of labor costs versus operational costs | Value | 40.00 | 41.00 | 27.00 |
Date | April 25, 2014 | December 31, 2015 | December 31, 2018 | |
Comment |
Submission of previous years' audit reports to clients by May 15 of following year (yes/no) | Value | NA | Yes | Yes |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Proportion of bills owed by "Instances Officielles" in total billing | Value | 24.00 | 22.00 | 20.00 |
Date | April 25, 2014 | December 31, 2015 | December 31, 2018 | |
Comment |
Proportion of volumes owed by "Instances Officielles" in total volumes owed | Value | 21.00 | 19.00 | 34.00 |
Date | April 25, 2014 | July 28, 2015 | December 31, 2015 | |
Comment |
Female beneficiaries | Value | 0.00 | 826530.00 | 1300000.00 |
Date | November 18, 2008 | December 31, 2015 | December 31, 2018 | |
Comment |
Citizen engagemen:Surveyed beneficiaries who know at least two of their responsibilities regarding their access to water | Value | 0.00 | 0.00 | 75.00 |
Date | December 31, 2015 | December 31, 2018 | ||
Comment |
Water production capacity installed under the project | Value | 0.00 | 64000.00 | 179000.00 |
Date | December 31, 2015 | December 31, 2018 | ||
Comment |
Citizen engagement satisfactory complaints resolution by REGIDESO | Value | 26.00 | 0.00 | 56.00 |
Date | December 31, 2018 | |||
Comment |