Zanzibar Urban Services Project Additional Financing

Development Objective

Improve access to urban services and conserve physical cultural heritage in Zanzibar.

Key Details

Project Details

  • P155392

  • Closed

  • Gyongshim An

  • N/A

  • Tanzania

  • May 5, 2016

  • (as of board presentation)

    June 13, 2016

  • N/A

  • US$ 55.00 million

  • A

  • August 5, 2024

  • May 31, 2021

  • TBD

  • BANK APPROVED

  • P111155

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 55.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 55.00
IBRD + IDA Commitment 55.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 55.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.00262311.00394765.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Households suffering from flooding in ZMC areaValue3645.004095.000.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • People in urban areas (ZMC) provided with access to solid waste management services under the projectValue75600.00126215.00190215.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • The Stone Town retains status of World Heritage CityValueYesYesYes
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Female beneficiariesValue52.0052.0052.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Beneficiaries that feel project investments reflected their needs (percentage)Value0.000.0060.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Beneficiaries that feel project inv. reflected their needs - female (number)Value0.000.00117000.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Total beneficiaries - female (number)Value0.00136000.00195000.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Total beneficiaries - male (number)Value0.00126000.00180000.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Beneficiaries that feel project inv. reflected their needs - male (number)Value0.000.00108000.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • ZMC's Change Management Strategic Plan developed and under implementationValueNoYesYes
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Diagrammatic Indicative Structure Plan completedValueNoYesYes
    DateJanuary 28, 2011March 31, 2016June 30, 2016
    Comment
  • Construction of storm water drains completed in ZMC outside of the Stone TownValue0.001300.0021800.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Streets with new lighting installed along selected roads and junctions (kms)Value0.004.2011.20
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Solid waste collection points provided and functionalValue0.0061.0061.00
    DateJanuary 28, 2011March 31, 2016June 30, 2016
    Comment
  • Length of Mizingani sea wall and promenade constructedValue0.00150.00340.00
    DateJanuary 28, 2011March 31, 2016June 30, 2019
    Comment
  • Retooling of 3 Town Councils completedValueNoYesYes
    DateJanuary 28, 2011March 31, 2016June 30, 2016
    Comment
  • Small investments identified and implemented by the three town councils in PembaValueNoYesYes
    DateJanuary 28, 2011November 5, 2015June 30, 2016
    Comment
  • New landfill of 425,000 cubic meters capacity constructed and equipped for operationValueNoNoYes
    DateMarch 31, 2016March 31, 2016June 30, 2019
    Comment
  • Households provided with access to infrastructure and services due to urban upgrading in Ng'ambo areaValue0.000.003246.00
    DateMarch 31, 2016March 31, 2016June 30, 2019
    Comment
  • Zanzibar Heritage Master Plan is updatedValueNoNoYes
    DateMarch 31, 2016March 31, 2016June 30, 2019
    Comment
  • Feasibility Studies for Public Private Partnerships completedValue0.000.004.00
    DateMarch 31, 2016March 31, 2016June 30, 2019
    Comment
  • LGRCIS in ZMC fully operationalValueNoNoYes
    DateMarch 31, 2016March 31, 2016June 30, 2019
    Comment
  • Small investments identified and implemented by the three town councils in PembaValue0.009.0014.00
    DateJanuary 28, 2011March 30, 2016June 30, 2019
    Comment