Financier | Commitments |
---|---|
Clean Technology Fund | 1.00 |
P155510
Closed
Fatma Akcollu Oguz
TEIAS-Turkiye Elektrik Iletim A.S.
July 27, 2015
(as of board presentation)
December 14, 2015
December 25, 2015
US$ 1.00 million
TEIAS-Turkiye Elektrik Iletim A.S.
2016
US$ 1.00 million
C
Not Applicable
March 31, 2019
BANK APPROVED
October 2, 2023
Financier | Commitments |
---|---|
Clean Technology Fund | 1.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.00 |
Total Project Cost** | 1.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
A new generation plan is prepared using the new planning software tool and submitted to the Government of Turkey | Value | No | Yes | No |
Date | August 31, 2015 | September 30, 2017 | March 14, 2018 | |
Comment |
At least 25 TEIAS employees are trained to use the new SCADA system | Value | No | Yes | Yes |
Date | August 31, 2015 | September 30, 2017 | March 14, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of TEIAS (and Government of Turkey) staff trained on using the new soiftware tool | Value | 0.00 | 8.00 | 8.00 |
Date | August 31, 2015 | September 30, 2017 | March 14, 2018 | |
Comment |
New software tool is installed at TEIAS | Value | No | Yes | Yes |
Date | August 31, 2015 | September 30, 2016 | March 14, 2018 | |
Comment |
Number of staff at TEIAS trained on use of new SCADA systems | Value | 0.00 | 25.00 | 25.00 |
Date | August 31, 2015 | September 30, 2017 | March 14, 2018 | |
Comment |
A new generation plan is prepared using the new software tool and submitted to Government of Turkey for approval. | Value | No | Yes | No |
Date | August 31, 2015 | September 30, 2017 | March 14, 2018 | |
Comment |