Renewable Energy Integration Technical Assistance Project

Development Objective

To enhance capacity for generation planning, transmission planning, and grid management in Turkey in anticipation of increased share of renewable energy in the generation mix.

Key Details

Project Details

  • P155510

  • Closed

  • Fatma Akcollu Oguz

  • TEIAS-Turkiye Elektrik Iletim A.S.

  • Turkiye

  • July 27, 2015

  • (as of board presentation)

    December 14, 2015

  • December 25, 2015

  • US$ 1.00 million

  • TEIAS-Turkiye Elektrik Iletim A.S.

  • Europe and Central Asia

  • 2016

  • US$ 1.00 million

  • C

  • Not Applicable

  • March 31, 2019

  • BANK APPROVED

  • October 2, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Clean Technology Fund 1.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 1.00
Total Project Cost** 1.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2018-03-20
Progress towards achievement of PDO Moderately Satisfactory 2018-03-20
Overall Low 2018-03-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • A new generation plan is prepared using the new planning software tool and submitted to the Government of TurkeyValueNoYesNo
    DateAugust 31, 2015September 30, 2017March 14, 2018
    Comment
  • At least 25 TEIAS employees are trained to use the new SCADA systemValueNoYesYes
    DateAugust 31, 2015September 30, 2017March 14, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of TEIAS (and Government of Turkey) staff trained on using the new soiftware toolValue0.008.008.00
    DateAugust 31, 2015September 30, 2017March 14, 2018
    Comment
  • New software tool is installed at TEIASValueNoYesYes
    DateAugust 31, 2015September 30, 2016March 14, 2018
    Comment
  • Number of staff at TEIAS trained on use of new SCADA systemsValue0.0025.0025.00
    DateAugust 31, 2015September 30, 2017March 14, 2018
    Comment
  • A new generation plan is prepared using the new software tool and submitted to Government of Turkey for approval.ValueNoYesNo
    DateAugust 31, 2015September 30, 2017March 14, 2018
    Comment