Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 52.39 |
Borrower/Recipient | 2.19 |
P155594
Closed
Gayane Minasyan , Cesar Niculescu
N/A
Romania
December 10, 2015
(as of board presentation)
March 28, 2016
N/A
US$ 54.58 million
N/A
2016
US$ 52.39 million
B
February 6, 2024
December 31, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 52.39 |
Borrower/Recipient | 2.19 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 52.39 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 52.39 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 54.58 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of population in the project area adopting preventative and remedial measures to reduce nutrient discharges (index measures various rural waste management and good agricultural practices) | Value | 3% | 52.6% | 75% |
Date | February 26, 2009 | November 4, 2015 | March 31, 2022 | |
Comment |
Improved inter-governmental coordination and capacity to assess, monitor and report on progress with implementation of the EU Nitrates Directive | Value | TBD from gap analysis report | Improvements acknowledged - Good capacity of the g | Improvements acknowledged |
Date | February 1, 2008 | November 4, 2015 | March 31, 2022 | |
Comment |
Favorable EU assessment of Romania's progress towards meeting EU Nitrates Directive | Value | n.a. | Progress acknowledged | Progress acknowledged through EU comments on repor |
Date | February 1, 2008 | November 4, 2015 | March 31, 2022 | |
Comment |
Nutrient load reduction (Nitrogen(N)) achieved under the project | Value | 0.00 | 255.50 | 600.00 |
Date | February 1, 2008 | November 4, 2015 | March 31, 2022 | |
Comment |
Land users adopting sustainable land mgt. practices as a result of the project | Value | 0.00 | 17400.00 | 21000.00 |
Date | February 1, 2008 | September 30, 2015 | May 31, 2017 | |
Comment |
Downward trend of nitrates concentration in waters: at least 70% of targeted project areas show 10% reduction in nitrates dischargeto water bodies | Value | 0 | 61.5% | 70% |
Date | February 16, 2007 | November 4, 2015 | March 31, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Relevant legislation updated and Ministerial Orders issued clearly defining responsibilities. EU reporting process tested and usinginputs of multiple institutions. | Value | Legislative and reporting framework un-tested | Completed | EU acceptance of Romania report. |
Date | February 16, 2007 | November 4, 2015 | May 31, 2017 | |
Comment |
Unified set of monitoring guidelines and standards for soil and water adopted, and monitoring program implemented. | Value | Separated monitoring frameworks for water and soil | Completed | Satisfactory Implementation to meet government and |
Date | February 16, 2007 | November 4, 2015 | May 31, 2017 | |
Comment |
Working groups at Water Basin and County levels functioning effectively and all staff working on the Nitrates Directive fully operational. | Value | Ad-hoc implementation of working groups | WGs are functioning effectively | WGs effective to support EU reporting and to coord |
Date | February 16, 2007 | November 4, 2015 | March 31, 2022 | |
Comment |
Number of technical staff (ANAR, EPA, Health Directorates) trained (cumulative) | Value | 0 | 302 | 700 |
Date | February 26, 2009 | November 4, 2015 | March 31, 2022 | |
Comment |
Number of communal platforms completed (cumulative) | Value | 0 | 63 | 150 |
Date | February 26, 2009 | November 4, 2015 | March 31, 2022 | |
Comment |
Number of project communes implementing at least one of the following nutrient reduction measures: communal platforms, pasture rehabilitation, tree planting (cumulative) | Value | 0 | 92 | 200 |
Date | February 26, 2009 | November 4, 2015 | May 31, 2022 | |
Comment |
Land area where sustainable land mgt. practices were adopted as a result of proj | Value | 0.00 | 15262.00 | 38000.00 |
Date | February 1, 2008 | November 4, 2015 | March 31, 2022 | |
Comment |
Increased number of groundwater quality monitoring sites and sample analysis for the Nitrate Directive | Value | 7.50 | 7.50 | 8.00 |
Date | November 4, 2015 | November 4, 2015 | March 31, 2022 | |
Comment | density per 1000 km2 |
Number of farmers trained by knowledge and training providers on Code of Good Agricultural Practices (male/female disaggregated) | Value | 0.00 | 0.00 | 6000.00 |
Date | November 4, 2015 | November 4, 2015 | March 31, 2022 | |
Comment |
Number of meetings/public consultations/workshops organized towards meeting project objectives | Value | 0.00 | 0.00 | 100.00 |
Date | November 4, 2015 | November 4, 2015 | March 31, 2022 | |
Comment |
Percentage of questions, comments or complaints relevant to the project that are received and addressed within indicated 30 days | Value | 0.00 | 0.00 | 100.00 |
Date | November 4, 2015 | November 4, 2015 | March 31, 2022 | |
Comment |
Number of surveys conducted that collect feedback and report back the results to the communities | Value | 0.00 | 0.00 | 3.00 |
Date | November 4, 2015 | November 4, 2015 | March 31, 2022 | |
Comment |
Reduction in number of farmers penalized by APIA for non-compliance with Nitrate Directive | Value | 50.00 | 50.00 | 30.00 |
Date | September 30, 2015 | December 2, 2015 | March 31, 2022 | |
Comment |
Land users adopting sustainable land mgt. practices as a result of the project | Value | 0.00 | 17400.00 | 30000.00 |
Date | February 1, 2008 | November 4, 2015 | March 31, 2022 | |
Comment | In reality this is not a new indicator. This used to be the PDO level indicator and monitored since the beginning of the project.It was just moved to the list of intermediate results indicators |
Number of female farmers trained by knowledge and training providers on Code of Good Agricultural Practices | Value | 0.00 | 0.00 | 3000.00 |
Date | November 4, 2015 | November 4, 2015 | March 31, 2022 | |
Comment |
Percentage of cropped area in the project communes under relevant nutrient reduction measures. | Value | 9% (updated from baseline survey) | 38% | 60% |
Date | February 26, 2009 | November 4, 2015 | May 31, 2022 | |
Comment |
Percentage of households with access and connection to sewage system (in targeted villages receiving sewage investments) | Value | 0 | 27% | 60% |
Date | February 16, 2007 | November 4, 2015 | March 31, 2022 | |
Comment |