Skip to Main Navigation

Burkina-Faso eGovernment Project

Abstract*

The objective of the eBurkina Project is to improve capacity and use of ICTs by the public administrations and agencies for (i) the provision of information and public e-services and (ii) to foster entrepreneurship in the digital economy, with a specific focus on agriculture and rural areas. There are four components to the project, the first component being enabling environment for e-Government, including policy, legal and regulatory frameworks...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Proposed Development Objective(s) The proposed Project Development Objective (PDO) is to improve capacity and use of ICTs by the public administrations and agencies for (i) the provision of information and public e-services and (ii) to foster entrepreneurship inthe digital economy, with a specific focus on agriculture and rural areas.

Key Details

Project Details

  • P155645

  • Closed

  • Tounwende Sawadogo

  • Burkina Faso

  • Burkina Faso

  • November 1, 2016

  • (as of board presentation)

    January 18, 2017

  • June 29, 2017

  • US$ 20.00 million

  • Agence Nationale de Promotion des TIC

  • Western and Central Africa

  • 2017

  • US$ 20.00 million

  • C

  • April 2, 2024

  • December 30, 2022

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 20.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2020 IDA-59430 Int Charges 27,978.65
Sep 15, 2020 IDA-59430 Int Charges 27,978.65
Mar 15, 2021 IDA-59430 Int Charges 1,016.10
Mar 15, 2021 IDA-59430 Int Charges 1,016.10
Mar 15, 2021 IDA-59430 Int Charges 33,837.79
Mar 15, 2021 IDA-59430 Int Charges 33,837.79
Mar 15, 2021 IDA-59430 Int Charges 93.81
Mar 15, 2021 IDA-59430 Int Charges 93.81
Mar 5, 2021 IDA-59430 Loan Disb 750,014.44
Sep 15, 2021 IDA-59430 Int Charges 37,613.08
Jul 31, 2017 IDA-59430 Loan Disb 1,251,919.00
Mar 15, 2018 IDA-59430 Int Charges 1,236.79
Mar 15, 2018 IDA-59430 Int Charges 1,236.79
Mar 15, 2018 IDA-59430 Int Charges 4,947.18
Mar 15, 2018 IDA-59430 Int Charges 4,947.18
Apr 16, 2018 IDA-59430 Loan Disb 208,736.62
Sep 15, 2018 IDA-59430 Int Charges 5,243.08
Sep 15, 2018 IDA-59430 Int Charges 5,243.08
Dec 4, 2018 IDA-59430 Loan Disb 74,908.27
Nov 7, 2018 IDA-59430 Loan Disb 229,520.62
Feb 5, 2019 IDA-59430 Loan Disb 397,985.66
May 8, 2019 IDA-59430 Loan Disb 935,573.80
Mar 18, 2019 IDA-59430 Int Charges 51.22
Mar 18, 2019 IDA-59430 Int Charges 51.22
Mar 18, 2019 IDA-59430 Int Charges 5,967.93
Mar 18, 2019 IDA-59430 Int Charges 5,967.93
Jul 11, 2019 IDA-59430 Loan Disb 1,174,474.40
Jul 11, 2019 IDA-59430 Loan Disb 966,567.75
Mar 11, 2019 IDA-59430 Loan Disb 792,248.50
Sep 15, 2019 IDA-59430 Int Charges 15,805.49
Sep 15, 2019 IDA-59430 Int Charges 15,805.49
Jan 18, 2017 IDA-59430 Loan Commitment 20,000,000.00
Mar 14, 2023 IDA-59430 Loan Disb 1,555,973.00
Mar 15, 2023 IDA-59430 Int Charges 1,643.15
Mar 15, 2023 IDA-59430 Int Charges 1,643.15
Mar 15, 2023 IDA-59430 Loan Repay 264,779.53
Mar 15, 2023 IDA-59430 Int Charges 47,382.82
Mar 15, 2023 IDA-59430 Int Charges 47,382.82
Apr 30, 2023 IDA-59430 Loan Cancel 73,993.23
Sep 15, 2023 IDA-59430 Int Charges 62,183.78
Sep 15, 2023 IDA-59430 Int Charges 62,183.78
Sep 15, 2023 IDA-59430 Int Charges 50.41
Sep 15, 2023 IDA-59430 Int Charges 50.41
Sep 15, 2023 IDA-59430 Loan Repay 265,972.34
Sep 15, 2023 IDA-59430 Loan Repay 50.41
Mar 15, 2024 IDA-59430 Loan Repay 271,889.44
Mar 15, 2024 IDA-59430 Int Charges 63,214.28
Mar 15, 2024 IDA-59430 Int Charges 63,214.28
Sep 15, 2021 IDA-59430 Int Charges 37,613.08
Sep 15, 2021 IDA-59430 Int Charges 154.88
Sep 15, 2021 IDA-59430 Int Charges 154.88
Jun 21, 2022 IDA-59430 Loan Disb 391,335.12
Jun 21, 2022 IDA-59430 Loan Disb 615,923.25
Mar 15, 2022 IDA-59430 Int Charges 36,172.04
Mar 15, 2022 IDA-59430 Int Charges 36,172.04
Dec 3, 2021 IDA-59430 Loan Disb 580,735.30
Jul 20, 2022 IDA-59430 Loan Disb 973,311.00
Aug 23, 2022 IDA-59430 Loan Disb 980,236.44
Dec 2, 2022 IDA-59430 Loan Cancel 2,902,256.00
Sep 15, 2022 IDA-59430 Int Charges 35,326.74
Sep 15, 2022 IDA-59430 Int Charges 35,326.74
Apr 6, 2023 IDA-59430 Loan Disb 146,134.55
Apr 17, 2023 IDA-59430 Loan Disb 153,467.67
Apr 17, 2023 IDA-59430 Loan Disb 117,192.60
Apr 17, 2023 IDA-59430 Loan Disb 117,170.20
Apr 21, 2023 IDA-59430 Loan Disb 207,055.56
Mar 22, 2023 IDA-59430 Loan Disb 1,012,575.20
Mar 27, 2023 IDA-59430 Loan Disb 218,180.81
Mar 14, 2023 IDA-59430 Loan Disb 878,529.90
Mar 15, 2023 IDA-59430 Loan Repay 1,643.15
Sep 15, 2019 IDA-59430 Int Charges 441.42
Sep 15, 2019 IDA-59430 Int Charges 441.42
Dec 30, 2019 IDA-59430 Loan Disb 711,964.80
Dec 18, 2019 IDA-59430 Loan Disb 383,575.50
Mar 15, 2020 IDA-59430 Int Charges 79.97
Mar 15, 2020 IDA-59430 Int Charges 79.97
Mar 15, 2020 IDA-59430 Int Charges 23,939.44
Mar 15, 2020 IDA-59430 Int Charges 23,939.44
Jul 15, 2020 IDA-59430 Loan Disb 851,472.30
Nov 17, 2020 IDA-59430 Loan Disb 994,776.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2022-12-22
Monitoring and Evaluation Satisfactory 2022-12-22
Project Management Satisfactory 2022-12-22
Overall Implementation Progress (IP) Moderately Satisfactory 2022-12-22
Procurement Moderately Satisfactory 2022-12-22
Financial Management Moderately Satisfactory 2022-12-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-01-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People using the Digital Platform for e-Service DeliveryValue0.008065.001000.00
    DateJanuary 2, 2017December 30, 2022December 31, 2019
    Comment
  • Startups, SMEs and Civic tech incubated (number) (including percent focusing on agriculture or rural areas)Value0.0076.000.00
    DateJanuary 2, 2017December 30, 2022
    Comment
  • e-Services deployed through the Digital Platform for e-Service Delivery, including number of e-Services targeting rural areasValue0.007.002.00
    DateJanuary 2, 2017December 30, 2022
    Comment
  • Percentage of ICT projects incubated and targeting rural areasValue0.000.000.00
    DateJanuary 2, 2017May 17, 2017
    Comment
  • Public authorities and external producers providing information as open data on the portal data.gov.bfValue31.00106.0060.00
    DateNovember 30, 2016December 30, 2022
    Comment
  • People trained under the project (including percentage of women)Value0.005000.001000.00
    DateJanuary 2, 2017December 30, 2022July 16, 2019
    Comment
  • Percentage of women trained under the projectValue0.0028.0033.00
    DateJanuary 2, 2017July 10, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Publication of a national e-Government strategyValueNoYesYes
    DateFebruary 1, 2017December 30, 2022
    Comment
  • Unique users of GIS e-Service for rural development and food security managementValue0.004000.001000.00
    DateFebruary 1, 2017December 30, 2022
    Comment
  • Incubator open to the publicValueNoYesNo
    DateJanuary 2, 2017December 30, 2022
    Comment
  • Citizens consulted for the design and delivery of e-Services (citizen engagement)Value0.001000.00200.00
    DateFebruary 1, 2017December 30, 2022July 1, 2019
    Comment
  • Publication of an e-Government technical frameworkValueNoYesYes
    DateFebruary 1, 2017December 30, 2022
    Comment
  • Unique users of the e-Service for agricultural markets informationValue0.0040000.0010000.00
    DateFebruary 1, 2017December 30, 2022
    Comment
  • Number of visitors at the incubator including womenValue0.005000.000.00
    DateJanuary 2, 2017December 30, 2022
    Comment
  • Number of municipalities having their performance indicators available as open dataValue0.00350.00140.00
    DateFebruary 1, 2017December 30, 2022September 3, 2018
    Comment
  • Percentage of women visiting the incubatorValue0.000.000.00
    DateJanuary 2, 2017
    Comment