Financier | Commitments |
---|---|
Borrower/Recipient | 1.08 |
Pacific Regional Infrastructure Facility Trust Fund | 0.31 |
IDA Grant | 7.25 |
P156018
Closed
Julie Babinard , Pierre Graftieaux
N/A
December 8, 2015
(as of board presentation)
March 9, 2016
N/A
US$ 8.64 million
N/A
2016
US$ 7.56 million
B
July 15, 2021
December 31, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 1.08 |
Pacific Regional Infrastructure Facility Trust Fund | 0.31 |
IDA Grant | 7.25 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 7.25 |
IBRD + IDA Commitment | 7.25 |
Lending Instrument | |
---|---|
Grant Amount | 0.31 |
Total Project Cost** | 8.64 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Indicator Three: Modernization of air traffic management | Value | Very Small Aperture Terminal (VSAT) (previously PA | Very Small Aperture Terminal (VSAT) (previously PA | Very Small Aperture Terminal (VSAT) (previously PA |
Date | December 13, 2011 | October 7, 2015 | December 31, 2016 | |
Comment | NavAids contract has been signed and this indicator will be satisfied as these investments are installed. The ADS-B roll out thatwill satisfy this indicator is expected to be installed over 2015/16. |
Indicator Four: Implementation of a regional safety and security levy for departing international passengers | Value | No Levy | Levy implemented and returning revenue to Tonga. | AU$ 5 collected from each departing international |
Date | December 13, 2011 | October 7, 2015 | December 31, 2016 | |
Comment | Implemented in 2013 and collection is progressing well. Disbursement framework was agreed this quarter and the levy will be auditedfrom the current financial year onwards. |
Indicator One: Regulatory certification of safety and security at project airports | Value | Fua’amotu Airport (TBU) currently certified, Vava’ | TBU remains certified. VAV is expected to be certi | Certification of both airports in accordance with |
Date | December 13, 2011 | October 7, 2015 | December 31, 2016 | |
Comment |
Indicator Two: State requirements for safety and security reaches global ICAO average | Value | 90.70 | 8.00 | 49.00 |
Date | December 13, 2011 | October 7, 2015 | June 30, 2016 | |
Comment | Runway civil works and supply and installation of navigation aids underway. Improvements are expected with the support of theAviation Adviser, however progress on corrective action plans is not known. Works on the terminal and traffic control towersproposed to be funded by the AF. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component A: Intermediate Result indicator One: Navigation and safety aids fully operational | Value | 0.00 | 20.00 | 100.00 |
Date | December 13, 2011 | October 7, 2015 | December 31, 2016 | |
Comment | NavAids contract has been signed and this indicator will be satisfied as these investments are installed. |
Component A: Intermediate Result indicator Two: Rehabilitation of Fua'amotu and Vava'u runways | Value | 0.00 | 20.00 | 100.00 |
Date | December 13, 2011 | October 7, 2015 | December 31, 2016 | |
Comment | Under progress in both TBU and VAV. Current completion date is according to schedule with no delays. |
Component A: Intermediate Result indicator Three: Energy efficient runway lighting fullyoperational and compliant at TBU | Value | Lighting not upgraded. | Lighting not upgraded. | Lighting fully operational. |
Date | December 13, 2011 | October 7, 2015 | December 31, 2016 | |
Comment | To be installed with the NavAids contract which has been signed and installation expected later in 2015. |
Component B: Intermediate Result indicator One: Preparation of necessary legislation for establishment of Tonga Airports Authority | Value | No legislation | Legislation drafted | Legislation prepared |
Date | December 13, 2011 | October 7, 2015 | December 31, 2016 | |
Comment | Legislation is drafted however has not been enacted. This will need to be pursued further. |
Component B: Intermediate Result indicator Two: Successful implementation of agreed training plan | Value | No training plan | Training plan under implementation. | Training plan completed |
Date | December 13, 2011 | October 7, 2015 | June 30, 2016 | |
Comment | Currently underway. An annual training program will be included in future quarterly reports. |
Citizen Engagement | Value | 0.00 | 0.00 | 100.00 |
Date | November 13, 2015 | November 13, 2015 | December 31, 2018 | |
Comment | New indicator for citizen engagement. The target is to resolve all grievances on the project, across all years of implementation. |
Construction and Operation of Air Traffic Control Tower (TBU) | Value | 20151109 | 20151109 | 20181231 |
Date | November 9, 2015 | November 9, 2015 | December 31, 2018 | |
Comment | Existing tower needs to be replaced with new tower at different location with new technologies and equipment installed. | The control tower is built, equipment installed and tower is operational. |