Tonga Aviation Investment Project - Additional Financing

Development Objective

The project development objective is to improve operational safety and oversight of international air transport infrastructure.

Key Details

Project Details

  • P156018

  • Closed

  • Julie Babinard , Pierre Graftieaux

  • N/A

  • Tonga

  • December 8, 2015

  • (as of board presentation)

    March 9, 2016

  • N/A

  • US$ 7.56 million

  • B

  • July 15, 2021

  • December 31, 2019

  • Yes

  • BANK APPROVED

  • P128939

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 1.08
Pacific Regional Infrastructure Facility Trust Fund 0.31
IDA Grant 7.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 7.25
IBRD + IDA Commitment 7.25
Lending Instrument
Grant Amount 0.31
Total Project Cost** 8.64

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator Three: Modernization of air traffic managementValueVery Small Aperture Terminal (VSAT) (previously PAVery Small Aperture Terminal (VSAT) (previously PAVery Small Aperture Terminal (VSAT) (previously PA
    DateDecember 13, 2011October 7, 2015December 31, 2016
    CommentNavAids contract has been signed and this indicator will be satisfied as these investments are installed. The ADS-B roll out thatwill satisfy this indicator is expected to be installed over 2015/16.
  • Indicator Four: Implementation of a regional safety and security levy for departing international passengersValueNo LevyLevy implemented and returning revenue to Tonga.AU$ 5 collected from each departing international
    DateDecember 13, 2011October 7, 2015December 31, 2016
    CommentImplemented in 2013 and collection is progressing well. Disbursement framework was agreed this quarter and the levy will be auditedfrom the current financial year onwards.
  • Indicator One: Regulatory certification of safety and security at project airportsValueFua’amotu Airport (TBU) currently certified, Vava’TBU remains certified. VAV is expected to be certiCertification of both airports in accordance with
    DateDecember 13, 2011October 7, 2015December 31, 2016
    Comment
  • Indicator Two: State requirements for safety and security reaches global ICAO averageValue90.708.0049.00
    DateDecember 13, 2011October 7, 2015June 30, 2016
    CommentRunway civil works and supply and installation of navigation aids underway. Improvements are expected with the support of theAviation Adviser, however progress on corrective action plans is not known. Works on the terminal and traffic control towersproposed to be funded by the AF.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component A: Intermediate Result indicator One: Navigation and safety aids fully operationalValue0.0020.00100.00
    DateDecember 13, 2011October 7, 2015December 31, 2016
    CommentNavAids contract has been signed and this indicator will be satisfied as these investments are installed.
  • Component A: Intermediate Result indicator Two: Rehabilitation of Fua'amotu and Vava'u runwaysValue0.0020.00100.00
    DateDecember 13, 2011October 7, 2015December 31, 2016
    CommentUnder progress in both TBU and VAV. Current completion date is according to schedule with no delays.
  • Component A: Intermediate Result indicator Three: Energy efficient runway lighting fullyoperational and compliant at TBUValueLighting not upgraded.Lighting not upgraded.Lighting fully operational.
    DateDecember 13, 2011October 7, 2015December 31, 2016
    CommentTo be installed with the NavAids contract which has been signed and installation expected later in 2015.
  • Component B: Intermediate Result indicator One: Preparation of necessary legislation for establishment of Tonga Airports AuthorityValueNo legislationLegislation draftedLegislation prepared
    DateDecember 13, 2011October 7, 2015December 31, 2016
    CommentLegislation is drafted however has not been enacted. This will need to be pursued further.
  • Component B: Intermediate Result indicator Two: Successful implementation of agreed training planValueNo training planTraining plan under implementation.Training plan completed
    DateDecember 13, 2011October 7, 2015June 30, 2016
    CommentCurrently underway. An annual training program will be included in future quarterly reports.
  • Citizen EngagementValue0.000.00100.00
    DateNovember 13, 2015November 13, 2015December 31, 2018
    CommentNew indicator for citizen engagement. The target is to resolve all grievances on the project, across all years of implementation.
  • Construction and Operation of Air Traffic Control Tower (TBU)Value201511092015110920181231
    DateNovember 9, 2015November 9, 2015December 31, 2018
    CommentExisting tower needs to be replaced with new tower at different location with new technologies and equipment installed.The control tower is built, equipment installed and tower is operational.