Development Objective

TThe objectives of the Project are to: (a) support the establishment of building blocks for the social safety net system; and (b) increase the access of poor and vulnerable households to targeted and adaptive cash transfers programs.

Key Details

Project Details

  • P156160

  • Closed

  • Aline Coudouel

  • N/A

  • Senegal

  • May 13, 2016

  • (as of board presentation)

    August 24, 2016

  • N/A

  • US$ 11.05 million

  • C

  • January 17, 2024

  • March 15, 2024

  • Yes

  • BANK APPROVED

  • P133597

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Free-standing TFs AFR Human Development 11.05

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 11.05
Total Project Cost** 11.05

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of households enrolled in the RNUValue60000.00280000.00450000.00
    DateMay 1, 2014March 31, 2016June 30, 2019
    CommentTarget in the original Project was 210000
  • Percentage of PNBSF beneficiary households who live below the poverty lineValue0.000.0080.00
    DateMay 1, 2014March 31, 2016June 30, 2019
    Comment
  • Percentage of female among beneficiaries of the PNBSFValue50.0050.0050.00
    DateMay 1, 2014March 31, 2016June 30, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of modules of the MIS PNBSF that are operational: beneficiary management, conditionality monitoring, payment, promotion and communication, grievance management, and adaptive interventionValue0.001.006.00
    DateMay 1, 2014March 31, 2016June 30, 2019
    CommentIndicator was revised to reflect separation of the PNBSF MIS and the RNU MIS
  • Percentage of complaints and grievances of the PNBSF resolved without delayValue0Definition underway60% cases resolved without delay
    DateMay 1, 2014March 31, 2016June 30, 2019
    CommentIndicator was revised to reflect separation of complaint and grievance system of the PNBSF and RNU
  • Number of MOUs signed between the DGPSN and sectorial actors to define sectoral involvement in the PNBSF.Value0.000.004.00
    DateMay 1, 2014June 30, 2019
    Comment
  • Share of households in the unique registry with complete informationValue65.000.0080.00
    DateMay 1, 2014June 30, 2019
    Comment
  • Percentage of PNBSF beneficiaries who know the programâ??s parameters as mentioned in the community scorecard (on their rights and responsibilities with regard to conditionalities, program rules, andValue0.000.0080.00
    DateMay 1, 2014June 30, 2019
    CommentIndicator revised to reflect introduction of community scorecards
  • Share of PNBSF beneficiary households for which the conditionality on attendance to the sensitization sessions was monitored duringthe last four sessionsValue0.000.0080.00
    DateMay 1, 2014March 31, 2016June 30, 2019
    CommentIndicator revised to reflect revised conditionality for PNBSF
  • Share of 6-12 years old in PNBSF beneficiaries households who respect the education conditionality (in the area where this conditionality is implemented)Value0.000.0075.00
    DateMay 1, 2014March 17, 2016June 30, 2019
    CommentRevised indicator to reflect pilot education conditionality monitoring system
  • Share of PNBSF beneficiary households who attended the last four sensitization sessionsValue0.000.0070.00
    DateMay 1, 2014March 17, 2016June 30, 2019
    CommentIndicator revised to reflect revised conditionality for PNBSF
  • Percentage of PNBSF beneficiaries receiving payments according to the program manualValueBase+20 p.p
    DateMay 1, 2014June 30, 2019
    Comment
  • Number of annual evaluations of the PNBSF on the basis of community score cardsValue0.000.004.00
    DateMay 1, 2014March 31, 2016June 30, 2019
    CommentIndicator revised to reflect introduction of community scorecards
  • Number of PNBSF beneficiary households (who have been registered)Value48000.0099924.00300000.00
    DateMay 1, 2014March 31, 2016June 30, 2019
    CommentTarget in original Project was 248,000
  • Number of modules of the MIS of the RNU that are operational: geographic segmentation, geographic targeting, community targeting, categorical targeting, promotion and communication, grievance managemeValue0.000.007.00
    DateMarch 15, 2016March 31, 2016June 30, 2019
    CommentIndicator was added to reflect separation of the PNBSF MIS and the RNU MIS
  • Utilization of a module of the RNU MIS for sectoral department to request dataValue00YES
    DateMarch 15, 2016March 31, 2016June 30, 2019
    Comment
  • Number of households benefiting from temporary transfers in response to shocksValue0.000.0011500.00
    DateMarch 15, 2016March 15, 2016June 30, 2019
    CommentNew indicator to reflect added focus on adaptive activities.
  • Number of households in the RNU benefiting from productive accompanying measures. The measures include (a) the preferential inclusion of poor households in existing resilience programs and (b) accompValue0.000.0050000.00
    DateMarch 17, 2016March 17, 2016June 30, 2019
    CommentNew indicator to reflect added focus on adaptive activities.
  • Share of PNBSF beneficiary households for which the education conditionality was monitored during the last quarter (in the area where this conditionality is implemented)Value0.000.0080.00
    DateMarch 17, 2016March 31, 2016June 30, 2019
    CommentNew indicator on pilot education conditionality monitoring system
  • Number of households in the RNU benefiting from productive transfersValue0.000.0020000.00
    DateMarch 17, 2016March 17, 2016June 30, 2019
    CommentNew indicator to reflect added focus on adaptive activities.
  • Percentage of complaints and grievances of the RNU resolved without delayValue0.000.0060.00
    DateMarch 15, 2016March 31, 2016June 30, 2019
    CommentIndicator was added to reflect separation of complaint and grievance system of the PNBSF and RNU
  • Adoption of an adaptation framework for social safety nets, describing social protection responses to shocks by the CIP/SNPSValueNoNoYes
    DateMarch 15, 2016March 31, 2016June 30, 2019
    CommentNew indicator to reflect added focus on adaptive activities.
  • Share of local committees who understand the objectives of the RNUValue0.000.0080.00
    DateMarch 15, 2016March 31, 2016June 30, 2019
    CommentNew indicators to measure quality of RNU processes.