Private Sector Development Support Project Additional Financing

Development Objective

Facilitate private investment and job creation and promote compliance with international quality standards, building codes, and good social and environmental practices in economic zones supported by PSDSP.

Key Details

Project Details

  • P156242

  • Closed

  • Michael Engman

  • People's Republic of Bangladesh

  • Bangladesh

  • December 13, 2015

  • (as of board presentation)

    April 5, 2016

  • N/A

  • US$ 137.00 million

  • Economic Relations Division (ERD)

  • South Asia

  • 2016

  • US$ 130.00 million

  • A

  • May 27, 2021

  • February 28, 2021

  • Yes

  • BANK APPROVED

  • P120843

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 7.00
IDA Credit 130.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 130.00
IBRD + IDA Commitment 130.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 137.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct private investment by zone tenant companies located within new zonesValue0.005.0010.00
    DateAugust 3, 2011September 10, 2015June 30, 2016
    Comment
  • Cumulative number of jobs facilitated by PSDSPValue0.003252.0015500.00
    DateAugust 3, 2010January 31, 2016February 28, 2021
    Comment
  • Cumulative number of jobs facilitated by PSDSP of which are femaleValue0.0028.0030.00
    DateAugust 3, 2010January 31, 2016February 28, 2021
    Comment
  • Share of tenant firms in EZs complying with quality standards (ISO 9000 or equivalent)Value0.000.0020.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Share of tenant firms in EZs complying with building codesValue0.000.00100.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Share of tenant firms in EZs complying with environmental standards (ISO 14000 or equivalent)Value0.000.0020.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Cumulative direct total private investment in EZs (USD millions)Value15000000.000.00125000000.00
    DateJanuary 31, 2016January 20, 2015February 28, 2021
    CommentThe indicator is revised to include investments by developers, tenant companies, and last-mile infrastructure provided. Thebaseline was revised accordingly.
  • Number of jobs created (No.) & of which female employment (%)Value0.002823.002000.00
    DateAugust 3, 2011September 10, 2015June 30, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Cumulative number of persons benefitting from demand-driven training or certificationValue0.0013539.0023800.00
    DateAugust 3, 2010January 31, 2016February 28, 2021
    Comment
  • Cumulative number of firms located in economic zones complying with relevant environmental standards (ISO 14000 or equivalent)Value0.0021.0015.00
    DateAugust 3, 2011September 10, 2015June 30, 2016
    Comment
  • Cumulative number of firms complying with Quality standards (ISO 9001 or equivalent)Value19.0052.0030.00
    DateAugust 3, 2011September 10, 2015June 30, 2016
    Comment
  • Cumulative number of developers receiving a license to develop an EZValue0.0011.0035.00
    DateAugust 3, 2010January 31, 2016February 28, 2021
    Comment
  • Time (days) to process business registration in a zone.Value44.008.009.00
    DateAugust 3, 2011September 10, 2015June 30, 2016
    Comment
  • Cumulative number of new operational EZsValue4.000.0015.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Cumulative number of environmental or social counselors maintained at EZsValue85.000.0095.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Cumulative number of local non-tenant firms supported by PSDSP that have received quality or environmental certificationValue77.000.00140.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Cumulative public investment in last mile off-site infrastructure and on-site facilities (USD millions)Value33.000.00139.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Share of persons benefitting from demand-driven training or certification of which are femaleValue0.000.0030.00
    DateAugust 3, 2010September 10, 2015February 28, 2021
    Comment
  • Share of new operational zones with childcare facilitiesValue0.000.00100.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Cumulative number of tenant firmsValue4.000.0048.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Increase in percentage of grievances received from workers in the EZs supported by PSDSP and responded to and/or resolved within one weekValue93.000.0097.00
    DateJanuary 31, 2016February 28, 2021
    Comment
  • Cumulative number of sites with completed assessments, feasibility studies or master plans for new EZsValue1.0025.0059.00
    DateAugust 3, 2010January 31, 2016February 28, 2021
    Comment
  • Development of new economic zones or tech parks (in progress)Value0.005.003.00
    DateAugust 3, 2011September 10, 2015June 30, 2016
    Comment