Special Financing Facility for Local Development

Abstract*

The development objective of the Special Financing Facility for Local Development Project for Somalia is to support the construction and reconstruction of infrastructure and the development of public service delivery capacity in targeted areas of Somalia and support the Federal Government and regional administrations’ capacity to respond to an eligible crisis or emergency. The project comprises of three components. The first component, small-scale...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

<p>To support the construction and reconstruction of infrastructure and the development of public service delivery capacity in targeted areas of Somalia and support the Federal Government and Interim Administration capacity to respond to an eligible crisis or emergency.</p>

Key Details

Project Details

  • P156257

  • Closed

  • Andrew Roberts , Ayaz Parvez

  • Ministry of Finance

  • Somalia

  • November 27, 2015

  • (as of board presentation)

    January 11, 2016

  • January 25, 2016

  • US$ 6.00 million

  • B

  • August 5, 2024

  • March 31, 2020

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Somalia Multi-Partner Fund 6.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 6.00
Total Project Cost** 6.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2019-12-10
Project Management Satisfactory 2019-12-10
Progress towards achievement of PDO Moderately Satisfactory 2019-12-10
Financial Management Moderately Satisfactory 2019-12-10
Overall Implementation Progress (IP) Moderately Satisfactory 2019-12-10
Monitoring and Evaluation Satisfactory 2019-12-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 11-23-2020
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-06-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.00880954.001000000.00
    DateNovember 9, 2015May 15, 2019
    Comment
  • Beneficiaries under the activated crisis response component (#)Value0.00236,123
    DateNovember 9, 2015May 15, 2019
    Comment
  • Sub-projects for which community/ or local authority engagement in post-project sustainability and/ or O&M plan is established (#)Value0.007.005.00
    DateNovember 9, 2015May 15, 2019
    Comment
  • Perceptions of Regional Administrations or federal government performance on sub-project activity (%)Value0.000.0060.00
    DateNovember 9, 2015November 26, 2018
    Comment
  • Female beneficiariesValue0.0050.0051.00
    DateNovember 9, 2015November 26, 2018
    Comment
  • Financed sub-projects that are functioning/ delivering services to communities three months after completion (#)Value0.007.003.00
    DateNovember 9, 2015June 6, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehabilitated, Non-ruralValue0.008.5014.00
    DateNovember 9, 2015May 15, 2019
    Comment
  • Grievances registered related to project are addressed (%)Value0.00100.00100.00
    DateNovember 9, 2015May 15, 2019
    Comment
  • Specific Project Operation Manual for the contingency component (Component 3) has been adoptedValueNoYes
    DateNovember 9, 2015May 15, 2019
    Comment
  • Sub-projects completed as planned and within budget (#)Value0.007.005.00
    DateNovember 9, 2015June 6, 2019
    Comment
  • Interim Regional Administrations accompanying project design and implementation (consultation, identification, procurement and implementation processes) (#)Value0.0011.005.00
    DateNovember 9, 2015May 15, 2019
    Comment
  • Local Project Oversight Committees established (#)Value0.0011.005.00
    DateNovember 9, 2015May 15, 2019
    Comment
  • Government officials participating in capacity building measures under the project (#)Value0.0018.000.00
    DateNovember 9, 2015May 15, 2019
    Comment
  • Work days created for short term employment in the sub-projects (of which female) (#)Value0.00912.000.00
    DateNovember 9, 2015June 6, 2019
    Comment
  • Work days created for short term employment in the sub-projects for womenValue0.00300.0051.00
    DateNovember 9, 2015June 6, 2019
    Comment