Federally Administered Tribal Areas (FATA) Governance and Policy Program

Development Objective

The Project Development Objective (PDO) is to strengthen the capacity of staff in the Merged Areas to manage public resources, and improved accountability in the delivery of public services.

Key Details

Project Details

  • P156412

  • Closed

  • Lucy Pan , Tobias Haque

  • Islamic Republic of Pakistan

  • Pakistan

  • June 30, 2016

  • (as of board presentation)

    December 2, 2016

  • February 23, 2017

  • US$ 16.50 million

  • Planning and Development Department, Government of Khyber-Pakhtunkhwa

  • South Asia

  • 2017

  • US$ 14.00 million

  • C

  • Not Applicable

  • June 30, 2023

  • Yes

  • BANK APPROVED

  • January 31, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrowing Agency 2.50
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan 14.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 14.00
Total Project Cost** 16.50

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2023-08-16
Progress towards achievement of PDO Satisfactory 2023-08-16
Financial Management Satisfactory 2023-08-16
Monitoring and Evaluation Satisfactory 2023-08-16
Overall Implementation Progress (IP) Satisfactory 2023-08-16
Procurement Satisfactory 2023-08-16
Project Management Satisfactory 2023-08-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2024
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-28-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualityModestN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Public assets in the Merged Areas that are geo-taggedValue0.0099.5675.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Staff of Merged Areas Secretariat reporting improvements in on-job performance after participating in trainingValue0.00100.0075.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Complaints from citizens of Merged Areas not resolved within stipulated timelines for services under the RTS ActValue0.004.6420.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Provincial Government employees in Merged Areas who completed Monitoring and Evaluation trainingValue0.0075.0075.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Internal audits conductedValue0.0015.0010.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Progress Report no later than 45 days after end of reporting periodValueNoYesYes
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • of which are womenValue0.0016.0030.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Districts in Merged Areas where Integration of geotagged data into GIS Decision Support System completedValue0.007.005.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Provincial Government employees in Merged Areas who completed Procurement trainingValue0.00229.0060.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Citizens reporting satisfaction with notified services under the RTS ActValue0.0081.0075.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • of which are womenValue0.0023.0030.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Provincial Government employees in Merged Areas who completed sectoral planning trainingValue0.0050.0050.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Provincial Government employees in Merged Areas who completed, at least, the certificate level of the PFM accreditation programValue0.000.0060.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Provincial Government employees in Merged Areas who completed Project Management trainingValue0.0090.0075.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • of which are womenValue0.000.0030.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Provincial Government employees from Merged Areas who have participated in gender awareness sessionsValue0.00100.00100.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment
  • Citizens registered in IGRS to give feedback on government servicesValue0.00737.001000.00
    DateJune 30, 2016June 23, 2023June 30, 2023
    Comment
  • Districts in Merged Areas submitting monthly Budget Execution Reports to FD, within 45 days of end of quarterValue0.007.005.00
    DateJune 30, 2016June 30, 2023June 30, 2023
    Comment