Financier | Commitments |
---|---|
Carbon Initiative for Development | 3.65 |
P156413
Active
Yasmina Oodally
SNV
September 29, 2016
(as of board presentation)
January 21, 2017
December 30, 2016
US$ 6.06 million
Minister of Agriculture, Hydro-agricultural Developments, Mechanization, and Animal and Fishery Reso
2017
US$ 3.65 million
C
March 27, 2024
October 31, 2025
BANK APPROVED
Financier | Commitments |
---|---|
Carbon Initiative for Development | 3.65 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.65 |
Total Project Cost** | 6.06 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2025-04-01 |
Financial Management | Satisfactory | 2025-04-01 |
Monitoring and Evaluation | Satisfactory | 2025-04-01 |
Procurement | Satisfactory | 2025-04-01 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-04-01 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-04-01 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 8000.00 | 135014.00 | 110670.00 |
Date | December 31, 2015 | December 31, 2023 | December 31, 2024 | |
Comment |
Biodigester installer per year - operating and in use (number) | Value | 1323.00 | 309.00 | 1800.00 |
Date | December 31, 2015 | December 31, 2023 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
ERPA amount covered by the installed capacity | Value | 0.00 | 84.00 | 65.00 |
Date | December 31, 2015 | December 31, 2023 | December 31, 2024 | |
Comment |
biodigester sector development | Value | 0.00 | 0.00 | 3.00 |
Date | December 31, 2015 | December 31, 2023 | December 31, 2024 | |
Comment |
PNB-BF financing gap covered by the installed capacity of CER production | Value | 0.00 | 70.00 | 65.00 |
Date | December 31, 2015 | December 31, 2023 | December 31, 2024 | |
Comment |