The development objective of the Oromia National Regional State Forested Landscape Project for Ethiopia is to improve the enabling environment for sustainable forest managementand investment in Oromia. The project has three components. First component, enabling investments will finance investment in PFM (including livelihoods support and selected nature-based community enterprise development) and reforestation in deforestation hotspots insites to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Development Objective is to improve the enabling environment for sustainable forest management and investment in Oromia.

Key Details

Project Details

  • P156475

  • Closed

  • Nicholas Zmijewski , Nigel Hughes

  • Federal Democratic Republic of Ethiopia

  • Ethiopia

  • November 23, 2015

  • (as of board presentation)

    March 17, 2017

  • April 28, 2017

  • US$ 18.00 million

  • B

  • Not Applicable

  • June 30, 2023

  • Yes

  • BANK APPROVED

  • July 29, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
BioCarbon Technical Assistance Trust Fund 18.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 18.00
Total Project Cost** 18.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2023-05-22
Procurement Moderately Satisfactory 2023-05-22
Financial Management Moderately Satisfactory 2023-05-22
Progress towards achievement of PDO Satisfactory 2023-05-22
Overall Implementation Progress (IP) Satisfactory 2023-05-22
Monitoring and Evaluation Moderately Satisfactory 2023-05-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-28-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-16-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualityModestN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Score on composite index for tracking changes in the enabling environment for reducing deforestation and forest degradationValue0.350.550.55
    DateMarch 31, 2017June 30, 2023April 11, 2022
    Comment
  • Incentives (policy, laws, regulations, markets)Value0.370.370.45
    DateMarch 31, 2017May 16, 2018
    Comment
  • Information (generation and dissemination of information)Value0.350.350.43
    DateMarch 31, 2017May 16, 2018
    Comment
  • Institutions (capacity to implement & coordinate)Value0.330.330.41
    DateMarch 31, 2017May 16, 2018
    Comment
  • Area reforestedValue0.009673.009000.00
    DateMarch 31, 2017June 30, 2023June 30, 2022
    Comment
  • Direct project beneficiariesValue0.0025000.0025000.00
    DateMarch 31, 2017June 30, 2023June 30, 2022
    Comment
  • Female beneficiariesValue0.008.0020.00
    DateMarch 31, 2017May 16, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Forest area brought under management plansValue0.00120000.000.00
    DateMarch 31, 2017June 30, 2023
    Comment
  • Reforms in forest policy, legislation or other regulations supportedValueNoYes
    DateMarch 31, 2017June 30, 2023
    Comment
  • Forest users trainedValue0.0025000.000.00
    DateMarch 31, 2017June 30, 2023
    Comment
  • Grievances registered related to delivery of project benefits addressedValue0.00100.000.00
    DateMarch 31, 2017June 30, 2023
    Comment
  • MRV system established and maintained at national and Oromia levelsValueNoYes
    DateMarch 31, 2017June 30, 2023
    Comment
  • Forest users trained - FemaleValue0.007500.000.00
    DateMarch 31, 2017June 30, 2023
    Comment
  • Benefit Sharing Mechanism (BSM) approvedValueNoYes
    DateMarch 31, 2017June 30, 2023
    Comment
  • Land users adopting sustainable land mgt. practices as a result of the projectValue0.0018000.000.00
    DateMarch 31, 2017June 30, 2023
    Comment
  • Safeguards system established and maintainedValueNoYes
    DateMarch 31, 2017June 30, 2023
    Comment
  • Land users adopting sustainable land management practices as a result of the project - FemaleValue0.000.000.00
    Date
    Comment
  • Beneficiaries that feel project investments reflected their needsValue0.0090.000.00
    DateMarch 31, 2017June 30, 2023
    Comment
  • Beneficiaries that feel project inv. reflected their needs - femaleValue0.000.000.00
    Date
    Comment
  • Beneficiaries that feel project inv. reflected their needs - maleValue0.000.000.00
    Date
    Comment
  • Total beneficiaries - femaleValue0.002054.000.00
    Date
    Comment
  • Total beneficiaries - maleValue0.0016754.000.00
    Date