Water and Sanitation Development Project

Abstract*

The development objective of Water and Sanitation Development Project is to improve water supply and sanitation services in select coastal and northeastern regions in Kenya. This project has four components. 1) The first component, Rehabilitation and expansion of urban water supply and sanitation services in the coastal region, has the following subcomponents: (i) Support to coastal counties; and (ii) Support to the coast bulk water services provider...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve water supply and sanitation services in select coastal and northeastern regions in Kenya and improve the financial performance of water service providers affected by the COVID-19 pandemic.

Key Details

Project Details

  • P156634

  • Active

  • Lewnida Sara , Pascaline Ndungu

  • Government of the Republic of Kenya

  • Kenya

  • March 1, 2017

  • (as of board presentation)

    April 26, 2017

  • March 9, 2018

  • US$ 330.00 million

  • Garissa Water and Saniation Company,Wajir Water and Sewerage Company,Coast Water Works Development Agency,Kilifi - Mariakani Water and Sewerage Company Ltd,Malindi Water and Sewerage Company Ltd,Kwale Water and Sewerage Company Ltd.,Ministry of Water, Sanitation and Irrigation,Mombasa Water and Sanitation Services Company,Water Services Regulatory Board,Tavevo Water and Sewerage Company Ltd,Water Sector Trust Fund,Northern Water Works Development Agency

  • Eastern and Southern Africa

  • 2017

  • US$ 300.00 million

  • B

  • April 24, 2024

  • October 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 300.00
Borrower/Recipient 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 300.00
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 330.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 22, 2021 IDA-60300 Loan Disb 402,837.97
Jul 1, 2021 IDA-60300 Loan Disb 913,385.94
Mar 18, 2022 IDA-60300 Loan Disb 687,876.00
Jun 3, 2021 IDA-60300 Loan Disb 3,730,587.00
Jun 15, 2021 IDA-60300 Loan Disb 961,846.56
May 25, 2021 IDA-60300 Loan Disb 20,330,318.00
Feb 16, 2021 IDA-60300 Int Charges 27,406.69
Feb 16, 2021 IDA-60300 Int Charges 328,685.25
Feb 16, 2021 IDA-60300 Int Charges 457,875.30
Feb 15, 2023 IDA-60300 Int Charges 48,012.27
Feb 15, 2023 IDA-60300 Int Charges 151,085.05
Feb 15, 2023 IDA-60300 Int Charges 2,074,948.60
Feb 2, 2023 IDA-60300 Loan Disb 299,951.40
Jan 31, 2023 IDA-60300 Loan Disb 956,273.60
Mar 27, 2023 IDA-60300 Loan Disb 180,128.55
Sep 12, 2022 IDA-60300 Loan Disb 428,335.62
Dec 14, 2022 IDA-60300 Loan Disb 612,219.70
Dec 8, 2022 IDA-60300 Loan Disb 8,536,699.00
Dec 9, 2022 IDA-60300 Loan Disb 31,004,274.00
Sep 9, 2022 IDA-60300 Loan Disb 511,438.06
Nov 22, 2022 IDA-60300 Loan Disb 1,589,950.10
Aug 15, 2022 IDA-60300 Int Charges 19,749.47
Nov 14, 2022 IDA-60300 Loan Disb 468,364.47
Dec 29, 2021 IDA-60300 Loan Disb 5,410,831.00
Jan 10, 2022 IDA-60300 Loan Disb 184,334.83
Jan 25, 2022 IDA-60300 Loan Disb 1,361,241.20
Aug 15, 2022 IDA-60300 Int Charges 183,958.64
Aug 15, 2022 IDA-60300 Int Charges 1,444,771.20
Dec 6, 2021 IDA-60300 Loan Disb 1,282,522.00
Aug 15, 2024 IDA-60300 Int Charges 34,526.65
Aug 15, 2024 IDA-60300 Int Charges 56,100.02
Aug 15, 2024 IDA-60300 Int Charges 3,249,625.80
Dec 1, 2023 IDA-60300 Loan Disb 1,556,442.60
Dec 8, 2023 IDA-60300 Loan Disb 879,971.50
Dec 7, 2023 IDA-60300 Loan Disb 24,008,770.00
Aug 15, 2023 IDA-60300 Int Charges 1,326.92
Aug 15, 2023 IDA-60300 Int Charges 104,903.46
Aug 15, 2023 IDA-60300 Int Charges 2,659,717.20
Sep 19, 2023 IDA-60300 Loan Disb 417,876.12
Sep 19, 2023 IDA-60300 Loan Disb 516,342.66
Jun 6, 2023 IDA-60300 Loan Disb 1,494,387.40
Dec 12, 2022 IDA-60300 Loan Disb 12,470,685.00
Feb 15, 2024 IDA-60300 Int Charges 86,553.08
Feb 15, 2024 IDA-60300 Int Charges 2,781,881.20
Jan 2, 2024 IDA-60300 Loan Disb 11,082,704.00
Apr 26, 2017 IDA-60290 Loan Commitment 37,000,000.00
Apr 26, 2017 IDA-60300 Loan Commitment 263,000,000.00
Aug 14, 2020 IDA-60300 Loan Disb 4,089,911.20
Oct 2, 2020 IDA-60300 Loan Disb 955,110.80
Jun 19, 2020 IDA-60300 Loan Disb 6,172,615.00
Feb 26, 2020 IDA-60300 Loan Disb 493,238.56
Apr 30, 2020 IDA-60300 Loan Disb 918,482.56
Feb 18, 2020 IDA-60300 Int Charges 18,750.98
Feb 18, 2020 IDA-60300 Int Charges 323,415.20
Feb 18, 2020 IDA-60300 Int Charges 163,806.16
Dec 20, 2019 IDA-60300 Loan Disb 1,020,348.75
May 7, 2020 IDA-60300 Loan Disb 2,266,320.00
Sep 13, 2019 IDA-60300 Loan Disb 951,707.20
Apr 13, 2022 IDA-60300 Loan Disb 11,505,611.00
Jan 3, 2022 IDA-60300 Loan Disb 503,185.56
Jun 28, 2022 IDA-60300 Loan Disb 1,637,710.50
Mar 3, 2022 IDA-60300 Loan Disb 801,156.56
Mar 22, 2022 IDA-60300 Loan Disb 2,526,370.50
Jun 21, 2022 IDA-60300 Loan Disb 323,213.10
Feb 15, 2022 IDA-60300 Int Charges 9,180.26
Feb 15, 2022 IDA-60300 Int Charges 235,944.69
Feb 15, 2022 IDA-60300 Int Charges 1,320,969.00
Jun 24, 2022 IDA-60300 Loan Disb 8,752,277.00
Aug 15, 2021 IDA-60300 Int Charges 112,629.19
Aug 15, 2021 IDA-60300 Int Charges 268,534.47
Aug 15, 2021 IDA-60300 Int Charges 1,054,294.90
Jul 6, 2022 IDA-60300 Loan Disb 2,828,201.00
Jun 22, 2021 IDA-60300 Loan Disb 283,700.84
Sep 30, 2019 IDA-60300 Loan Disb 509,481.40
Apr 16, 2019 IDA-60300 Loan Disb 736,603.06
Mar 1, 2019 IDA-60300 Loan Disb 1,041,693.06
Feb 26, 2019 IDA-60300 Int Charges 353,954.10
Feb 26, 2019 IDA-60300 Int Charges 10,524.42
Aug 30, 2019 IDA-60300 Int Charges 4,723.21
Aug 30, 2019 IDA-60300 Int Charges 331,948.30
Aug 30, 2019 IDA-60300 Int Charges 68,205.10
Jun 27, 2019 IDA-60300 Loan Disb 5,689,500.00
Jan 22, 2019 IDA-60300 Loan Disb 1,022,310.00
Aug 27, 2018 IDA-60300 Int Charges 709,492.06
Aug 27, 2018 IDA-60300 Int Charges 8,893.72
Jan 18, 2019 IDA-60300 Loan Disb 1,633,733.00
Mar 9, 2018 IDA-60300 Loan Disb 762,814.44
Mar 9, 2018 IDA-60300 Fee Charges 762,814.44
Jun 7, 2021 IDA-60300 Loan Disb 9,589,225.00
Dec 21, 2020 IDA-60300 Loan Disb 29,958,628.00
Sep 4, 2020 IDA-60300 Loan Disb 746,549.30
Mar 10, 2021 IDA-60300 Loan Disb 926,871.75
May 28, 2020 IDA-60300 Loan Disb 497,199.94
Aug 15, 2020 IDA-60300 Int Charges 4,304.82
Aug 15, 2020 IDA-60300 Int Charges 341,073.66
Aug 15, 2020 IDA-60300 Int Charges 238,466.10
Jul 10, 2024 IDA-60290 Loan Disb 691,973.90
Jul 10, 2024 IDA-60290 Loan Disb 666,066.00
Apr 23, 2024 IDA-60290 Loan Disb 396,507.70
Aug 15, 2024 IDA-60290 Loan Repay 806,422.90
Mar 11, 2024 IDA-60290 Loan Cancel 19,234,080.00
Mar 26, 2024 IDA-60290 Loan Disb 247,778.34
Mar 26, 2024 IDA-60290 Loan Disb 646,230.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Unsatisfactory 2025-02-18
Project Management Moderately Satisfactory 2025-02-18
Monitoring and Evaluation Moderately Satisfactory 2025-02-18
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-18
Progress towards achievement of PDO Moderately Satisfactory 2025-02-18
Procurement Moderately Satisfactory 2025-02-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People in urban areas provided with access to Improved Water Sources under the projectValue0.003550.0074300.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • WSPs benefiting from the CLSG that demonstrate an increase in their OCCR by 2022 compared with 2019 (annual average).Value0.000.0077.00
    DateJune 2, 2020January 25, 2024August 30, 2024
    Comment
  • People benefiting under the project from a connection to the sewage system or from improved septic sludge management.Value0.000.00130000.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • People with existing connections benefiting from more hours per day of water services.Value0.000.001930000.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Direct project beneficiariesValue0.003550.002030200.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Female beneficiariesValue0.000.0050.00
    DateApril 26, 2017June 30, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Piped household water connections that are benefiting from rehabilitation works undertaken under the project.Value0.00710.0015500.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Guidelines for results-based financing adoptedValueNoYesYes
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Improved community water points constructed or rehabilitated under the projectValue0.000.0037.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • New piped household water connections under the project.Value0.000.0011900.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • New water supplied to northeastern WSPs under the project (m3/day).Value0.000.007600.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Additional Water delivered by WSPs to customers due to project interventions (as reflected in water bills)Value39.3039.3044.50
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Complaints handling system (Maji Voice) established in WSPs supported under the project.Value0.000.002.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Gender action plans developed and under implementation.Value0.001.002.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • People provided with access to improved shared sanitation facilities under the project.Value0.000.007050.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Average performance score for WSPs receiving the CLSGValue0.000.0051.00
    DateJune 2, 2020January 25, 2024August 30, 2024
    Comment
  • People provided with access to improved shared sanitation facilitiesValue0.000.0013650.00
    DateJuly 20, 2016January 25, 2024August 30, 2024
    Comment
  • Volume of biological oxygen demand pollution loads removed by treatment plants supported under the project.Value0.000.001600.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Hours of service per day provided by coastal WSPs benefiting from the project.Value10.0011.0012.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Non-revenue water (% of water that a service provider supplies to its distribution system that is not reflected in revenues).Value50.0050.0043.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Operations and maintenance costs of coastal WSPs benefiting from the project recovered from customers.Value90.0065.00100.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment
  • Septic sludge treatment facilities constructed under the projectValue0.000.002.00
    DateApril 26, 2017January 25, 2024August 30, 2024
    Comment