Financier | Commitments |
---|---|
IDA Credit | 300.00 |
P156777
Closed
Beatriz Eraso Puig , Davison Muchadenyika
Republic of Kenya
June 6, 2016
(as of board presentation)
July 26, 2017
January 11, 2018
US$ 300.00 million
Ministry of Lands, Public Works, Housing, and Urban Development
2018
US$ 300.00 million
C
June 18, 2024
December 31, 2023
No
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 300.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 300.00 |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 300.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2024 | IDA-61340 | Int Charges | 1,735,897.00 |
Feb 15, 2024 | IDA-61340 | Int Charges | 1,735,897.00 |
Feb 15, 2024 | IDA-61340 | Int Charges | 1,873,666.60 |
Jun 18, 2024 | IDA-61340 | Loan Disb | -8,215.49 |
Jun 18, 2024 | IDA-61340 | Loan Disb | -166.61 |
Aug 15, 2024 | IDA-61340 | Loan Repay | 4,801,132.00 |
Aug 15, 2024 | IDA-61340 | Int Charges | 1,705,947.00 |
Aug 15, 2024 | IDA-61340 | Int Charges | 1,705,947.00 |
Aug 15, 2024 | IDA-61340 | Int Charges | 1,841,339.80 |
May 8, 2024 | IDA-61340 | Loan Disb | -41.24 |
Feb 15, 2023 | IDA-61340 | Loan Repay | 4,950,000.00 |
Feb 15, 2023 | IDA-61340 | Int Charges | 1,765,944.50 |
Feb 15, 2023 | IDA-61340 | Int Charges | 1,765,944.50 |
Feb 15, 2023 | IDA-61340 | Int Charges | 1,906,098.90 |
Sep 19, 2023 | IDA-61340 | Loan Disb | 3,411,020.00 |
Jul 10, 2023 | IDA-61340 | Loan Cancel | 8,575,695.00 |
Aug 15, 2023 | IDA-61340 | Loan Repay | 4,950,000.00 |
Aug 15, 2023 | IDA-61340 | Int Charges | 1,748,080.50 |
Aug 15, 2023 | IDA-61340 | Int Charges | 1,748,080.50 |
Aug 15, 2023 | IDA-61340 | Int Charges | 1,886,817.00 |
Sep 8, 2022 | IDA-61340 | Loan Disb | 2,529,620.80 |
Mar 7, 2023 | IDA-61340 | Loan Disb | 2,040,607.80 |
Feb 15, 2022 | IDA-61340 | Int Charges | 122,569.62 |
Feb 15, 2022 | IDA-61340 | Int Charges | 1,774,435.50 |
Feb 15, 2022 | IDA-61340 | Int Charges | 1,774,435.50 |
Feb 15, 2022 | IDA-61340 | Int Charges | 1,915,263.60 |
Aug 15, 2022 | IDA-61340 | Int Charges | 1,781,505.60 |
Aug 15, 2022 | IDA-61340 | Int Charges | 1,781,505.60 |
Aug 15, 2022 | IDA-61340 | Int Charges | 1,922,894.90 |
Aug 15, 2022 | IDA-61340 | Loan Repay | 4,950,000.00 |
Mar 25, 2022 | IDA-61340 | Loan Disb | 1,231,201.80 |
Sep 9, 2021 | IDA-61340 | Loan Disb | 1,234,835.50 |
Aug 15, 2021 | IDA-61340 | Int Charges | 1,593,989.40 |
Aug 15, 2021 | IDA-61340 | Int Charges | 1,590,341.50 |
Aug 15, 2021 | IDA-61340 | Int Charges | 1,590,341.50 |
Jun 30, 2021 | IDA-61340 | Loan Disb | 37,425,836.00 |
Jun 23, 2020 | IDA-61340 | Loan Disb | 102,368,808.00 |
Aug 19, 2020 | IDA-61340 | Loan Disb | 957,596.20 |
Aug 15, 2020 | IDA-61340 | Int Charges | 1,054,814.90 |
Aug 15, 2020 | IDA-61340 | Int Charges | 1,054,814.90 |
Aug 15, 2020 | IDA-61340 | Int Charges | 751,121.25 |
Mar 4, 2021 | IDA-61340 | Loan Disb | 774,018.10 |
Feb 15, 2021 | IDA-61340 | Int Charges | 387,409.06 |
Feb 15, 2021 | IDA-61340 | Int Charges | 1,526,900.10 |
Feb 15, 2021 | IDA-61340 | Int Charges | 1,526,900.10 |
Feb 15, 2021 | IDA-61340 | Int Charges | 1,648,082.60 |
Feb 15, 2020 | IDA-61340 | Int Charges | 921,081.90 |
Feb 15, 2020 | IDA-61340 | Int Charges | 853,355.25 |
Feb 15, 2020 | IDA-61340 | Int Charges | 853,355.25 |
Apr 15, 2020 | IDA-61340 | Loan Disb | 3,606,748.80 |
Mar 7, 2019 | IDA-61340 | Int Charges | 430,353.06 |
Mar 7, 2019 | IDA-61340 | Int Charges | 430,353.06 |
Mar 7, 2019 | IDA-61340 | Int Charges | 464,508.06 |
Mar 7, 2019 | IDA-61340 | Int Charges | 11,819.97 |
Mar 7, 2019 | IDA-61340 | Int Charges | 11,819.97 |
Mar 7, 2019 | IDA-61340 | Int Charges | 55,645.02 |
Aug 30, 2019 | IDA-61340 | Int Charges | 853,355.25 |
Aug 30, 2019 | IDA-61340 | Int Charges | 853,355.25 |
Aug 30, 2019 | IDA-61340 | Int Charges | 921,081.90 |
Jun 27, 2018 | IDA-61340 | Loan Disb | 9,000,000.00 |
Jun 20, 2018 | IDA-61340 | Loan Disb | 9,000,000.00 |
Aug 27, 2018 | IDA-61340 | Int Charges | 1,705.01 |
Aug 27, 2018 | IDA-61340 | Int Charges | 1,705.01 |
Aug 27, 2018 | IDA-61340 | Int Charges | 1,840.32 |
Aug 27, 2018 | IDA-61340 | Int Charges | 39,733.51 |
Aug 27, 2018 | IDA-61340 | Int Charges | 39,733.51 |
Dec 3, 2018 | IDA-61340 | Loan Disb | 111,905,360.00 |
Jan 11, 2018 | IDA-61340 | Loan Disb | 1,432,782.20 |
Jun 5, 2018 | IDA-61340 | Loan Disb | 4,115,084.00 |
Jul 26, 2017 | IDA-61340 | Loan Commitment | 300,000,000.00 |
May 13, 2024 | IDA-61340 | Loan Disb | -1,163,071.80 |
Feb 15, 2024 | IDA-61340 | Loan Repay | 4,801,132.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2023-12-11 |
Monitoring and Evaluation | Satisfactory | 2023-12-11 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-12-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-18-2024 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 10-07-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Urban areas that utilize at least 50 percent of the budget intended for their urban investments | Value | 0.00 | 17.00 | 0.00 |
Date | July 31, 2017 | December 31, 2023 | ||
Comment |
Urban areas that have an approved Annual Investment Plan and Urban Area plans | Value | 0.00 | 15.00 | 0.00 |
Date | July 31, 2017 | December 31, 2023 | ||
Comment |
Urban areas with approved charters, established boards, appointed urban managers, and a budget vote (measures establishment of urban institutions). | Value | 0.00 | 35.00 | 0.00 |
Date | July 26, 2017 | December 31, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Counties that qualify for the UIGs | Value | 0.00 | 45.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Guidelines on planning, infrastructure, and basic service delivery prepared and made public on MTIHUD website | Value | 0.00 | 6.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
People provided with improved urban living conditions (million) | Value | 0.00 | 3.50 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Urban areas for which citizen fora (public consultations between urban board and residents, including plan and budget consultations) have been held at least once a year. | Value | 0.00 | 35.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
APA results (UIG and UDG allocations) made on time (before end of FY and prior to start of next FY) | Value | No | Yes | |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
1.a. People provided with improved urban living conditions (of which female, [percentage]) | Value | 0.00 | 50.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
UDGs for the previous FY spent in accordance with the eligible investment menu | Value | 0.00 | 90.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Drainage systems built or rehabilitated under the progarm | Value | 0.00 | 10.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Nonmotorized transport facilities constructed or rehabilitated under the program | Value | 0.00 | 100.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
High-mast security lights installed under the program | Value | 0.00 | 30.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Markets constructed under the program | Value | 0.00 | 4.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Public green urban spaces constructed or rehabilitated under the program | Value | 0.00 | 10.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Municipal solid waste policies and plans prepared under the program adopted | Value | 0.00 | 10.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Urban spatial plans completed under the program | Value | 0.00 | 8.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Urban IDEPs completed under the program | Value | 0.00 | 35.00 | 0.00 |
Date | July 6, 2017 | December 31, 2023 | ||
Comment |
Roads constructed or rehabilitated under the program | Value | 0.00 | 100.00 | 0.00 |
Date | June 17, 2021 | December 31, 2023 | ||
Comment |
Street lights installed under the program | Value | 0.00 | 1000.00 | 0.00 |
Date | June 17, 2021 | December 31, 2023 | ||
Comment |